P10 – Pipeline 2500Ø: Piloting work at Lebuh Tun Hussein Onn in progress.
P10 – Inlet Portal: Soil nailing works at LHS slope in progress.
P10 – Inlet Portal: Excavation work at CH18.375 in progress.
P10 – Pipeline 2500 Ø: Pipe laying works at CH2906.8 – CH2914.8 in progress.
P10 – Pipeline 2500 Ø: Welding of external joint for S-bend overcrossing no.4 in progress.
P10 – Pipeline 2500 Ø: Pipe laying work at CH9015.61 – CH9030.21 in progress.
P10 – General: Quarterly risk management meeting no.02/2018 at Langat 2 conference room.
P10 – Pipeline 2500 Ø: Welding works for collar joint at CH8720 in progress.
P10 – Inlet Portal: Excavation works to expose pile heads for hacking & PIT test in progress.
Dec 18
Nov 18
Oct 18
Sep 18
Aug 18
Jul 18
Jun 18
May 18
Apr 18
Mar 18
Feb 18
Jan 18

P10 – Pipeline 2500 Ø: Pipe laying works at CH12181 – CH12176 in progress.

P10 – Inlet Portal: Trimming slope at LHS tunnel in progress.

P10 – Pipeline 2500Ø: Piloting work at Lebuh Tun Hussein Onn in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CHA765.63 – CH763.03 in progress.

P10 – Outlet Portal: Construction of interceptor drain from RL109 to RL104 in progress.

P10 – Pipeline 2500 Ø: Rock excavation at Lebuh Tun Hussein Onn in progress.

P10 – Inlet Portal: Soil nailing works at LHS slope in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH2976.80 – CH2980.21 in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH12169.3 – CH12166.3 in progress.










P10 – Inlet Portal: Grouting work area CH15.375 to CH17.375 in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH2874.8 – CH2890.8 in progress.

P10 – Inlet Portal: Excavation work at CH18.375 in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH12232 – CH12216 in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH8392 to CH8384 in progress.

P10 – Inlet Portal: Hacking boulder area at CH19.375 in progress.

P10 – Pipeline 2500 Ø: Road reinstatement in progress at Jln Permaisuri – Jln Laksamana.

P10 – Pipeline 2500 Ø: Pipe laying works at CH2906.8 – CH2914.8 in progress.

P10 – Inlet Portal: Installation of steel rib at CH20.375 in progress.










P10 – Inlet Portal: Cleaning CBP wall surface prior to safety shotcreting works in progress.

P10 – Rivercrossing: Fixing of saddle support for overcrossing steel truss in progress.

P10 – Pipeline 2500 Ø: Internal welding works at CH2709.27 in progress.

P10 – Pipeline 2500 Ø: Welding of external joint for S-bend overcrossing no.4 in progress.

P10 – Inlet Portal: Drilling and installation of pipe arch for point no. 15 & 16 in progress.

P10 – Pipeline 2500 Ø: Pipe laying work at CH12549.3 – CH12551.9 in progress.

P10 – Inlet Portal: Shotcreting for steel rib no.2 at CH13.375 in progress.

P10 – Pipeline 2500 Ø: Site visit and briefing with MPKJ and resident at Lebuh Tun Hussein Onn.

P10 – Inlet Portal: Hacking of boulder to install steel rib no.3 in progress.

P10 – Inlet Portal: Installation of steel galvanized soil nails at RHS wall in progress.

P10 – Pipeline 2500 Ø: Pipe laying work at CH9015.61 – CH9030.21 in progress.

P10 – Pipeline 2500 Ø: Pipe laying work at CH1444.36 – CH1447.86 in progress.

P10 – Pipeline 2500 Ø: Pipe laying work at CH2717.27 – CH2733.27 in progress.














P10 – Pipeline 2500 Ø: Pipe delivery at storage yard Mahkota Cheras 3 in progress

P10 – Pipeline 2500 Ø: Pipe laying works at CH.2766 – CH.2774 in progress

P10 – Pipeline 2500 Ø: Fabrication shortpiece & bend 45ᵒ (Overcrossing no.4) in progress.

P10 – Pipeline 2500 Ø: Internal welding works at CH.2766 in progress.

P10 – Inlet Portal: Shotcreting works at RL.91 – RL.88.8 in progress.

P10 – Pipeline 2500 Ø: Site visit & discussion with TNB representative at JDC in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH.2652.07 – CH.2660.07 in progress.

P10 – Pipeline 2500 Ø: Sand blasting inspection at Bukit Kemuning in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH.12481.70 – CH.12489.70 in progress.

P10 – Inlet Portal: Shotcreting works for wall & tunnel face Inlet Portal in progress.

P10 – Inlet Portal: Shotcreting works at cascade drain at LHS in progress.

P10 – Inlet Portal: Cleaning surface concrete at canopy RC slab tunnel in progress.

P10 – Pipeline 2500 Ø: Pipe laying works (Overcrossing no.4) at CH1430 – CH1437 in progress.

P10 – Inlet Portal: Hacking boulder below tunnel canopy in progress.















P10 – Pipeline 2500 Ø: Wrapping works to welded joint at CH2593 in progress.

P10 – Pipeline 2500 Ø: Meeting within TNB, PAAB, RCSB, SMHB and PIMSB in progress.

P10 – Inlet Portal: Shotcreting works for canopy RC slab & critical slope area in progress

P10 – Pipeline 2500 Ø: Pipe laying works at CH12358 – CH12366 in progress.

P10 – Pipeline 2500 Ø: Pipe laying works (Bend 15ᵒ) at CH12368 – CH12369 in progress.

P10 – Inlet Portal: Construction of capping beam in progress.







P10 – Pipeline 2500 Ø: Meeting with MPKJ regarding interfacing works at Mahkota Cheras

P10 – Pipeline 2500 Ø: Site clearing at Kg. Pinang CH12325 – CH12400 in progress.

P10 – Inlet Portal: Installation of weepholes at retaining wall in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH2490.48 – CH2498.26 in progress.

P10 – Pipeline 2500 Ø: Installation of air valve tee at CH2497.06 – CH2499.66 in progress.

P10 – Pipeline 2500 Ø: Pipe laying for overcrossing no.3 at CH838.67 – CH828.01 in progress

P10 – Pipeline 2500 Ø: Construction of thrust block at CH8456 in progress.

P10 – Inlet Portal: Preparation of access and drainage system at Inlet Portal in progress.









P10 – Authority: Site visit & serving eviction notices at Kg. Pinang with PTG and DBKL.

P10 – Pipeline 2500 Ø: Pipe laying works at CH832.29 – CH835.29 in progress.

P10 – Pipeline 2500 Ø: Backfilling works with sand at CH808.29 – CH816.29 in progress.

P10 – Pipeline 2500 Ø: Fabrication for S-Bend no.3 (VB 45ᵒ painted) in progress.

P10 – Inlet Portal: Installation of filter material for weepholes at retaining wall in progress.

P10 – General: Quarterly risk management meeting no.02/2018 at Langat 2 conference room.

P10 – Pipeline 2500 Ø: Backfilling with sand at CH2435.10 – CH2427.10 in progress.

P10 – Pipeline 2500 Ø: Backfilling with sand at CH2435.10 – CH2427.10 in progress.
P10 – Pipeline 2500 Ø: Soil investigation works at jacking pit CH2543 in progress.

P10 – Inlet Portal: Backfilling works at retaining wall area in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH2427.10 – CH2419.10 in progress.

P10 – Pipeline 2500 Ø: Welding works for collar joint at CH8720 in progress.

P10 – Inlet Portal: Excavation works to expose pile heads for hacking & PIT test in progress.













P10 – Pipeline 2500Ø: Fabrication of 45˚bend and washout tee at CH8517 in progress.

P10 – Pipeline 2500Ø: Pipe laying works at CH1973.245 – CH1981.245 in progress.

P10 – Inlet Portal: Concreting works for CBP wall (point.13) in progress.

P10 – Pipeline 2500Ø: Pipe laying works at CH780.69 – CH788.69 in progress.

P10 – Pipeline 2500Ø: Pipe laying works at CH943.5 – CH941.5 in progress.

P10 – Inlet Portal: Backfilling works at retaining wall area in progress.







P10 – Inlet Portal : Installation of steelcage for CBP Wall (Point.9) in progress.

P10 – Inlet Portal : Concreting works for CBP Wall (Point.9) in progress.

P10 – Pipeline 2500Ø: Pipe laying works at CH990 – CH982 in progress.

P10 – Pipeline 2500Ø: External welding works at CH990 in progress.

P10 – Pipeline 2500Ø: Pipe laying works at CH732.69 – CH740.69 in progress.

P10 – Pipeline 2500Ø: Pipe laying works at CH2004 – CH2012 in progress.

P10 – Inlet Portal : Backfilling to retaining wall in progress.

P10 – Inlet Portal : Concreting works for CBP Wall (Point.15) in progress.









P10 – Pipeline 2500Ø: Jointing of short piece and bend in progress (Persiaran Mahkota Cheras)

P10 – Pipeline 2500Ø: Pipe laying (CH1046 – CH1038) at Persiaran Mahkota Cheras in progress.

P10 –Pipeline 2500Ø: Pipe laying (CH1662 – CH1678) at Persiaran Mahkota Cheras in progress.

P10 – Inlet Portal: Earthworks in progress.

P10 – Inlet Portal: Concreting Work in Progress for CBP Point No. 7.

P10 – Pipeline 2500Ø: Pipe laying (CH694 – CH697) at Persiaran Mahkota Cheras in progress.







P10 – Pipeline 2500Ø: Factory inspection for pipes (ALLPIPES) in progress.

P10 – Pipeline 2500Ø: Rock excavation at CH523 in progress.

P10 – Pipeline 2500Ø: Pipe laying works at CH8619 – CH8611 in progress.

P10 – Pipeline 2500Ø: Pipe delivery at Mahkota Cheras in progress.

P10 – Inlet Portal: Drilling works for CBP Wall (Point.24 in progress).

P10 – HSSE: Safety walkabout in progress.

P10 – HSSE: Safety walkabout meeting in progress.

P10 – Pipeline 2500Ø: Driving sheet pile for pipe trench at CH8611 – CH8603 in progress.

P10 – Inlet Portal: Installation steelcage for CBP wall point.24 in progress.

P10 – Pipeline 2500Ø: Pipe laying works at CH1879 – CH1887 in progress.

P10 – Inlet Portal: Concreting works for CBP wall point.24 in progress.

P10 – Pipeline 2500Ø: Pipe laying works at CH8611 – CH8603 in progress.













P10 – Pipe Jacking 2500Ø: Delivery of jacking pipes at contractor’s storage yard in progress.

P10 – Pipeline 2500Ø: Welding works for HB 30’ at CH439 in progress.

P10 – Rivercrossing: Erecting rebar for pier at CH8423 in progress.

P10 – Pipeline 2500Ø: Air pressure test at CH8488 in progress.

P10 – Pipeline 2500Ø: Pipe laying works at CH439– CH449 in progress.

P10 – HSSE: Toolbox Meeting at jacking pit CH2300.

P10 – Pipeline 2500Ø: Pipe laying works at CH8638 – CH8630 in progress.

P10 – Pipe Jacking 2500Ø: Material inspection in progress at CH3500.

P10 – Inlet Portal Drilling works for CBP wall (pt.28) in progress.

P10 – Pipe Jacking 2500Ø: Excavation works for jacking pit at CH2300 in progress.

P10 – Pipeline 2500Ø: Pipe laying works at CH1342 – CH1334 in progress.

P10 – Pipeline 2500Ø: Fabrication works for PE pipe & bend 30’ in progress.