Open Menu
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Pakej 10 : Paip Air Terawat Utama dari Kolam Air Imbangan Bukit Enggang ke Lebuhraya Sg. Besi 2018
print
2020
2019
2018
2017
2016
Dec 18
Nov 18
Oct 18
Sep 18
Aug 18
Jul 18
Jun 18
May 18
Apr 18
Mar 18
Feb 18
Jan 18
P10 – Pipeline 2500 Ø: Pipe laying works at CH12181 – CH12176 in progress.
P10 – Inlet Portal: Trimming slope at LHS tunnel in progress.
P10 – Pipeline 2500Ø: Piloting work at Lebuh Tun Hussein Onn in progress.
P10 – Pipeline 2500 Ø: Pipe laying works at CHA765.63 – CH763.03 in progress.
P10 – Outlet Portal: Construction of interceptor drain from RL109 to RL104 in progress.
P10 – Pipeline 2500 Ø: Rock excavation at Lebuh Tun Hussein Onn in progress.
P10 – Inlet Portal: Soil nailing works at LHS slope in progress.
P10 – Pipeline 2500 Ø: Pipe laying works at CH2976.80 – CH2980.21 in progress.
P10 – Pipeline 2500 Ø: Pipe laying works at CH12169.3 – CH12166.3 in progress.
P10 – Inlet Portal: Grouting work area CH15.375 to CH17.375 in progress.
P10 – Pipeline 2500 Ø: Pipe laying works at CH2874.8 – CH2890.8 in progress.
P10 – Inlet Portal: Excavation work at CH18.375 in progress.
P10 – Pipeline 2500 Ø: Pipe laying works at CH12232 – CH12216 in progress.
P10 – Pipeline 2500 Ø: Pipe laying works at CH8392 to CH8384 in progress.
P10 – Inlet Portal: Hacking boulder area at CH19.375 in progress.
P10 – Pipeline 2500 Ø: Road reinstatement in progress at Jln Permaisuri – Jln Laksamana.
P10 – Pipeline 2500 Ø: Pipe laying works at CH2906.8 – CH2914.8 in progress.
P10 – Inlet Portal: Installation of steel rib at CH20.375 in progress.
P10 – Inlet Portal: Cleaning CBP wall surface prior to safety shotcreting works in progress.
P10 – Rivercrossing: Fixing of saddle support for overcrossing steel truss in progress.
P10 – Pipeline 2500 Ø: Internal welding works at CH2709.27 in progress.
P10 – Pipeline 2500 Ø: Welding of external joint for S-bend overcrossing no.4 in progress.
P10 – Inlet Portal: Drilling and installation of pipe arch for point no. 15 & 16 in progress.
P10 – Pipeline 2500 Ø: Pipe laying work at CH12549.3 – CH12551.9 in progress.
P10 – Inlet Portal: Shotcreting for steel rib no.2 at CH13.375 in progress.
P10 – Pipeline 2500 Ø: Site visit and briefing with MPKJ and resident at Lebuh Tun Hussein Onn.
P10 – Inlet Portal: Hacking of boulder to install steel rib no.3 in progress.
P10 – Inlet Portal: Installation of steel galvanized soil nails at RHS wall in progress.
P10 – Pipeline 2500 Ø: Pipe laying work at CH9015.61 – CH9030.21 in progress.
P10 – Pipeline 2500 Ø: Pipe laying work at CH1444.36 – CH1447.86 in progress.
P10 – Pipeline 2500 Ø: Pipe laying work at CH2717.27 – CH2733.27 in progress.
P10 – Pipeline 2500 Ø: Pipe delivery at storage yard Mahkota Cheras 3 in progress
P10 – Pipeline 2500 Ø: Pipe laying works at CH.2766 – CH.2774 in progress
P10 – Pipeline 2500 Ø: Fabrication shortpiece & bend 45ᵒ (Overcrossing no.4) in progress.
P10 – Pipeline 2500 Ø: Internal welding works at CH.2766 in progress.
P10 – Inlet Portal: Shotcreting works at RL.91 – RL.88.8 in progress.
P10 – Pipeline 2500 Ø: Site visit & discussion with TNB representative at JDC in progress.
P10 – Pipeline 2500 Ø: Pipe laying works at CH.2652.07 – CH.2660.07 in progress.
P10 – Pipeline 2500 Ø: Sand blasting inspection at Bukit Kemuning in progress.
P10 – Pipeline 2500 Ø: Pipe laying works at CH.12481.70 – CH.12489.70 in progress.
P10 – Inlet Portal: Shotcreting works for wall & tunnel face Inlet Portal in progress.
P10 – Inlet Portal: Shotcreting works at cascade drain at LHS in progress.
P10 – Inlet Portal: Cleaning surface concrete at canopy RC slab tunnel in progress.
P10 – Pipeline 2500 Ø: Pipe laying works (Overcrossing no.4) at CH1430 – CH1437 in progress.
P10 – Inlet Portal: Hacking boulder below tunnel canopy in progress.
P10 – Pipeline 2500 Ø: Wrapping works to welded joint at CH2593 in progress.
P10 – Pipeline 2500 Ø: Meeting within TNB, PAAB, RCSB, SMHB and PIMSB in progress.
P10 – Inlet Portal: Shotcreting works for canopy RC slab & critical slope area in progress
P10 – Pipeline 2500 Ø: Pipe laying works at CH12358 – CH12366 in progress.
P10 – Pipeline 2500 Ø: Pipe laying works (Bend 15ᵒ) at CH12368 – CH12369 in progress.
P10 – Inlet Portal: Construction of capping beam in progress.
P10 – Pipeline 2500 Ø: Meeting with MPKJ regarding interfacing works at Mahkota Cheras
P10 – Pipeline 2500 Ø: Site clearing at Kg. Pinang CH12325 – CH12400 in progress.
P10 – Inlet Portal: Installation of weepholes at retaining wall in progress.
P10 – Pipeline 2500 Ø: Pipe laying works at CH2490.48 – CH2498.26 in progress.
P10 – Pipeline 2500 Ø: Installation of air valve tee at CH2497.06 – CH2499.66 in progress.
P10 – Pipeline 2500 Ø: Pipe laying for overcrossing no.3 at CH838.67 – CH828.01 in progress
P10 – Pipeline 2500 Ø: Construction of thrust block at CH8456 in progress.
P10 – Inlet Portal: Preparation of access and drainage system at Inlet Portal in progress.
P10 – Authority: Site visit & serving eviction notices at Kg. Pinang with PTG and DBKL.
P10 – Pipeline 2500 Ø: Pipe laying works at CH832.29 – CH835.29 in progress.
P10 – Pipeline 2500 Ø: Backfilling works with sand at CH808.29 – CH816.29 in progress.
P10 – Pipeline 2500 Ø: Fabrication for S-Bend no.3 (VB 45ᵒ painted) in progress.
P10 – Inlet Portal: Installation of filter material for weepholes at retaining wall in progress.
P10 – General: Quarterly risk management meeting no.02/2018 at Langat 2 conference room.
P10 – Pipeline 2500 Ø: Backfilling with sand at CH2435.10 – CH2427.10 in progress.
P10 – Pipeline 2500 Ø: Backfilling with sand at CH2435.10 – CH2427.10 in progress.
P10 – Pipeline 2500 Ø: Soil investigation works at jacking pit CH2543 in progress.
P10 – Inlet Portal: Backfilling works at retaining wall area in progress.
P10 – Pipeline 2500 Ø: Pipe laying works at CH2427.10 – CH2419.10 in progress.
P10 – Pipeline 2500 Ø: Welding works for collar joint at CH8720 in progress.
P10 – Inlet Portal: Excavation works to expose pile heads for hacking & PIT test in progress.
P10 – Pipeline 2500Ø: Fabrication of 45˚bend and washout tee at CH8517 in progress.
P10 – Pipeline 2500Ø: Pipe laying works at CH1973.245 – CH1981.245 in progress.
P10 – Inlet Portal: Concreting works for CBP wall (point.13) in progress.
P10 – Pipeline 2500Ø: Pipe laying works at CH780.69 – CH788.69 in progress.
P10 – Pipeline 2500Ø: Pipe laying works at CH943.5 – CH941.5 in progress.
P10 – Inlet Portal: Backfilling works at retaining wall area in progress.
P10 – Inlet Portal : Installation of steelcage for CBP Wall (Point.9) in progress.
P10 – Inlet Portal : Concreting works for CBP Wall (Point.9) in progress.
P10 – Pipeline 2500Ø: Pipe laying works at CH990 – CH982 in progress.
P10 – Pipeline 2500Ø: External welding works at CH990 in progress.
P10 – Pipeline 2500Ø: Pipe laying works at CH732.69 – CH740.69 in progress.
P10 – Pipeline 2500Ø: Pipe laying works at CH2004 – CH2012 in progress.
P10 – Inlet Portal : Backfilling to retaining wall in progress.
P10 – Inlet Portal : Concreting works for CBP Wall (Point.15) in progress.
P10 – Pipeline 2500Ø: Jointing of short piece and bend in progress (Persiaran Mahkota Cheras)
P10 – Pipeline 2500Ø: Pipe laying (CH1046 – CH1038) at Persiaran Mahkota Cheras in progress.
P10 –Pipeline 2500Ø: Pipe laying (CH1662 – CH1678) at Persiaran Mahkota Cheras in progress.
P10 – Inlet Portal: Earthworks in progress.
P10 – Inlet Portal: Concreting Work in Progress for CBP Point No. 7.
P10 – Pipeline 2500Ø: Pipe laying (CH694 – CH697) at Persiaran Mahkota Cheras in progress.
P10 – Pipeline 2500Ø: Factory inspection for pipes (ALLPIPES) in progress.
P10 – Pipeline 2500Ø: Rock excavation at CH523 in progress.
P10 – Pipeline 2500Ø: Pipe laying works at CH8619 – CH8611 in progress.
P10 – Pipeline 2500Ø: Pipe delivery at Mahkota Cheras in progress.
P10 – Inlet Portal: Drilling works for CBP Wall (Point.24 in progress).
P10 – HSSE: Safety walkabout in progress.
P10 – HSSE: Safety walkabout meeting in progress.
P10 – Pipeline 2500Ø: Driving sheet pile for pipe trench at CH8611 – CH8603 in progress.
P10 – Inlet Portal: Installation steelcage for CBP wall point.24 in progress.
P10 – Pipeline 2500Ø: Pipe laying works at CH1879 – CH1887 in progress.
P10 – Inlet Portal: Concreting works for CBP wall point.24 in progress.
P10 – Pipeline 2500Ø: Pipe laying works at CH8611 – CH8603 in progress.
P10 – Pipe Jacking 2500Ø: Delivery of jacking pipes at contractor’s storage yard in progress.
P10 – Pipeline 2500Ø: Welding works for HB 30’ at CH439 in progress.
P10 – Rivercrossing: Erecting rebar for pier at CH8423 in progress.
P10 – Pipeline 2500Ø: Air pressure test at CH8488 in progress.
P10 – Pipeline 2500Ø: Pipe laying works at CH439– CH449 in progress.
P10 – HSSE: Toolbox Meeting at jacking pit CH2300.
P10 – Pipeline 2500Ø: Pipe laying works at CH8638 – CH8630 in progress.
P10 – Pipe Jacking 2500Ø: Material inspection in progress at CH3500.
P10 – Inlet Portal Drilling works for CBP wall (pt.28) in progress.
P10 – Pipe Jacking 2500Ø: Excavation works for jacking pit at CH2300 in progress.
P10 – Pipeline 2500Ø: Pipe laying works at CH1342 – CH1334 in progress.
P10 – Pipeline 2500Ø: Fabrication works for PE pipe & bend 30’ in progress.