P11- Pipeline 2.5mØ: Air test for bend 85.8◦ at CH1477 in progress

P11- Pipeline 2.5mØ: Air test for pipe no.16 at CH1477 in progress

P11- Pipeline 2.5mØ: Formwork installation at CH1485 in progress

P11- Pipeline 2.5mØ: Concreting in progress for bend and pipe no.16 and 17 at CH1485.

P11- Pipeline 2.5mØ: Concreting in progress for bend at CH1485.

P11- Pipeline 2.5mØ: Concreting in progress for pipe no.16 and 17 at CH1485







P11 –Pipeline 2.5m Ø: Trench excavations in progress.

P11 –Pipeline 2.5m Ø: Site Clearing at CH1150 to CH1250 in progress.

P11 –Pipeline 2.5m Ø: Driving of sheet piles for trench excavation in progress.

P11 –Pipeline 2.5m Ø: Extracting of sheet piles in progress.

P11 –Pipeline 2.5m Ø: Installation of silt fence in progress.

P11 –Pipeline 2.5m Ø: Installation of silt fence in progress.







P11 – Sg.Kuyuh CH1350 till CH1370: Sheet piling in progress.

P11 – Sg.Kuyuh CH1350 till CH1370: Welding pipe in progress.

P11 – Sg.Kuyuh CH1350 till CH1370: Welding pipe in progress.

P11 – Sg.Kuyuh CH1350 till CH1370: Concrete surround in progress.

P11 – Sg.Kuyuh CH1350 till CH1370: Pipe delivery in progress.

P11 – Sg.Kuyuh CH1350 till CH1370: Cement lining in progress.







P11 – Sg Kuyuh: Flagman & Signalman training in progress.

P11 – Sg Kuyoh : Delivery of Crusher Run for preparing temporary access in progress.

P11 – Hutan Simpanan Air Hitam : Pegging for ROW at CH7527 to CH2700 in progress.

P11 – Hutan Simpanan Air Hitam : Pegging for ROW at CH7527 to CH2700 in progress.

P11 – Sg Kuyoh : Mobilization of machineries for pipe laying work at CH1350 in progress.

P11 – Sg Kuyoh : Mobilization of machineries for pipe laying work at CH1350 in progress.







P11 – General: Taking samples at the source of sand for material testing.

P11 – General: Material testing for sand at Revelation Soil Testing Lab, Petaling Jaya.

P11 – 2.5m Ø Pipeline: Surveying work at CH1025 @ Sungai Kuyuh in progress.

P11 – 2.5m Ø Pipeline: Surveying work at CH1250 @ Sungai Kuyuh in progress.

P11 – 2.5m Ø Pipeline: Surveying work at CH1250 @ Sungai Kuyuh in progress.