2020
2019
2018
2017
2016
Dec 17
Nov 17
Oct 17
Sep 17
Aug 17
Jul 17
Jun 17
May 17
Apr 17
Mar 17
Feb 17
Jan 17

P11 – Pipeline 2500Ø: Repairing slope (CH1650) at Sg. Kuyuh in progress.

P11 – Pipeline 2500Ø: Pipe laying works (CH5478) at PUJ 8 in progress.

P11 – Pipeline 1950Ø: Casting of Thrust Block (CH1055) at BK 6 in progress.

P11 – Pipeline 2500Ø: Casting of Thrust Block (CH1987) at Sg. Kuyuh in progress.

P11 – Pipeline 2500Ø: Casting of Anchor Block (CH1170) at DBKL/ASTRO area in progress.

P11 – Pipeline 2500Ø: Casting of Thrust Block (CH5558) at PUJ 8 in progress.

P11 – Pipeline 2500Ø: Piloting Work (CH2100) at Jalan PBS 14/7 in progress.

P11 – Pipeline 1950Ø: Sandfilling to pipeline (CH1080) at BK 6 in progress.

P11 – Pipeline 2500Ø: Excavation for Jacking Pit (CH6632) at Jalan Kinrara 6f in progress.










P11 – Pipeline 2500Ø: Formwork and Rebar Inspection at CH1266 (DBKL/ASTRO) in progress.

P11 – Pipeline 2500Ø: Pipe Laying works at CH1191 (DBKL/ASTRO) in progress.

P11 – Pipeline 2400Ø: Pipe Laying works at CH5686 (PUJ 8) in progress.

P11 – Pipeline 1950Ø: Road reinstatement works at CH1050 (BK 6) in progress.

P11 – Pipeline 2400Ø: Pipe Delivery at CH5022 (PUJ 9) in progress.

P11 – Pipeline 2500Ø: Driving in sheet piles at CH1940 (Sg. Kuyuh) in progress.







P11 – Pipeline 1400Ø: Pipe Laying works at CH700 (Jalan BS 7/12) in progress.

P11 – Pipeline 2500Ø: Construction of pile caps at CH1258 (ASTRO area) in progress.

P11 – Pipeline 2400Ø: Piloting works at CH3475 (Jalan Kasturi) in progress.

P11 – Pipeline 2500Ø: Installation of S-Bend at CH1214 (DBKL/ASTRO area) in progress.

P11 – Pipeline 2500Ø: Internal Collar welding inspection at CH1960 (Jalan PBS 14/5).

P11 – Pipeline 1950Ø: Excavation works at CH1064 (BK 6) in progress.







P11 – Pipeline 2400Ø: Excavation for Receiving Pit at CH5777 (Persiaran Puncak Jalil) in progress

P11 – Pipeline 2500Ø: Lean concrete for Pile Cap at CH1258 (ASTRO area) in progress.

P11 – Pipeline 2400Ø: Formwork installation for Thrust Block at CH4100 (Jalan Kasturi).

P11 – Pipeline 1950Ø: Pipe laying works at CH1040 (Bandar Kinrara 6) in progress.

P11 – Pipeline 1950Ø: Installation of pre-cast slab for existing U-Drain at CH1045 (BK6).

P11 – Pipeline 1400Ø: Reinstatement of existing turfing at CH375 (BS9) in progress.







P11 – Pipeline 2400Ø: Excavation for Jacking Pit at CH4506 (MEX Highway) in progress.

P11 – Pipeline 1400Ø: Trench excavation in progress at CH430 (Jalan BS9).

P11 – Pipeline 2500Ø: Jacking of 9th Pipe in progress at CH1989 (Jalan PBS 14/5).

P11 – Pipeline 2400Ø: Pipe laying at CH4095 (Jalan Kasturi) in progress.

P11 – Pipeline 1400Ø: Trench excavation in progress at CH430 (Jalan BS9).

P11 – Pipeline 2500Ø: Construction of Precast Chamber at CH1700 (Sg. Kuyuh) in progress.







P11 – Pipeline 2400Ø: Excavation at CH4173 (Jalan Kasturi) in progress.

P11 – Pipeline 2400Ø: Backfilling works at CH4000 (Jalan Kasturi) in progress.

P11 – Pipeline 2500Ø: Pilotting Works at CH2050 (Jalan PBS 14/5) in progress.

P11 – Pipeline 2500Ø: Pipe Jacking at CH1989 (Jalan PBS 14/5) in progress.

P11 – Pipeline 2400Ø: Trench Excavation at CH3890 (Jalan Kasturi) in progress.

P11 – Pipeline 2400Ø: Technical Meeting No.10/2017 (Site walk) at CH3880 (Jln Kasturi).

P11 – Pipeline 2400Ø: Pipe Delivery at CH3850 (Jalan Kasturi) in progress.








P11 – Pipeline 2400Ø: Installing temporary Entrance Gate at CH3750 (Jalan Kasturi)

P11 – Pipeline 1950Ø: Pipe laying at CH717 (Bandar Kinrara 6) in progress.

P11 – Pipeline 2500Ø: Excavation of Receiving Pit at CH1750 (Sungai Kuyuh) in progress.

P11 – Pipeline 1400Ø: Trench Excavation at CH400 (Jalan Kasturi) in progress.

P11 – Pipeline 2400Ø: Trench excavation at CH4244 (Jalan Kasturi) in progress.

P11 – Pipeline 2500Ø: Preparation for pipe jacking at CH1945-CH1989 in progress.







P11 – Pipeline 2400mmØ: Backfilling at CH3940 (Jalan Kasturi) in progress.

P11 – Pipeline 2500mmØ: Site Clearing at CH1800 (Sungai Kuyuh) in progress.

P11 – Pipeline 2400mmØ: Construction of Wash Through at CH3750 (Jalan Kasturi) in progress.

P11 – Pipeline 2400mmØ: Pipe Laying at CH4451 (Jalan Kasturi) in progress.

P11 – Pipeline 1950mmØ: Trimming slope at CH745 (Bandar Kinrara 6) in progress.

P11 – Pipeline 2400mmØ: Site Clearing at CH4470 (Maju Express Highway) in progress.

P11 – Pipeline 1950mmØ: Construction of Thrust Block at CH770 (Bandar Kinrara 6) in progress.

P11 – Pipeline 1950mmØ: Excavation at CH765 (Bandar Kinrara 6) in progress.

P11 – Pipeline 2400mmØ: Pipes delivery at CH3800 (Jalan Kasturi) in progress.










P11-Pipeine 1950Ø: Backfilling works at CH845 in progress.

P11 – Pipeine 1950Ø: Sand filling to pipe surround at CH875 in progress.

P11 – Pipeine 1950Ø: Construction of washout chamber at CH1500 in progress.

P11 – Pipeine 1950Ø: Trench excavation at CH825 in progress.

P11 – Pipeine 1950Ø: Ripping of hard layer for welding pit at CH825 in progress.

P11 – Pipeine 1950Ø: Pipes delivery at CH750 in progress.

P11 – Pipeine 1950Ø: Pipe laying at CH825 in progress.

P11 – Pipeine 1950Ø: Site Clearing at CH3750 in progress.

P11 – Pipeine 1950Ø: Pipes delivery at CH750 in progress.










P11 – Pipeine 1950Ø: Surveying work for Thrust Block position at CH2790 in progress.

P11 – Pipeine 1950Ø: Outlet pipe installation for Washout Chamber at CH 1500 in progress.

P11 – Pipeine 1950Ø: Pipe delivery at CH2900 in progress.

P11 – Pipeine 1950Ø: Site Clearing work at CH800 in progress.

P11 – Pipeine 1950Ø: Sand Filling at CH2830 – CH2800 in progress

P11 – Pipeine 1950Ø: Construction of Washout Chamber at CH1500 in progress.

P11 – Pipeine 1950Ø: Site Clearing work at CH750 – CH900 in progress.

P11 – Pipeine 1950Ø: Delivery of pipes and fittings at CH2890 in progress.









P11 – Pipeine 1950Ø: Pipe laying work in progress at CH2940.

P11 – Pipeine 1950Ø: Pipe Fittings delivery in progress at CH1500.

P11- Pipeine 1950Ø: Excavation work at CH2930 in progress.

P11 – Pipeine 1950Ø: Piling work for Thrust Block at CH1325 in progress.

P11 – Pipeine 1950Ø: Casting for Thrust Block done at CH1630.

P11 – Pipeine 1950Ø: Excavation works at CH2920 in progress.

P11 – Pipeine 1950Ø: Driving sheet pile in progress at CH1636.

P11 – Pipeine 1950Ø: Laying pipe for Pipe No. 4 in progress.









P11 – Pipeline: Welding works in progress.

P11 – Pipeline: PDA test on piling point in progress.

P11 –Pipeline: PDA test at CH1785 for piling point ‘A’ in progress.

P11 – Pipeline: Joint inspection for delivered pipes in progress.

P11 – Pipeline: Repairing of damaged existing road in progress.

P11 –Pipeline: Piling for thrust block of vertical bend for overcrossing at CH 1622.

P11 – Pipeline: Piling for thrust block of vertical bend for overcrossing at CH1622 to CH1775.

P11 – Pipeline: Concreting work completed at CH1600.







