P11-Pipeline 2500Ø: Pipe jacking at CH2900 (Jln Bukit Serdang 10) in progress.
P11-Pipeline 2500Ø: Extraction of sheetpiles at CH2224 (Jln PBS14/7) in progress.
P11-Pipeline 2500Ø: Pipe laying at CH2224–CH2232 (Jln PBS14/7) in progress.
Dec 19
Nov 19
Oct 19
Sep 19
Aug 19
Jul 19
Jun 19
May 19
Apr 19
Mar 19
Feb 19
Jan 19



















P11-Pipeline 2400Ø: Road reinstatement work at CH4506.00 – CH4566.00 (Mex higway).

P11-Pipeline 2400Ø: Piling work (450mm RC piles) for 24 points at Hutan Simpan Ayer HItam.

P11-Pipeline 2400Ø: Installation of 20° bend at CH7277–CH7279 (Jln Kinrara 6e, BK6E).

P11-Pipeline 1950Ø: Pipe laying at CH1996–CH2006 (Hutan Rimba, BK5) in progress.

P11-Pipeline 1950Ø: Pipe laying at CH600–CH603 (Forest Reserved, BK6) in progress.

P11-Pipeline 2500Ø: Pipe laying at CH2558-CH2550 (Jln PBS 14/16, Tmn Perindustrian Bukit Serdang).

P11- Pipeline 2400Ø: Pipe laying at CH7279-CH7287 (Hutan Rimba, BK5) in progress.

P11-Pipeline 1950Ø: Pipe laying at CH2046-CH2056 (Hutan Rimba, BK5) in progress.

P11-Pipeline 1950Ø: Casting of thrust block for 45°bend at CH603-CH606 (Forest reserved,BK6).










P11-Pipeline 2500Ø: Pipe laying at CH2511–CH2519 (Jln PBS 14/16) in progress.

P11-Pipeline 1950Ø: Pipe laying at CH 69.48 – CH 79.40 (Taman Hening, BK5E) in progress.

P11-Pipeline 1950Ø: Installation of counterweight at Taman Hening, BK5E in progress.

P11-Pipeline 2400Ø: Reinstatement of existing road at Jalan Kinrara 6F, BK6F in progress.

P11-Pipeline 2500Ø: Unloading of 2500Ø pipes at Taman Perindustrian Bukit Serdang.

P11-Pipeline 2400Ø: Pipe laying at CH7257–CH7263 (Jalan Kinrara 6E, Taman Damai Utama).







P11-Pipeline 2400Ø: Delivery of pipe fittings at Taman Melody, BK6E in progress.

P11-Pipeline 1950Ø: Piling works for overcrossing at Hening, BK5E in progress.

P11-Pipeline 1950Ø: Installation of counterweight for pipeline at Hening, BK5E in progress.

P11-Pipeline 1950Ø: Pipe laying at CH171.45 – CH 181.38 (Kinrara Hill, BK5D) in progress.

P11-Pipeline 2400Ø: Pipe laying at CH 5874 – CH 5878 (Jalan Kinrara 6F, BK6F) in progress.

P11-Pipeline 2500Ø: Pipe laying at CH2463–CH2471 (Jln PBS 14/16) in progress.

P11-Pipeline 2400Ø: Piling work for overcrossing at Sg. Bohol in progress.

P11-Pipeline 1950Ø: Pipe laying at CH156–CH161 (Kinrara hill, BK5D) in progress.

P11-Pipeline 2500Ø: Laying of washout tee at jacking pit (BS10) in progress.

P11-Pipeline 2400Ø: Pipe laying at CH5886–CH5893 (Jalan Kinrara 6F, BK6F) in progress.











P11-Pipeline 2500Ø: Pressure grouting for pipe jacking at CH2925–CH3017 (Jln Kasturi, BS10).

P11-Pipeline 1950Ø: Pipe laying at CH320–CH330 (Kinrara hill, BK5D) in progress.

P11-Pipeline 2400Ø: Casting thrust block HB60°at CH5829–CH5833 (Jalan Kinrara 6F, BK6F).

P11-Pipeline 2500Ø: Pipe laying at CH2439–CH2447 (Jln PBS 14/16, Tmn Per. Bukit serdang).

P11-Pipeline 2500Ø: Reinstatement work at CH2345–CH2400 (Jln PBS 14/16) in progress.

P11-Pipeline 1950Ø: Pipe laying at CH 290–CH 300 (Kinrara hill, BK5D) in progress.

P11-Pipeline 2400Ø: Pipe laying CH5837–CH5845 (Jalan Kinrara 6F, BK6F) in progress

P11-Pipeline 2400Ø: Pipe laying at CH7782 – CH 7790 (Taman Melody, BK6E) in progresss.









Pipeline 2400Ø: Pipe delivery at PUJ 9 in progress.

P11-Pipeline 2500Ø: Pipe delivery at Jalan Kasturi in progress.

P11-Pipeline 1950Ø: Road reinstatement at CH3950–CH4250 Taman Perindustrian Kinrara.

P11-Pipeline 1950Ø: CBR test at CH3925, CH4050 and CH4150 Taman Perindustrian Kinrara.

P11-Pipeline 2500Ø: Relocation of overhead cable at pipe jacking area, Bukit Serdang 10.

P11-Pipeline 1950Ø: Site clearing at CH200–CH400, Kinrara hill / Hening, BK5E in progress.

P11-Pipeline 1950Ø: Macintosh probe test at CH0–CH200, Hutan Simpan Ayer Hitamg, BK5E.

P11-Pipeline 2400Ø: Laying of 20° vertical bend at CH5821–CH5827, Jalan Kinrara 6F.

P11-Pipeline 2500Ø: Clearing of internal pipe for water pressure test at CH1943.50. Sg. Kuyoh.

Pipeline 2500Ø: Pipe laying at CH2410.34 – CH2417.05, Jln PBS 14/16 in progress.











P10 – Pipeline 2500 Ø: Pipe laying works at CH.A203.99 – CH.195.99 in progress.

P11-Pipeline 1950Ø: Laying of Air valve tee at CH4022 (Jln TPK 2/1, Tmn Perindustrian Kinrara).

P11-Pipeline 1950Ø: Casting of thrust block at CH4013 (Jln TPK 2/1, Tmn Perindustrian Kinrara).

P11-Pipeline 1950Ø: Pipe laying at CH4034–CH4044 (Jalan TPK 2/1) in progress.

P11-Pipeline 2400Ø: Construction of air valve chamber at CH7610 (Taman melody, Jln BK6E).

P11-Pipeline 1950Ø: Pipe laying at CH4074–CH4083 (Jln TPK 2/1, Tmn Perindustrian Kinrara).







P11-Pipeline 2500Ø: Pipe laying at CH2345–CH2352 (Jalan PBS 14/16) in progress.

P11-Pipeline 1950Ø: Pipe laying at CH3933–CH3943 (Tmn Perindustrian Kinrara) in progress.

P11-Pipeline 2400Ø: Pipe laying at CH7664–CH7672 (Taman Melody, BK6E) in progress.

P11-Pipeline 1950Ø: Pipe laying at CH3943-CH3953 (Tmn Perindustrian Kinrara) in progress.

P11-Pipeline 2500Ø: Welding of inner collar pipe joint at CH2925-CH3017 (Jalan Kasturi, BS10).

P11-Pipeline 2500Ø: Pipe laying at CH2352–CH2360 (Taman Prindustrian Bukit Serdang).







P11-Pipeline 1950Ø: Pipe laying at CH3106.68 – CH3112.33 (TPK,Jln BK5) in progress.

P11-Pipeline 2500Ø: Pipe laying at CH2334.042 – CH2337.092 (Jln PBS 14/16) in progress.

P11-Pipeline 1950: Casting of thrust block & concrete surround at CH3085–CH3112 (TPK, BK5).

Pipeline 1950Ø: Site clearance for hot tapping area at CH4825 – CH4875 (Puchong Jaya).

Pipeline 2500Ø: Formwork for thrust block HB 90° at CH250 (Sg. Kuyuh, DBKL) in progress.

Pipeline 2400Ø: Piloting work for proposed new alignment at CH7587 (Tmn Melody, BK6E).

Pipeline 2500 Ø: Welding for inner collar at CH2925–CH3065 (Jln Kasturi, BS 10) in progress.








P11–Pipeline 2400Ø: Bulk excavation at CH7522 – CH7562 (Jalan BK6E) in progress.

P11-Pipeline 1950Ø: Pipe laying at CH3021.830 – CH3031.880 (Jalan BK5) in progress.

P11-Pipeline 2500Ø: Pipe laying at CH2310.12 – CH2315.19 (Jalan PBS14/7) in progress.

P11-Pipeline 2500Ø: Pipe jacking completed at Jalan BS10.





P11-Pipeline 2500Ø: Extraction of sheet piles for at CH2264.575 (Jln PBS14/7) in progress.

P11–Pipeline 2400Ø: Pipe laying at CH7476.225 to CH7468.30 (Jln BK6E) in progress.

P11-Pipeline 2500Ø: Piloting work at CH500 Technology Park Malaysia (TPM-CARPARK).

P11-Pipeline 2500Ø: Construction of RC thrust block at CH1250 DBKL/SG kuyuh in progress.

P11-Pipeline 2500Ø: Delivery of pipes and fittings at Jln BK5 in progress.

P11-Pipeline 2500Ø: Pipe jacking at CH2900 (Jln Bukit Serdang 10) in progress.

P11-Pipeline 2500Ø: Pipe laying at CH2280.420 to CH2288.345 (Jln PBS14/7) in progress.








P11-Pipeline 2400Ø: Reinstatement work at Jalan Kasturi (CH3555- CH3400) in progress.

P11–Pipeline 2500Ø: Casting of piling extension at Sg Kuyuh river crossing CH1250 in progress.

P11–Pipeline 2400Ø: Laying of discharge pipe from washout chamber at CH4877 (Jln PUJ9).

P11-Pipeline 2500Ø: Extraction of sheetpiles at CH2224 (Jln PBS14/7) in progress.

P11-Pipeline 2400Ø: Pipe laying at CH6658–CH6666 (Jln BK6E) in progress.

P11-Pipeline 2500Ø: Pipe laying at CH2224–CH2232 (Jln PBS14/7) in progress.

P11-Pipeline 2400Ø: Pipe laying at CH6669–CH6672 (Jln BK6E) in progress.