Open Menu
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Pakej 13 :Kolam Air Bukit Jalil Berkapasiti 22 Juta Liter
print
2020
2019
2018
Dec 20
Nov 20
Oct 20
Sep 20
Aug 20
Jul 20
Jun 20
May 20
Apr 20
Mar 20
Feb 20
Jan 20
P13: Chamber Concreting of 2nd lift Flowmeter Chamber 2 in progress
P13: Earthworks Breaking hard material and slope trimming FGL 99.50m in progress
P13: Earthworks Breaking hard material and slope excavation in progress
P13: Drainage Excavation of Berm Drain Type 2 in progress
P13: Earthworks Hacking hard material and slope excavation in progress
P13: Detention Pond Excavation Detention Pond in progress
P13: Drainage Hacking and excavation Drain Type 2 at FGL 114.50m in progress
P13: Detention Pond Excavation and USM replacement at Detention Pond in progress
P13: Drainage Brickworks to 450mm PC Drain in progress
P13-Pipework: Excavation for Air Valve Chamber and Bypass Chamber in progress.
P13- Reservoir: Concreting for Roof Slab Panel RC3 in progress.
P13- Reservoir: Rebar to Roof Slab Panel RC3 in progress.
P13- Drainage: Concreting of RC Wall for 450mm PC Drain in progress.
P13- Reservoir: Fixing formwork for Roof Slab Panel RB3 in progress.
P13- RE Wall: Backfilling works in progress.
P13- Drainage: Excavation for Berm Drain Type 1 in progress.
P13- Reservoir: Rebar for Roof Slab Panel B2 in progress.
P13- Reservoir: Formwork for 3rd lift of wall Panel A7 in progress.
P13- Reservoir: Concreting of 2nd lift wall Panel B7 in progress.
P13- Drainage: Concreting for PC drain in progress.
P13- RE Wall: Backfilling to RE Wall in progress.
No Progress due to MCO
P13- Reservoir Compartment 2: Concreting of 3rd lift wall (Panel A4) in progress.
P13- Reservoir Compartment 1: Concreting of 1st lift wall for Outlet Chamber in progress.
P13- Drainage: Fixing formwork to 3rd lift wall of Manhole MH05 in progress.
P13- Reservoir Compartment 2: Fixing formwork to 1st lift wall of Panel B7 in progress.
P13- Detention Pond: Excavation to Detention Pond in progress.
P13- Reservoir Compartment 1: Rebar and formwork to Roof Slab Panel RC2 in progress.
P13- Reservoir: Concreting of roof slab Panel RA1 in progress
P13- Reservoir: Concreting of roof slab Panel RC1 in progress.
P13- Drainage: Plastering work to 300mm PC Drain in progress.
P13- Reservoir Compartment 2: Formwork to 1st lift wall Panel C7 in progress.
P13- RE Wall Phase 2: Hacking and excavation to RE Wall platform in progress.