Open Menu
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Pakej 13 :Kolam Air Bukit Jalil Berkapasiti 22 Juta Liter 2019
print
2020
2019
2018
Dec 19
Nov 19
Oct 19
Sep 19
Aug 19
Jul 19
Jun 19
May 19
Apr 19
Mar 19
Feb 19
Jan 19
P13- Reservoir Compartment 2: Concreting of slab Panel C6 in progress.
P13- Reservoir Compartment 1: Rebar to 1st lift wall Panel C3 in progress.
P13- Reservoir Compartment 2: Rebar to slab Panel A6 in progress.
P13- RE Wall: Plate bearing test for RE Wall foundation in progress.
P13- RE Wall: Excavation and preparation for RE Wall foundation base in progress.
P13-Reservoir Compartment 1: Concreting of Slab Panel C2 in progress.
P13-Reservoir Compartment 1: Concreting of 1st Lift Wall Panel A1 in progress.
P13-Reservoir Compartment 2: Fixing of rebar and formwork to Slab Panel A5 in progress.
P13- Reservoir Compartment 1: Casting of Slab Panel A4 in progress.
P13- Reservoir Compartment 1: Concrete Blinding to Slab Panel A4 in progress.
P13- Reservoir Compartment 1: Fixing rebar to Slab Panel A3 in progress.
P13- Drainage: Concreting work to 300mm PC Drain in progress.
P13- Reservoir Compartment 2: Concreting work to wall for Outlet and Spare Sump in progress.
P13- Temporary facility: Construction of Mechanical Wash Through Sump in progress.
P13 -TNB Sub-Station: Excavation to TNB Trenches and Footing in progress.
P13-Reservoir Compartment 1: Laying and backfilling to subsoil drain in progress.
P13-Reservoir Compartment 1: Laying of 900 DN Pipe to Spare Outlet Chamber in progress.
P13-Drainage: Construction of 300mm PC Drain in progress.
P13-Reservoir Compartment 1: Construction of Scour and Inlet Chamber in progress.
P13-Soil Investigation: Monitoring of Standpipe Piezometer in progress.
P13: Reservoir Phase 2: Bulk Excavation and Earth Disposal at FGL 88.50m in progress.
P13: Reservoir Phase 1: Excavation to slab level in progress.
P13: Reservoir: Hacking and excavation to slab level in progress
P13: Reservoir: Soil Investigation Works in progress
P13: Reservoir: Hacking for subsoil pipe in progress.
P13-Reservoir: Bulk Excavation and Earth Disposal at FGL 88.50m in progress.
P13-Reservoir: Turfing work at Slope FGL 128.0m in progress.
P13-Reservoir: Drilling blasthole at Reservoir Phase 2 in progress.
P13-Reservoir: Excavation to Reservoir slab level in progress
P13-Reservoir: Fencing work along the boundary in progress.
P13-Reservoir: Bulk Excavation and Earth Disposal at FGL 88.50m in progress.
P13-Reservoir: Turfing work on slopes of Detention Pond in progress.
P13-Reservoir: Slope and Berm excavation at Detention Pond in progress.
P13-Reservoir: Preparation for Rock Blasting in progress.
P13-Reservoir: Bulk Excavation and Earth Disposal at ground level 95.00m in progress.
P13-Reservoir: Preparation for rock blasting No. 21 at ground level 108.00m in progress
P13-Reservoir: Slope and berm trimming at Detention Pond in progress.
P13-Reservoir: Bulk excavation and earth disposal at Ground Level 95.00m in progress
P13-Reservoir: Drilling of blasthole at Ground Level 108.00m in progress
P13-Reservoir: Preparation for Rock Blasting No. 17 at Ground Level 108.00m in progress.
P13-Reservoir: Slope and berm trimming at Ground Level 128.00m and 119.50m in Progress
P13-Reservoir: Joint inspection with consultant for the delivered Butterfly Valves in progress.
P13-Reservoir: Bulk Excavation and Earth Disposal in progress.
P13-Reservoir: Excavation to Detention Pond in Progress.
P13-Reservoir: Drilling to Blasthole in progress.
P13-Reservoir: Blasting Work in progress
P13-Reservoir: Bulk Excavation and Earth Disposal in progress
P13-Reservoir: Inspection by Jabatan Mineral & Geosains for Blasting Works
P13-Reservoir: Drilling to blasthole in progress
P13-Reservoir: Casting of PC fence post in progress
P13-Reservoir: Reinstatement works to damaged public road in progress.
P13-HSSE: Dust Control in progress