Open Menu
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Pakej 14 :Kolam Air Petaling Berkapasiti 80 Juta Liter
print
2020
2019
Dec 20
Nov 20
Oct 20
Sep 20
Aug 20
Jul 20
Jun 20
May 20
Apr 20
Mar 20
Feb 20
Jan 20
L2P14 – Site formation: Preparation of blasting works at reservoir platform.
L2P14 – General: Overall project site view.
L2P14 – Site Formation: Rock blasting works at reservoir platform.
L2P14 – Drainage Works: Construction of MH S4 in progress.
L2P14 – Earthworks: Excavation and transportation out of earth material.
L2P14 – Site Visit: Site visit to the new disposal location at Putra Perdana, Sepang
L2P14 – Site Formation: Aerial View towards Petaling Reservoir.
L2P14 – Earthwork: Excavate and transport out of earth from reservoir platform.
L2P14 – HSSE: Dust control activity.
L2P14 – Earthworks: Transportation out of earth material from project site.
L2P14 – Earthworks: Transportation out of earth material from project site.
P14 –Earthworks: View from Jalan Kinrara 6 towards Petaling Reservoir.7
P14 – Site Formation: Turfing on slope in progress.
P14 –Site Formation: Aerial view of completed RE Wall No. 1.
P14 –Reservoir: Overall Project site view.
P14 –Site Formation: Field density test for RE Wall No. 3 in progress.
P14 –Site Formation: Construction of RE Wall No. 3 in progress.
P14 – Site Formation: Auto Sprinkle System for wash trough facility completed.
P14 –Pipeworks: Pipelaying works for DN2400mm MS pipes in progress.
No Progress due to MCO
P14 –Roadworks: Construction of access road toward reservoir platform in progress.
P14 – Site Formation: Plate bearing test for RE Wall No.3 in progress.
P14 – Site Formation: Construction of RE Wall No.1 in progress.
P14 – Pipeworks: Pipelaying works for DN1950mm MS pipe (CH250 – CH 690) in progress.
P14 – Pipeworks: Pipelaying works for DN2400mm MS pipe (CH591 – CH787) in progress.
P14 –Drainage: Laying of 1800mm RCP pipe in progress.
P14 – Earthworks: Plate bearing test for foundation of RE Wall No.1.
P14 – Pipeworks: Pipelaying works for DN1950mm MS pipe in progress.
P14 – Site formation: Turfing works and construction of berm drain at CH400-CH500.
P14 – Survey works: Setting out for RE Wall No.1.
P14 – Site formation: Site visit from Jabatan Mineral dan Geosains (JMG) for blasting work.