Open Menu
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Pakej 1B: Paip Air Mentah dari Terowong Projek Air Mentah Pahang-Selangor ke Loji Rawatan Air Langat 2 dan Paip Terawat dari Loji Rawatan Air langat 2 ke Kolam Air Imbangan Hulu Langat 2016
print
2019
2018
2017
2016
Dec 16
Nov 16
Oct 16
Sep 16
Aug 16
Jul 16
Raw Water Outlet Connecting Chamber: Preparation and fixing of roof rebar in progress.
P1B – Pressure Testing of Pipeline: Pressure Test for Line3 of Stage 1 was carried on 29
December2016.
P1B – Pipeline Area A1: Preparation to construct toe drain between CH200 & CH300 in
progress.
P1B – Pipeline Area B1: Construction of toe drain between CH350 & CH475 is generally
completed.
P1B – Pipeline Area A3: Fixing capping beam rebar to 1200 U-drain between CH790 &
CH890 in progress.
P1B – Pipeline Area A5: Pipe laying for 3000DN pipes between CH1025 & CH1115 for Line
3&4 in progress.
P1B – Pipeline Area A7: Construction of Crib Retaining Wall for slope protection completed.
P1B – Pipeline Area A8: Concreting for thrust block of 1750DN pipeline at CH443 completed
P1B – Pipeline Area B2: Construction of Crib Retaining Wall for slope protection in
progress.
P1B – Pipeline Area B2: Pipe laying works for 1750DN pipes between CH0 & CH100 in
progress.
Raw Water Outlet Connecting Chamber: Preparation and fixing of wall rebar in progress.
P1B – Pipeline Area A1: Construction of wing wall for stone pitched channel at CH200 in progress.
P1B – Pipeline Area B1: Construction of wing wall for stone pitched channel at CH450 in progress.
P1B – Pipeline Area A3: Laying of 1200 u-drain between CH790 & CH890 in progress.
P1B – Pipeline Area A5: Pipe laying for 3000DN pipes between CH1350 & CH1110 in progress.
P1B – Pipeline Area A5: Pipe laying for 3000DN pipes at CH1025 for Line 3&4 in progress
P1B – Pipeline Area A6: Concreting thrust blocks for 3000DN overcrossing pipes at CH1357 (upstream area) in progress.
P1B – Pipeline Area A7: Construction of Crib Retaining Wall for slope protection in progress.
P1B – Pipeline Area A8: 1750DN pipeline Phase 2 at thrust block (CH443) laid on 09 Dec 2016.
P1B – Pipeline Area B2: Construction of Crib Retaining Wall for slope protection in progress.
P1B – Pipeline Area B2: Pipe laying work for 3000DN pipes between CH2465 & CH2540 in progress.
Raw Water Outlet Connecting Chamber: Removal of existing precast concrete blocks & mass concrete in progress.
3000DN RAW WATER PIPELINES: Preparation to carry out Pressure Testing for Line 1 in progress.
P1B – Pipeline Area B1: Construction of stone pitched channel at CH450 in progress.
P1B – Pipeline Area A2: Laying of permanent block drain practically completed.
P1B – Pipeline Area A5: Pipe laying for 3000DN pipes between CH1350 & CH1155 in progress.
P1B – Pipeline Area A5: Erecting temporary sheet piles for shore up pipe trench between CH1020 & CH1075 in progress.
P1B – Pipeline Area A7: Construction of stone pitched channel at CH1550 in progress.
P1B – Pipeline Area A7: Construction of Crib Retaining Wall for slope protection in progress.
P1B – Pipeline Area B2: Pipe laying work for 3000DN pipes between CH2465 & CH2540 in progress.
P1B – Pipeline Area B2: Pipe laying work for 1750DN pipe between CH100 & CH290 in progress.
P1B – Pipeline Area A1: Dismantling temporary sheet piling (CH20 to CH50) completed.
P1B – Pipeline Area A5: Pipe laying for 3000DN pipes between CH1350 & CH1300 in progress.
P1B – Pipeline Area A6: Pipe laying for 3000DN pipes overcrossing in progress.
P1B – Pipeline Area A7: Pipe laying for 3000DN pipes (Line1&2) toward Pipe Bridge in progress.
P1B – Pipeline Area A7: Pipe laying for 1750DN pipe towards Pipe Bridge in progress.
P1B – Pipeline Area A7: Construction of permanent drains in progress.
P1B – Pipeline Area A7: Construction of Crib Retaining Wall for slope protection in progress.
P1B – Pipeline Area A7: Construction of washout chamber for 3000DN pipes at CH2015 practically completed.
P1B – Pipeline Area A8: Construction of stone pitched channel and brick sump at CH2155 in progress.
P1B – Pipeline Area A1 – Pipe laying works between CH80 & CH20 in progress.
P1B – Pipeline Area A2 – Backfilling to pipe trench (CH700 to CH850) with suitable materials in progress.
P1B – Pipeline Area A3 – Backfilling to pipe trench (CH850 to CH950) with suitable materials in progress.
P1B – Pipe Jacking Area A4 – Pipe Jacking work for 1500DN RC culvert pipe in progress.
P1B – Pipeline Area A7 – Pipe laying for 1750DN pipe in progress.
P1B – Pipeline Area A7 – Filling work for 1750DN pipe (between CH610&CH750) in progress.
P1B – Pipeline Area A7 – Commenced on construction of Crib Retaining Wall for slope protection on 06 August 2016.
P1B – Pipeline Area A8 – Permanent drainage works in progress.
P1B – Pipeline Area A8 – Casting of saddle support for 1750DN pipe above ground generally completed.
P1B – Pipeline Area B2 – Trimming to form permanent slope in progress.
P1B – Pipeline Area B2 – Permanent drainage works at slope area in progress.
P1B – Pipeline Area B2 – Backfilling to pipe trench (CH2290 to CH2275) with sand in progress.
P1B-3m diameter pipeline above ground
P1B-Pipe Bridge Crossing Sungai Langat
P1B- Raw Water Outlet Connecting Chamber
P1B – Pipeline Area A1: Pipe laying works between CH80 & CH40 in progress.
P1B – Pipeline Area A1: Turfing between CH175 & CH100 in progress.
P1B – Pipeline Area B1: Turfing in progress.
P1B – Pipeline Area A2: Backfilling to pipe trench (CH770 to CH850) with suitable materials in progress.
P1B – Pipe Jacking Area A4: Pipe Jacking work for 1500DN RC culvert pipe in progress.
P1B – Pipeline Area A6: Installation of Pipe Bridge for TW 1750DN pipe in progress.
P1B – Pipeline Area A7: Pipe laying works between CH2000 & CH2020 in progress.
P1B – Pipeline Area A7: Pipe laying for 1750DN pipe in progress.
P1B – Pipeline Area A7: Permanent drainage works at slope area in progress.
P1B – Pipeline Area A8: Casting of saddle support for 1750DN pipe above ground in progress.
P1B – Pipeline Area B2: Construction of air valve chambers (at CH2370) in progress.