Raw Water Outlet Connecting Chamber: Preparation and fixing of roof rebar in progress.

P1B – Pressure Testing of Pipeline: Pressure Test for Line3 of Stage 1 was carried on 29
December2016.
December2016.

P1B – Pipeline Area A1: Preparation to construct toe drain between CH200 & CH300 in
progress.
progress.

P1B – Pipeline Area B1: Construction of toe drain between CH350 & CH475 is generally
completed.
completed.

P1B – Pipeline Area A3: Fixing capping beam rebar to 1200 U-drain between CH790 &
CH890 in progress.
CH890 in progress.

P1B – Pipeline Area A5: Pipe laying for 3000DN pipes between CH1025 & CH1115 for Line
3&4 in progress.
3&4 in progress.

P1B – Pipeline Area A7: Construction of Crib Retaining Wall for slope protection completed.

P1B – Pipeline Area A8: Concreting for thrust block of 1750DN pipeline at CH443 completed

P1B – Pipeline Area B2: Construction of Crib Retaining Wall for slope protection in
progress.
progress.

P1B – Pipeline Area B2: Pipe laying works for 1750DN pipes between CH0 & CH100 in
progress.
progress.











Raw Water Outlet Connecting Chamber: Preparation and fixing of wall rebar in progress.

P1B – Pipeline Area A1: Construction of wing wall for stone pitched channel at CH200 in progress.

P1B – Pipeline Area B1: Construction of wing wall for stone pitched channel at CH450 in progress.

P1B – Pipeline Area A3: Laying of 1200 u-drain between CH790 & CH890 in progress.

P1B – Pipeline Area A5: Pipe laying for 3000DN pipes between CH1350 & CH1110 in progress.

P1B – Pipeline Area A5: Pipe laying for 3000DN pipes at CH1025 for Line 3&4 in progress

P1B – Pipeline Area A6: Concreting thrust blocks for 3000DN overcrossing pipes at CH1357 (upstream area) in progress.

P1B – Pipeline Area A7: Construction of Crib Retaining Wall for slope protection in progress.

P1B – Pipeline Area A8: 1750DN pipeline Phase 2 at thrust block (CH443) laid on 09 Dec 2016.

P1B – Pipeline Area B2: Construction of Crib Retaining Wall for slope protection in progress.

P1B – Pipeline Area B2: Pipe laying work for 3000DN pipes between CH2465 & CH2540 in progress.












Raw Water Outlet Connecting Chamber: Removal of existing precast concrete blocks & mass concrete in progress.

3000DN RAW WATER PIPELINES: Preparation to carry out Pressure Testing for Line 1 in progress.

P1B – Pipeline Area B1: Construction of stone pitched channel at CH450 in progress.

P1B – Pipeline Area A2: Laying of permanent block drain practically completed.

P1B – Pipeline Area A5: Pipe laying for 3000DN pipes between CH1350 & CH1155 in progress.

P1B – Pipeline Area A5: Erecting temporary sheet piles for shore up pipe trench between CH1020 & CH1075 in progress.

P1B – Pipeline Area A7: Construction of stone pitched channel at CH1550 in progress.

P1B – Pipeline Area A7: Construction of Crib Retaining Wall for slope protection in progress.

P1B – Pipeline Area B2: Pipe laying work for 3000DN pipes between CH2465 & CH2540 in progress.

P1B – Pipeline Area B2: Pipe laying work for 1750DN pipe between CH100 & CH290 in progress.











P1B – Pipeline Area A1: Dismantling temporary sheet piling (CH20 to CH50) completed.

P1B – Pipeline Area A5: Pipe laying for 3000DN pipes between CH1350 & CH1300 in progress.

P1B – Pipeline Area A6: Pipe laying for 3000DN pipes overcrossing in progress.

P1B – Pipeline Area A7: Pipe laying for 3000DN pipes (Line1&2) toward Pipe Bridge in progress.

P1B – Pipeline Area A7: Pipe laying for 1750DN pipe towards Pipe Bridge in progress.

P1B – Pipeline Area A7: Construction of permanent drains in progress.

P1B – Pipeline Area A7: Construction of Crib Retaining Wall for slope protection in progress.

P1B – Pipeline Area A7: Construction of washout chamber for 3000DN pipes at CH2015 practically completed.

P1B – Pipeline Area A8: Construction of stone pitched channel and brick sump at CH2155 in progress.










P1B – Pipeline Area A1 – Pipe laying works between CH80 & CH20 in progress.

P1B – Pipeline Area A2 – Backfilling to pipe trench (CH700 to CH850) with suitable materials in progress.

P1B – Pipeline Area A3 – Backfilling to pipe trench (CH850 to CH950) with suitable materials in progress.

P1B – Pipe Jacking Area A4 – Pipe Jacking work for 1500DN RC culvert pipe in progress.

P1B – Pipeline Area A7 – Pipe laying for 1750DN pipe in progress.

P1B – Pipeline Area A7 – Filling work for 1750DN pipe (between CH610&CH750) in progress.

P1B – Pipeline Area A7 – Commenced on construction of Crib Retaining Wall for slope protection on 06 August 2016.

P1B – Pipeline Area A8 – Permanent drainage works in progress.

P1B – Pipeline Area A8 – Casting of saddle support for 1750DN pipe above ground generally completed.

P1B – Pipeline Area B2 – Trimming to form permanent slope in progress.

P1B – Pipeline Area B2 – Permanent drainage works at slope area in progress.

P1B – Pipeline Area B2 – Backfilling to pipe trench (CH2290 to CH2275) with sand in progress.

P1B-3m diameter pipeline above ground

P1B-Pipe Bridge Crossing Sungai Langat

P1B- Raw Water Outlet Connecting Chamber
















P1B – Pipeline Area A1: Pipe laying works between CH80 & CH40 in progress.

P1B – Pipeline Area A1: Turfing between CH175 & CH100 in progress.

P1B – Pipeline Area B1: Turfing in progress.

P1B – Pipeline Area A2: Backfilling to pipe trench (CH770 to CH850) with suitable materials in progress.

P1B – Pipe Jacking Area A4: Pipe Jacking work for 1500DN RC culvert pipe in progress.

P1B – Pipeline Area A6: Installation of Pipe Bridge for TW 1750DN pipe in progress.

P1B – Pipeline Area A7: Pipe laying works between CH2000 & CH2020 in progress.

P1B – Pipeline Area A7: Pipe laying for 1750DN pipe in progress.

P1B – Pipeline Area A7: Permanent drainage works at slope area in progress.

P1B – Pipeline Area A8: Casting of saddle support for 1750DN pipe above ground in progress.

P1B – Pipeline Area B2: Construction of air valve chambers (at CH2370) in progress.