P2A –TNB 33 kV Switching Station: Completed.
P2A – Consumer 33kV Switch House: Installation of louvers frame and painting in progress.
P2A – Aerator & Pre-Oxidation Tank Stream A: Fixing of hand railing in progress.
P2A – Aerator & Pre-Oxidation Tank Stream B: Painting in progress
P2A – Administration Building: RC structural works for roof slab, brickwork and wall
plastering in progress.
P2A – Administration Building: Floor screeding, brick works, piping work, plastering works,
installation of air condition ducting and small power &
lighting works in progress.
P2A – Chemical Building: Painting, brick laying and wall plastering in progress
P2A – Chemical Building: Roof screeding, wall plastering and painting in progress.
P2A – Chlorine Building: Brick laying, wall plastering and waterproofing in progress.
P2A – Chlorine Building: Painting in progress
P2A – Residual Emergency Lagoon: Preparation for water tightness test in progress.
P2A – Workshop: RC structural works in progress.
P2A – Clear Water Tank: Casting of slabs, walls and columns in progress.
P2A – Clear Water Tank: Filling water for watertightness test for Tank no.3 in progress
P2A – Washwater Recovery Plant stream A: RC structural works in progress.
P2A– Washwater Recovery Plant stream B: RC structural works in progress.
P2A – Filters Stream A: RC structural works in progress
P2A – Filters Stream B: RC structural works in progress.
P2A – Flood Detention Pond No.1: Construction of Inlet Structure in progress.
P2A – Flood Detention Pond No.2: Construction of outlet Structure in progress.
P2A – Process Control Building Stream A: RC structural works in progress.
P2A – Process Control Building Stream B: RC structural works in progress
P2A – Clarifier Stream A: RC structural works in progress.
P2A – Clarifier Stream B: RC structural works and watertightness test in progress.
P2A – Chemical Mixing Chamber Stream A: RC structural works in progress.
P2A – Chemical Mixing Chamber Stream B: RC structural works in progress.
P2A – Generator Building: Plastering and wall painting in progress.
P2A – Generator Building: Installation of generator sets in progress.
P2A –Treatment Plant Switch House Stream A: Painting in progress
P2A –Treatment Plant Switch House Stream B: Painting in progress.
P2A – Buck Fuel Storage Tank: Construction of base slab and drainage in progress.
P2A – Residual Thickening Tank: RC structural work in progress.
P2A – Thickened Residuals Pumping Station: Incidental Excavation in progress.
P2A – Store: Wall plastering and painting in progress.
P2A – Clarifier Control Building Stream B: RC structural work for foundation in progress.
P2A – Walkthrough Duct A: MP testing in progress.
P2A – RC Ramp at Outlet C: Construction of RC wall in progress.
P2A – Outlet Structure C: RC structural works in progress.
P2A – Outlet Structure A Pond 2: RC structural works in progress
P2A – Service Trench: RC structural works in progress.
P2A – Pipe Bridge: Testing Initial pile in progress.
P2A – Raw Water 3.0mØ MS Pipe: Construction of Inter Connection Chamber in progress.
P2A – Raw Water 3.0m Ø MS Pipe: Laying of pipe in progress.
P2A –Raw water 2.4m Ø MS Pipe: Installation of butterfly valve at stream A in progress.
P2A –Raw water 2.4m Ø MS Pipe: Installation of butterfly valve at stream B in progress.
P2A – Raw water 3.0 m Ø MS Pipe: Pipe laying in progress.
P2A – Interconnection 2.4m Ø MS Pipe Stream A: Pipe laying in progress.
P2A – Treated Water 1.75m Ø MS Pipe: Pipe laying in progress
P2A – Treated Water 3.0m Ø MS Pipe: Pipe laying in progress.
P2A – Treated Water 1.75m Ø MS Pipe: RC works for Valve chamber in progress.
P2A – Treated Water ‘T’ 2.0m Ø MS Pipe: Construction of RC manhole in progress.
P2A – Treated Water 1.90m Ø MS Pipe: RC works for washout chamber in progress.
P2A – Treated Water ‘T’ 2.4m Ø MS Pipe: Construction of RC manhole in progress.
P2A – Overflow 2.4m Ø RC Pipe: Pipe laying in progress.
P2A – Overflow 2.4m Ø twin RC Pipe: Construction of RC manhole in progress.
P2A – Overflow 3.0m Ø RC Pipe: Construction of manhole structure in progress.
P2A – Overflow 3.0m Ø RC Pipe: Construction of manhole structure in progress.
P2A – Overflow 2.4m Ø RC Pipe (Filter): Construction of RC Chamber in progress.
P2A – Overflow 2.1m Ø R.C Pipe: Construction of RC chamber in progress
P2A – Residual 1.35m Ø RC Pipe Stream A: Construction of RC manhole in progress.
P2A – Residual 1.05m Ø RC Pipe Stream B: Pipe laying in progress
P2A – Residual 1.05m Ø RC Pipe Stream A: Construction of RC manhole in progress.
P2A – Residual 1.35m Ø RC Pipe Stream B: Construction of RC manhole in progress.
P2A – Washwater 1.35m Ø RC Pipe Stream A: Construction of RC manhole in progress
P2A – Washwater 1.35m Ø RC Pipe Stream B: Construction of RC manhole in progress.
P2A – Permanent Bridge: Casting of bridge (1st cast) in progress.
P2A –Drainage L-Shape Drain: Installing 6500mm x 2000mm L-shape drain in progress.
P2A – M & E Equipment temporary storage: Delivery of M&E equipment in progress.
P2A – M & E Equipment temporary storage: Delivery of M&E equipment in progress.