2020
2019
2018
2017
2016
Dec 16
Nov 16
Oct 16
Sep 16
Aug 16
Jul 16
May 16
Dec 14

P2A –TNB 33 kV Switching Station: Completed.

P2A – Consumer 33kV Switch House: Installation of louvers frame and painting in progress.

P2A – Aerator & Pre-Oxidation Tank Stream A: Fixing of hand railing in progress.

P2A – Aerator & Pre-Oxidation Tank Stream B: Painting in progress

P2A – Administration Building: RC structural works for roof slab, brickwork and wall
plastering in progress.
plastering in progress.

P2A – Administration Building: Floor screeding, brick works, piping work, plastering works,
installation of air condition ducting and small power &
lighting works in progress.
installation of air condition ducting and small power &
lighting works in progress.

P2A – Chemical Building: Painting, brick laying and wall plastering in progress

P2A – Chemical Building: Roof screeding, wall plastering and painting in progress.

P2A – Chlorine Building: Brick laying, wall plastering and waterproofing in progress.

P2A – Chlorine Building: Painting in progress

P2A – Residual Emergency Lagoon: Preparation for water tightness test in progress.

P2A – Workshop: RC structural works in progress.

P2A – Clear Water Tank: Casting of slabs, walls and columns in progress.

P2A – Clear Water Tank: Filling water for watertightness test for Tank no.3 in progress

P2A – Washwater Recovery Plant stream A: RC structural works in progress.

P2A– Washwater Recovery Plant stream B: RC structural works in progress.

P2A – Filters Stream A: RC structural works in progress

P2A – Filters Stream B: RC structural works in progress.

P2A – Flood Detention Pond No.1: Construction of Inlet Structure in progress.

P2A – Flood Detention Pond No.2: Construction of outlet Structure in progress.

P2A – Process Control Building Stream A: RC structural works in progress.

P2A – Process Control Building Stream B: RC structural works in progress

P2A – Clarifier Stream A: RC structural works in progress.

P2A – Clarifier Stream B: RC structural works and watertightness test in progress.

P2A – Chemical Mixing Chamber Stream A: RC structural works in progress.

P2A – Chemical Mixing Chamber Stream B: RC structural works in progress.

P2A – Generator Building: Plastering and wall painting in progress.

P2A – Generator Building: Installation of generator sets in progress.

P2A –Treatment Plant Switch House Stream A: Painting in progress

P2A –Treatment Plant Switch House Stream B: Painting in progress.


P2A – Buck Fuel Storage Tank: Construction of base slab and drainage in progress.

P2A – Residual Thickening Tank: RC structural work in progress.

P2A – Thickened Residuals Pumping Station: Incidental Excavation in progress.

P2A – Store: Wall plastering and painting in progress.

P2A – Clarifier Control Building Stream B: RC structural work for foundation in progress.

P2A – Walkthrough Duct A: MP testing in progress.

P2A – RC Ramp at Outlet C: Construction of RC wall in progress.

P2A – Outlet Structure C: RC structural works in progress.

P2A – Outlet Structure A Pond 2: RC structural works in progress

P2A – Service Trench: RC structural works in progress.

P2A – Pipe Bridge: Testing Initial pile in progress.

P2A – Raw Water 3.0mØ MS Pipe: Construction of Inter Connection Chamber in progress.

P2A – Raw Water 3.0m Ø MS Pipe: Laying of pipe in progress.

P2A –Raw water 2.4m Ø MS Pipe: Installation of butterfly valve at stream A in progress.

P2A –Raw water 2.4m Ø MS Pipe: Installation of butterfly valve at stream B in progress.

P2A – Raw water 3.0 m Ø MS Pipe: Pipe laying in progress.

P2A – Interconnection 2.4m Ø MS Pipe Stream A: Pipe laying in progress.

P2A – Treated Water 1.75m Ø MS Pipe: Pipe laying in progress

P2A – Treated Water 3.0m Ø MS Pipe: Pipe laying in progress.

P2A – Treated Water 1.75m Ø MS Pipe: RC works for Valve chamber in progress.

P2A – Treated Water ‘T’ 2.0m Ø MS Pipe: Construction of RC manhole in progress.

P2A – Treated Water 1.90m Ø MS Pipe: RC works for washout chamber in progress.

P2A – Treated Water ‘T’ 2.4m Ø MS Pipe: Construction of RC manhole in progress.

P2A – Overflow 2.4m Ø RC Pipe: Pipe laying in progress.

P2A – Overflow 2.4m Ø twin RC Pipe: Construction of RC manhole in progress.

P2A – Overflow 3.0m Ø RC Pipe: Construction of manhole structure in progress.

P2A – Overflow 3.0m Ø RC Pipe: Construction of manhole structure in progress.

P2A – Overflow 2.4m Ø RC Pipe (Filter): Construction of RC Chamber in progress.

P2A – Overflow 2.1m Ø R.C Pipe: Construction of RC chamber in progress

P2A – Residual 1.35m Ø RC Pipe Stream A: Construction of RC manhole in progress.

P2A – Residual 1.05m Ø RC Pipe Stream B: Pipe laying in progress

P2A – Residual 1.05m Ø RC Pipe Stream A: Construction of RC manhole in progress.

P2A – Residual 1.35m Ø RC Pipe Stream B: Construction of RC manhole in progress.

P2A – Washwater 1.35m Ø RC Pipe Stream A: Construction of RC manhole in progress

P2A – Washwater 1.35m Ø RC Pipe Stream B: Construction of RC manhole in progress.

P2A – Permanent Bridge: Casting of bridge (1st cast) in progress.

P2A –Drainage L-Shape Drain: Installing 6500mm x 2000mm L-shape drain in progress.

P2A – M & E Equipment temporary storage: Delivery of M&E equipment in progress.

P2A – M & E Equipment temporary storage: Delivery of M&E equipment in progress.







































































P2A –TNB 33 kV Switching Station: Completed.

P2A – Consumer 33kV Switch House: Installation of louvers frame and painting in progress.

P2A – Aerator & Pre-Oxidation Tank Stream A: Fixing of hand railing in progress.

P2A – Aerator & Pre-Oxidation Tank Stream B: Painting in progress.

P2A – Administration Building: RC structural works for roof slab, brickwork and wall plastering in progress.

P2A – Administration Building: Floor screeding, brick works, piping work, plastering works, installation of air condition ducting and small power & lighting works in progress.

P2A – Chemical Building: Painting, brick laying and wall plastering in progress.

P2A – Chemical Building: Roof screeding, wall plastering and painting in progress.

P2A – Chlorine Building: Brick laying, wall plastering and waterproofing in progress.

P2A – Chlorine Building: Floor screeding in progress.

P2A – Residual Emergency Lagoon: Preparation for water tightness test in progress.

P2A – Workshop: RC structural works in progress.

P2A – Clear Water Tank: Casting of slabs, walls and columns in progress.

P2A – Clear Water Tank: Filling water for watertightness test for Tank no.3 in progress.

P2A – Washwater Recovery Plant stream A: RC structural works in progress.

P2A– Washwater Recovery Plant stream B: RC structural works in progress.

P2A – Filters Stream A: RC structural works in progress.

P2A – Filters Stream B: RC structural works in progress.

P2A – Flood Detention Pond No.1: Construction of Inlet Structure in progress.

P2A – Flood Detention Pond No.2: Slope protection works completed.

P2A – Process Control Building Stream A: RC structural works in progress.

P2A – Process Control Building Stream B: RC structural works in progress.

P2A – Clarifier Stream A: RC structural works in progress.

P2A – Clarifier Stream B: RC structural works and watertightness test in progress.

P2A – Chemical Mixing Chamber Stream A: RC structural works in progress.

P2A – Chemical Mixing Chamber Stream B: RC structural works in progress.

P2A – Generator Building: Plastering and wall painting in progress.

P2A – Generator Building: Installation of generator sets in progress.

P2A –Treatment Plant Switch House Stream A: Painting in progress.

P2A –Treatment Plant Switch House Stream B: Painting in progress.

P2A – Treated Water Pumping Station: Brick works and RC structural works in progress.

P2A – Buck Fuel Storage Tank: Construction of base slab and drainage in progress.

P2A – Residual Thickening Tank: RC structural work in progress.

P2A – Thickened Residuals Pumping Station: Incidental Excavation in progress.

P2A – Store: Wall plastering and painting in progress.

P2A – Clarifier Control Building: RC structural work for foundation in progress.

P2A – Walkthrough Duct: MP testing in progress.

P2A – RC Ramp at Outlet C: Construction of RC wall in progress.

P2A – Outlet Structure C: RC structural works in progress.

P2A – Outlet Structure A Pond 2: RC structural works in progress.

P2A – Raw Water 3.0mØ MS Pipe: Construction of Inter Connection Chamber in progress.

P2A – Raw Water 3.0m Ø MS Pipe: Installing pipe in progress.

P2A –Raw water ‘T’ 3.0m- 2.4m Ø MS Pipe: Installation of inlet pipe at stream A in progress.

P2A –Raw water ‘T’ 3.0m- 2.4m Ø MS Pipe: Installation of inlet pipe at stream B in progress.

P2A Treated Water 1.75m Ø MS Pipe: Pipe laying in progress.

P2A Treated Water 1.90m Ø MS Pipe: RC works for washout chamber in progress.

P2A – Treated Water ‘T’ 2.0m- 3.0m Ø MS Pipe: Installing pipe in progress.

P2A – Treated Water ‘T’ 2.0m- 3.0m Ø MS Pipe: Construction of RC manhole in progress.

P2A – Overflow 2.4m Ø RC Pipe: Pipe laying in progress.

P2A – Overflow 2.4m Ø twin RC Pipe: Construction of RC manhole in progress.

P2A – Overflow 2.1m Ø R.C Pipe: Construction of RC chamber in progress.

P2A – Overflow 0.9m Ø R.C Pipe: Construction of RC chamber in progress.

P2A – Overflow 2.4m Ø RC Pipe: Construction of Inlet structure in progress.

P2A – Overflow 2.4m Ø RC Pipe (Filter): Construction of RC Chamber in progress.

P2A – Residual 1.35m Ø RC Pipe Stream A: Construction of RC manhole in progress.

P2A – Residual 1.35m Ø RC Pipe Stream B: Construction of RC manhole in progress.

P2A – Washwater 1.35m Ø RC Pipe Stream A: Construction of RC manhole in progress.

P2A – Washwater 1.35m Ø RC Pipe Stream B: Construction of RC manhole in progress.

P2A – Permanent Bridge: Temporary work and formwork for RC beams crossing in progress.

P2A – Drainage: Construction of road side drains at Jalan Penghulu in progress.

P2A –Drainage L-Shape Drain: Installing 6500mm x 2000mm L-shape drain in progress.

P2A – Pipe Bridge: Installing pipe in progress.

P2A – M & E Equipment temporary storage: Delivery of M&E equipment in progress.

P2A – M & E Equipment temporary storage: Delivery of M&E equipment in progress.

































































P2A –TNB 33 kV Switching Station: Completed.

P2A – Consumer 33kV Switch House: Installation of louvers frame and painting in progress.

P2A – Aerator & Pre-Oxidation Tank Stream A: Back filling to inlet valve chambers in progress.

P2A – Administration Building: RC structural works for roof slab, brickwork and wall plastering in progress.

P2A – Administration Building: Brick works, piping work, plastering works, installation of air condition ducting and small power & lighting works in progress.

P2A – Chemical Building: R.C structural work, walkthrough duct, brick laying and wall plastering in progress.

P2A – Chemical Building: Wall plastering and painting in progress.

P2A – Chlorine Building: Brick laying, wall plastering and waterproofing in progress.

P2A – Chlorine Building: Installation of duct for ventilation system in progress.

P2A – Aerator & Pre-Oxidation Tank Stream B: Fixing of hand railing in progress.

P2A – Residual Emergency Lagoon: Preparation for water tightness test at Inlet Chamber in progress.

P2A – Store: Wall plastering and painting in progress.

P2A – Clear Water Tank: Casting of slabs, walls and columns in progress.

P2A – Clear Water Tank: Filling water for watertightness test for Tank no.3 in progress.

P2A – Washwater Recovery Plant stream A: RC structural works in progress.

P2A– Washwater Recovery Plant stream B: RC structural works in progress.

P2A – Filters Stream A: RC structural works in progress.

P2A – Filters Stream B: RC structural works in progress.

P2A – Flood Detention Pond No.1: Construction of Inlet Structure in progress.

P2A – Flood Detention Pond No.2: Slope protection works completed.

P2A – Process Control Building Stream A: RC structural works in progress.

P2A – Process Control Building Stream B: RC structural works in progress.

P2A – Clarifier Stream A: RC structural works in progress.

P2A – Clarifier Stream B: RC structural works and watertightness test in progress.

P2A – Chemical Mixing Chamber Stream A: RC structural works in progress.

P2A – Chemical Mixing Chamber Stream B: RC structural works in progress.

P2A – Generator Building: Plastering and wall painting in progress.

P2A – Generator Building: Installation of generator sets in progress.

P2A –Treatment Plant Switch House Stream A: Brick works and wall plastering in progress.

P2A –Treatment Plant Switch House Stream B: Painting in progress.

P2A – Treated Water Pumping Station: Brick works and RC structural works in progress.

P2A – Buck Fuel Storage Tank: Construction of base slab and drainage in progress.

P2A – Residual Thickening Tank: RC structural work in progress.

P2A – Thickened Residuals Pumping Station: Incidental Excavation in progress.

P2A – Workshop: RC structural works in progress.

P2A – Walkthrough Duct: RC structural works in progress.

P2A – RC Ramp at Outlet C: Construction of base slab in progress.

P2A – Outlet Structure C: RC structural works in progress.

P2A – Raw Water 3.0m Ø MS Pipe: Construction of Inter Connection Chamber in progress.

P2A – Raw Water 3.0m Ø MS Pipe: Backfill pipe in progress.

P2A –Raw water ‘T’ 3.0m- 2.4m Ø MS Pipe: Connection Inlet pipe at stream A in progress.

P2A –Raw water ‘T’ 3.0m- 2.4m Ø MS Pipe: Connection Inlet pipe at stream B in progress.

P2A Treated Water 1.75m Ø MS Pipe: Pipe laying in progress.

P2A – Treated Water 1.9m Ø MS Pipe: Pipe laying works in progress.

P2A Treated Water 1.90m Ø MS Pipe: RC works for air valve chamber in progress.

P2A – Treated Water ‘T-junction’ 3.0m- 2.0m Ø MS Pipe: Construction Outlet Chamber in progress.

P2A – Overflow 2.4m Ø RC Pipe: Pipe laying in progress.

P2A – Overflow 2.4m Ø twin RC Pipe: Construction of RC manhole in progress.

P2A – Overflow 2.1m Ø R.C Pipe: Pipe laying in progress.

P2A – Overflow 2.1m Ø R.C Pipe: Construction of RC chamber in progress.

P2A – Overflow 900 mm Ø R.C Pipe (R.E.L): Pipe laying in progress.

P2A – Overflow 2.4m Ø RC Pipe (Filter): Construction of RC Chamber in progress.

P2A – Overflow 2.4m Ø RC Pipe: Construction of Inlet structure in progress.

P2A – Residual 1.35m Ø RC Pipe Stream A: Construction of RC manhole in progress.

P2A – Washwater 1.35m Ø RC Pipe Stream A: Construction of RC Chamber in progress.

P2A – Washwater 1.35m Ø RC Pipe Stream B: Construction of RC Chamber in progress.

P2A – Permanent Bridge: Temporary work for RC beams crossing in progress.

P2A – Drainage: Construction of road side drain at Jalan Penghulu in progress.

P2A Over Crossing No:1: MP test in progress.

P2A – M & E Equipment temporary storage: Delivery of M&E equipment in progress.





























































P2A –TNB 33 kV Switching Station: Completed.

P2A – Consumer 33kV Switch House: Installation of doors in progress.

P2A – Aerator & Pre-Oxidation Tank Stream A: RC structural works for inlet valve chambers in progress.

P2A – Aerator & Pre-Oxidation Tank Stream B: Fixing of weir plate in progress.

P2A – Administration Building: RC structural works for roof and brickwork in progress.

P2A – Administration Building: Brick works, plastering works, installation of air condition ducting and small power & lighting works in progress.

P2A – Chemical Building: R.C structural work, walkthrough duct and brick laying in progress.

P2A – Chlorine Building: Brick laying and wall plastering in progress.

P2A – Chlorine Building: Installation of Air Blower in progress.

P2A – Residual Emergency Lagoon: C&S work completed.

P2A – Store: Wall plastering in progress.

P2A – Clear Water Tank: Casting of slabs, walls and columns in progress.

P2A – Washwater Recovery Plant stream A: RC structural works in progress.

P2A– Washwater Recovery Plant stream B: RC structural works in progress.

P2A – Flood Detention Pond No.2: Slope protection works completed.

P2A – Filters Stream A: RC structural works in progress.

P2A – Filters Stream B: RC structural works in progress.

P2A – Flood Detention Pond No.1: Construction of Inlet Structure in progress.



















P2A-Aerator Stream A

P2A-Chemical Building

P2A-Chlorine Building

P2A-Clear Water Tank

P2A-Generator Building

P2A-Residual Emergency Lagoon

P2A-Treated Water Pumping Station

P2A– Washwater Recovery Plant stream B: RC structural works in progress.

P2A –Treatment Plant Switch House Stream B: Brick laying in progress.

P2A –Treatment Plant Switch House Stream A: RC structural works in progress.

P2A Treated Water 1.75 m Pipeline: Pipe laying in progress.

P2A –TNB 33 kV Switching Station: Completed.

P2A – Washwater Recovery Plant stream A: RC structural works in progress.

P2A – TWP Bukit Enggang Embankment: Laying of stone pitching in progress.

P2A – Treated Water 1900mm Ø M.S Pipe to Bukit Enggang: Pipe laying in progress.

P2A – Thickened residuals Pumping Station: Incidental Excavation in progress.

P2A – Store: Wall plastering in progress.

P2A – Sludge Pipe 1350 Ø RC Pipe (Filter to Washwater): Pipe laying in progress.

P2A – Residual Thickening Tank: Incidental Excavation in progress.

P2A – Residual Emergency Lagoon: Water tightness test in progress.

P2A – Raw Water 3.0m Ø Pipeline: Construction of Inter Connection Chamber in progress.

P2A – Raw Water 3.0 m Pipeline: Pipe laying in progress.

P2A – Process Control Building Stream B: RC structural works in progress.

P2A – Process Control Building Stream A: RC structural works in progress.

P2A – Permanent Bridge: Construction of Pier 1 in progress.

P2A – Overflow 2.4m Ø RC Pipe: Construction of RC manhole in progress.

P2A – Overflow 2.4m Ø RC Pipe: Construction of inlet structure in progress.

P2A – M & E Equipment temporary storage: Delivery of M&E equipment in progress.

P2A – Generator Building: Small power & lighting works in progress.

P2A – Generator Building: Plastering in progress.

P2A – Flood Detention Pond No.2: Slope protection works completed.

P2A – Flood Detention Pond No.1: Construction of Inlet Structure in progress.

P2A – Filters Stream B: RC structural works in progress.

P2A – Filters Stream A: RC structural works in progress.

P2A – Drainage 2100mm Ø R.C Pipe: Construction of RC manhole in progress.

P2A – Drainage 2100mm Ø R.C Pipe to Inlet Structure A: Pipe laying in progress.

P2A – Consumer 33kV Switch House: Installation of doors in progress.

P2A – Clear Water Tank: Casting of slabs, walls and columns in progress.

P2A – Clarifier Stream B: RC structural works and watertightness test in progress.

P2A – Clarifier Stream A: RC structural works in progress.

P2A – Chlorine Building: Installation of Scrubber Tower and brick laying in progress.

P2A – Chemical Mixing Chamber Stream B: RC structural works in progress.

P2A – Chemical Mixing Chamber Stream A: Foundation works in progress.

P2A – Chemical Building: Walkthrough duct and brick laying in progress.

P2A – Buck Fuel Storage Tank: Construction of base slab in progress.

P2A – Aerator & Pre-Oxidation Tank Stream B: Water tightness test in progress.

P2A – Aerator & Pre-Oxidation Tank Stream A: RC structural works for inlet valve chambers in progress.

P2A – Administration Building: RC structural works and brickwork in progress.

P2A – Administration Building: Plastering works, installation of air condition ducting and small power & lighting works in progress.


















































2A – Site Clearance