P2A – Administration Building: Installation of ceiling panel system in progress.
P2A – Generator Building: Installation of Generator Piping System in progress.
P2A – M & E Equipment temporary storage: Delivery of M&E equipment in progress.
Dec 17
Nov 17
Oct 17
Sep 17
Aug 17
Jul 17
Jun 17
May 17
Apr 17
Mar 17
Feb 17
Jan 17

P2A – Aerator & Pre-Oxidation Tank Stream A: Fixing handrails in progress.

P2A – Aerator & Pre-Oxidation Tank Stream B: Casting of Flow Splitters in progress.

P2A – Administration Building: Architectural façade works in progress.

P2A – Administration Building: Laying of skirting tiles at Laboratory Room in progress.

P2A – Administration Building: Installation of Chiller Power Board in progress.

P2A – Administration Building: Ceiling works at corridor area in progress.

P2A – Administration Building: Installation of CPU at Computer Room in progress.

P2A – Administration Building: Installation of granite wall tiles in progress.

P2A – Chemical Building: External architectural work in progress.

P2A – Chemical Building: Installation of pumps and piping system at Lime Service Tank dosing area in progress.

P2A– Chemical Building: Installation of valves and pipes for lime silos in progress.

P2A – Chemical Building: Piping and cabling works at polyelectrolyte residual thickening plant in progress.

P2A – Chemical Building: Installation of ceiling system at locker area in progress.

P2A – Chemical Building: Installation of cable trays at walk through duct area in progress.

P2A–Consumer 33kV Switch House: Installation of electrical panels in progress.

P2A – Clear Water Tank: Installation of static mixer in progress.

P2A – CWT Control Building Stream A: Roof slab screeding and finishing works in progress.

P2A – CWT Control Building Stream A: Brickworks in progress.

P2A – Chlorine Building: External architectural works and painting in progress.

P2A – Chlorine Building: Cabling works for chlorinator panels in progress.

P2A – Wash Water Recovery Plant Stream A: Cabling works for firefighting system in progress.

P2A– Wash Water Recovery Plant Stream B: Installation of wash water pipes in progress.

P2A – Pre-Chlorine Injector House A: Roof waterproofing & screeding work in progress.

P2A – Pre-Chlorine Injector House B: Installation of dosing piping system in progress.

P2A – Filters Stream A: Water tightness test at Tank 2 in progress.

P2A – Filters Stream A: Installation of washwater pipes in progress.

P2A – Filters Stream A: Rendering on waterproofing system in progress.

P2A – Filters Stream A: Plastering to brick wall in progress.

P2A – Filter Stream B: Installation of flowmeter for treated water pipe in progress.

P2A – Filters Stream B: Installation of wall and floor tiles inside the filtered water channel in progress.

P2A – Filter Stream B: Cabling works for ventilation system in progress.

P2A – Filter Stream B: Installation of glass handrailing in progress.

P2A – Filter Stream B: installation of Level Electrodes in progress.

P2A – Filter Stream B: Cable gland & termination works for Filter Control Panels in progress.

P2A – Filter Stream B: Charging of filter media sand at tank 1, 3, 5, 7, 9 and 11 in progress.

P2A – Filter Stream B: Charging of filter media GAC at tank 1, 3, 5, 7, 9 and 11 in progress.

P2A – Clarifier Control Building Stream A: Preparation for brick laying in progress.

P2A–Clarifier Control Building Stream B: Installation of Clarifier MCC B2 in progress.

P2A – Workshop: Installation of architectural roof fascia in progress.

P2A – Store: Installation of DB panel at store hall in progress.

P2A – Process Control Building Stream A: External brickwork in progress.

P2A – Process Control Building Stream B: Painting work and perimeter drain in progress.

P2A – Clarifier Stream A: Installation of PVC sludge pipes at T3 in progress.

P2A –Clarifier Stream A: Preparation for watertightness test at T5 in progress.

P2A –Clarifier Stream B: Cabling works at Clarifier B2 in progress.

P2A –Clarifier Stream B: Grouting for lamella outlet trough in progress.

P2A – Generator Building: External architectural works in progress.

P2A – Generator Building: Installation of walls acoustic system in progress.

P2A – Generator Building: Installation of Auto Main Failure Panel in progress.

P2A – Generator Building: Cabling works for O/S Panel at the Marshalling Panel in progress.

P2A – Generator Building: Cabling works for small power & fire alarm system in progress.

P2A – Bulk Fuel Storage Area: Installation of daily service tank in progress.

P2A – Residual Emergency Lagoon: Installation of slewing jibs completed.

P2A –Residuals Dewatering Building: Construction of RC ground beam and service trench in progress.

P2A – Thickened Residuals Pumping Station: Brickwork in progress.

P2A – Residual Thickening Tank: Precast slab cover for Inlet Chamber completed.

P2A –Treated Water Pumping Station: Installation of cable and small power system in progress.

P2A – Treated Water Pumping Station: Valve installation in progress.

P2A – Treated Water Pumping Station: Final grouting for pump support in progress.

P2A – Treated Water Pumping Station: HT (6.6kV) cabling works in progress.

P2A – Pipe Bridge 2: Installation of steel structure completed.

P2A – Pipe Bridge 1: Installation of steel structure in progress.

P2A – Elevated Walkway A: Construction of RC stumps in progress.

P2A – Stilling Basin: Sand bedding in progress.

P2A – Elevated Walkway B: Construction of RC piers in progress.

P2A – Transformer Yard: Fencing & crusher run works completed.

P2A – Overflow 3.0m Ø RC Pipe: Construction of RC sump in progress.

P2A – Parshall Flume No. 2: Construction RC wall in progress.

P2A – Treated Water 1.90m Ø MS Pipe: Construction of RC flowmeter chamber in progress.

P2A- Outlet Structure C: Laying of rip-rap in progress.

P2A- Guard House: Construction of RC roof beam in progress.

P2A- Roadwork: Joint dipping to sub-grade level in progress.

P2A – Raw Water 3.0m Ø MS Pipe: Installation of interconnection pipe in progress.

P2A – TNB Sub-Station: External (HT) Cabling works for Stream B from Administration Building to TPSH-B in progress.

P2A – Drainage works: Construction of block drain at excess road to Taman Penghulu in progress

P2A – M&E External: Cable conduit road crossing works near Admin Building in progress.

P2A – External M&E: Laying of 6.6kV HT cable & SCADA network conduits from TPSH to PCB (Stream B) in progress.

P2A –External M&E: Laying of High Pressure Main in progress.















































































P2A – Aerator & Pre-Oxidation Tank Stream A: Completed except RC staircase.

P2A – Aerator & Pre-Oxidation Tank Stream B: Pre-installations of sampling pumps in progress.

P2A – Administration Building: External architectural works in progress.

P2A – Administration Building: Painting in progress.

P2A – Administration Building: Installation of floor tiles at toilet area in progress.

P2A – Administration Building: Cabling works in progress.

P2A – Administration Building: Installation of lighting system in progress.

P2A – Administration Building: Installation of granite wall in progress.

P2A – Chemical Building: External architectural work in progress.

P2A – Chemical Building: Installation of pumps and piping system at Lime Service Tank and dosing area in progress.

P2A– Chemical Building: Installation of polyelectrolyte valve power board in progress.

P2A – Chemical Building: Installation of architectural external fins completed.

P2A – Chemical Building: Installation of cable trays at Polyaluminium Chloride plant in progress.

P2A – Chemical Building: Installation of air compressor system at Lime Silo plant in progress.

P2A–Consumer 33kV Switch House: Calibration of Switchboard panel in progress.

P2A – Clear Water Tank: Applying Sodium Silicate at Tank 4 in progress.

P2A – CWT Control Building Stream A: RC structural works in progress.

P2A – CWT Control Building Stream B: Doors and louvres installation in progress.

P2A – Chlorine Building: External architectural works and painting in progress.

P2A – Chlorine Building: JKKP inspection for OH cranes (A&B) completed.

P2A – Wash Water Recovery Plant Stream A: Installation of switchboard panels in progress.

P2A– Wash Water Recovery Plant Stream B: Preparation for pipes installation in progress.

P2A – Pre-Chlorine Injector House A: Preparation for installation of louvers in progress.

P2A – Pre-Chlorine Injector House B: Painting in progress.

P2A – Filters Stream A: Watertightness test at Tank 19 in progress.

P2A – Filters Stream A: Brickwork in progress.

P2A – Filters Stream A: Installation of butterfly valve in progress.

P2A – Filters Stream A: Installations of Filter Slabs at tank 24 in progress.

P2A – Filters Stream A: Installations of Filter Slabs at tank 24 in progress.

P2A – Filters Stream B: Installation of wall and floor tiles inside the clear water channel in progress.

P2A – Filter Stream B: Cabling works for pump motor starter board in progress.

P2A – Filter Stream B: Epoxy Coating for filtered water pipe (post chlorination) in progress.

P2A – Filter Stream B: Discharging of filter gravel at Filter B1 (T4, 6, 8, 10 & 12) in progress.

P2A – Filter Stream B: Discharging of filter media (sand) at Filter B1 Tank 12 in progress.

P2A – Clarifier Control Building Stream A: Prepare for brickwork in progress.

P2A–Clarifier Control Building Stream B: External painting in progress.

P2A – Workshop: External architectural works in progress.

P2A – Store: Installation of ceiling panel system in progress.

P2A – Process Control Building Stream A: External brickwork in progress.

P2A – Process Control Building Stream B: Painting work and perimeter drain in progress.

P2A – Clarifier Stream A: Setting out for installation of PVC sludge pipes at T5 in progress.

P2A –Clarifier Stream A: Valves installation for desludging piping system in progress.

P2A –Clarifier Stream B: Grouting for lamella outlet trough in progress.

P2A –Clarifier Stream B: Cabling works at desludging piping area in progress.

P2A – Generator Building: External architectural works in progress.

P2A – Generator Building: Cabling works at Generator Hall in progress.

P2A – Generator Building: Installation of wall acoustic system in progress.

P2A – Generator Building: Cabling works at LV Room in progress.

P2A – Generator Building: Cabling works at remote switching panel in progress.

P2A – Generator Building: Cabling works for alarm panel in progress.

P2A – Generator Building: Installation of waterproofing system in progress.

P2A – Bulk Fuel Storage Area: Painting for pipes in progress.

P2A – Residual Emergency Lagoon: Installation of slewing jibs completed.

P2A –Residuals Dewatering Building: Construction of RC service trench in progress.

P2A – Thickened Residuals Pumping Station: RC structural works in progress.

P2A –Treated Water Pumping Station: Installation cooper strips in progress.

P2A – Treated Water Pumping Station: Installation of bracket for 5 ton lifting beam in progress.

P2A – Treated Water Pumping Station: Cable tray works at 6.6Kv switch room in progress.

P2A – Treated Water Pumping Station: Installation of handrailing in progress.

P2A – Residual Thickening Tank: Painting in progress.

P2A – Pipe Bridge A: Construction of RC support beam at Abutment A in progress.

P2A – Elevated Walkway: RC structural works in progress.

P2A – Surge Vessel: Preparation for receiving the surge vessels in progress.

P2A – Overflow 3.0m Ø RC Pipe: Construction of RC sump in progress.

P2A – Walk Through Duct to Filter (Stream B): Fixing rebars for foundation base in progress.

P2A – Treated Water 1.90m Ø MS Pipe: Installation of Butterfly Valves at RC interconnection chamber in progress.

P2A- Outlet Structure C: Laying of rip-rap in progress.

P2A- Guard House: Construction of foundation base and columns in progress.

P2A – TNB Sub-Station: TNB SSU Pre-Commissioning Inspection and Testing (PIAT) in progress.






































































P2A – Aerator & Pre-Oxidation Tank Stream A: Painting in progress.

P2A – Aerator & Pre-Oxidation Tank Stream B: External painting completed except final coat.

P2A – Administration Building: External architectural works in progress.

P2A – Administration Building: Pressure testing for air conditioning pipes in progress.

P2A – Administration Building: Installation of transformer in progress.

P2A – Administration Building: Water proofing test at toilet area in progress.

P2A – Administration Building: Installation of air conditioning flexible ducts in progress.

P2A – Administration Building: Installation of granite wall in progress.

P2A – Chemical Building: External architectural work in progress.

P2A – Chemical Building: M&E installation works at Lime Plant in progress.

P2A – Chemical Building: Installation of architectural wall fins and louvres in progress.

P2A – Chemical Building: Installation of decorative fins in progress.

P2A – Chemical Building: Cable tray works at Polyelectrolyte Dosing Area in progress.

P2A – Chemical Building: Installation of pipes and pumps at Potassium Permanganate Plant.

P2A–Consumer 33kV Switch House: Installation of 33kV switch house panel in progress.

P2A – Clear Water Tank: Installation of Cordrain and Stripdrain in progress.

P2A – CWT Control Building Stream A: RC structural works in progress.

P2A – CWT Control Building Stream B: External plastering in progress.

P2A – Chlorine Building: External architectural works and painting in progress.

P2A – Chlorine Building: Installation of cable tray in progress.

P2A – Wash Water Recovery Plant Stream A: Installation of swing jibs in progress.

P2A– Wash Water Recovery Plant Stream B: Installation of ventilation systems in progress.

P2A – Pre-Chlorine Injector House A: Applying roof waterproofing systems in progress.

P2A – Pre-Chlorine Injector House B: External works in progress.

P2A – Filters Stream A: Preparation for watertightness test at Tank 16 in progress.

P2A – Filters Stream A: Brickwork in progress.

P2A – Filters Stream A: Installation of butterfly valve for washwater pipe in progress.

P2A – Filters Stream B: Preparation for mock-up of timber handrailing in progress.

P2A – Filters Stream B: Installation of nozzle caps at tank 8 in progress.

P2A – Filter Stream B: Discharging of filter media at Tank 20 in progress.

P2A – Filter Stream B: Main cable installation in progress.

P2A – Filter Stream B: Cabling works at Filter Gallery in progress.

P2A – Clarifier Control Building Stream A: Construction of roof slab in progress.

P2A–Clarifier Control Building Stream B: External painting in progress.

P2A – Workshop: External architectural works in progress.

P2A – Store: Preparation for floor epoxy coating in progress.

P2A – Process Control Building Stream A: External brickwork in progress.

P2A – Process Control Building Stream A: Small power fittings installation in progress.

P2A – Process Control Building Stream B: Painting work and perimeter drain in progress.

P2A – Clarifier Stream A: Preparation for M&E works at Tank A2 CT1 in progress.

P2A – Chemical Mixing Chamber A: Installation of lifting crane for static mixer in progress.

P2A – Chemical Mixing Chamber B: Installation of lifting crane for static mixer in progress.

P2A –Clarifier Stream B: Grouting for lamella outlet trough in progress.

P2A –Clarifier Stream B: Installation of penstock actuator in progress.

P2A – Generator Building: External architectural works in progress.

P2A – Generator Building: Installation of engine cooling piping system in progress.

P2A – Generator Building: Installation of acoustic rockwool in progress.

P2A – Generator Building: Cable tray and cabling works at LV Room in progress.

P2A – Generator Building: HV cabling works in progress.

P2A – Generator Building: Installation of fresh air ventilation system completed.

P2A – Generator Building: Installation of cooling water pipes in progress.

P2A – Transformer Yard: Installation of transformer completed.

P2A – Bulk Fuel Storage Area: Installation of cooling tower completed.

P2A – Residual Emergency Lagoon: Installation of slewing jibs in progress.

P2A –Residuals Dewatering Building: Back filling in progress.

P2A – Thickened Residuals Pumping Station: RC structural works in progress.

P2A –Treated Water Pumping Station: External plastering work in progress.

P2A –Treated Water Pumping Station: Installation of pumps and internal pipes in progress.

P2A – Treated Water Pumping Station: Installation of ventilation blower systems in progress.

P2A – Treated Water Pumping Station: Installation of Motor Starter Boards and Valve Actuator Power Boards in progress.

P2A – Treated Water Pumping Station: Installation of cable tray in progress.

P2A – Treated Water Pumping Station: Installation of cable tray and copper strips in progress.

P2A – Residual Thickening Tank: Voltage Test at scrapper systems in progress.

P2A – Pipe Bridge B: Construction of pier columns in progress at Abutment A.

P2A – Service Trench: Construction of trench wall in progress.

P2A – Overflow 2400mmØ RC Pipe (Stream B): Construction of RC sump in progress.

P2A – Interconnection 2200mmØ MS Pipe (Stream A): Holiday Test in progress.

P2A – Treated Water 1.90m Ø MS Pipe: Construction of RC Interconnection Chamber in progress.

P2A- Outlet Structure C: Laying of rip-rap in progress.

P2A- Guard House: Construction of foundation base in progress.

P2A- M&E Equipment: Delivery of power cables in progress.








































































P2A – Aerator & Pre-Oxidation Tank Stream A: Valve installation in progress.

P2A – Aerator & Pre-Oxidation Tank Stream B: Cabling works in progress.

P2A – Administration Building: External architectural works in progress.

P2A – Administration Building: Installation of cold water piping system in progress.

P2A – Administration Building: Installation of skylight glasses in progress.

P2A – Administration Building: Building Services piping and cabling works in progress.

P2A – Administration Building: Plaster ceiling work at Asset Manager Office in progress.

P2A – Administration Building: Mock-up for interior furniture at Manager Room in progress.

P2A – Chemical Building: External architectural work in progress.

P2A – Chemical Building: Installation of Fluoride Crusher systems at Fluoride Plant in progress.

P2A – Chemical Building: Installation of architectural wall fins and louvres in progress.

P2A – Chemical Building: Installation of Lime Dosing Pumps in progress.

P2A – Chemical Building: Installation of cable trays at Polyelectrolyte Dosing Area in progress.

P2A – Chemical Building: installation of Rotameter (industrial flowmeter) in progress.

P2A–Consumer 33kV Switch House: Installation firefighting system and cable works in progress.

P2A – Clear Water Tank: Applying sodium silicate on concrete surface at Tank 4 in progress.

P2A – CWT Control Building Stream A: Construction of cable trench and slab in progress.

P2A – CWT Control Building Stream B: Brick laying in progress.

P2A – Chlorine Building: External Cable trays in progress.

P2A – Chlorine Building: Installation of Air Compressor and Air Dryer in progress.

P2A – Wash Water Recovery Plant Stream A: Installation of floor tiles in progress.

P2A– Wash Water Recovery Plant Stream B: Installation of Lighting & Small Power works in progress.

P2A – Pre-Chlorine Injector House A: Preparation for brick laying in progress.

P2A – Pre-Chlorine Injector House B: External painting in progress.

P2A – Filters Stream A: Watertightness test at Tank 20 in progress.

P2A – Filters Stream A: Installation of washwater valves in progress.

P2A – Filters Stream A: Brickwork in progress.

P2A – Filters Stream B: Discharging of filter gravel at Tank 15 in progress.

P2A – Filters Stream B: Discharging of filter sand at Tank 21 in progress.

P2A – Filters Stream B: Discharging of GAC filters media at Tank 23 in progress.

P2A – Filter Stream B: Installation of monorail runway beam in progress.

P2A – Filter Stream B: Installation of cable trays in progress.

P2A – Clarifier Control Building Stream A: Construction of roof slab in progress.

P2A–Clarifier Control Building Stream B: Installation of air compressor system in progress.

P2A – Workshop: Installation of architectural roofing system in progress.

P2A – Store: Lighting & Small Power works in progress.

P2A – Process Control Building Stream A: Brickwork in progress.

P2A – Process Control Building Stream B: Painting work in progress.

P2A – Clarifier Stream A: RC structural works completed except RC staircases.

P2A – Clarifier Stream A: Installation of Slewing Jibs in progress.

P2A – Clarifier Stream A: Water tightness test at Tank A2 CT5 in progress.

P2A – Clarifier Stream A: Installation of desludging piping systems at Tank A2 CT1 in progress.

P2A – Clarifier Stream A: Installation of handrailing in progress.

P2A – Clarifier Stream A: Installation of penstock actuator in progress.

P2A – Clarifier Stream B: Installation of flocculator mixer push button panel in progress.

P2A –Clarifier Stream B: Installation of headstock for sluice valve in progress.

P2A – Generator Building: External architectural works in progress.

P2A – Generator Building: Camshaft & Crankshaft lubrications (periodic engine maintenance) in progress.

P2A – Generator Building: Installation of generator piping system in progress.

P2A – Generator Building: LV cabling works in progress.

P2A – Generator Building: Cable tray works at Generator Hall in progress.

P2A – Generator Building: Installation of oil sump drainage tank in progress.

P2A – Transformer Yard: Secondary cable terminations for transformer in progress.

P2A – Bulk Fuel Storage Area: External painting in progress.

P2A – Cooling Towers Area: Watertightness test for Generator Cooling system in progress.

P2A – Bulk Fuel Storage Area: Installation of piping system for Generator Cooling System in progress.

P2A –Residuals Dewatering Building: Preparation for cable trench foundation in progress.

P2A – Thickened Residuals Pumping Station: RC structural works in progress.

P2A –Treated Water Pumping Station: Plastering work in progress.

P2A –Treated Water Pumping Station: Installation of pump and pipe in progress.

P2A – Treated Water Pumping Station: Installation of fresh air supply fan and ventilation system in progress.

P2A – Treated Water Pumping Station: installation of Delivery Sluice Valve headstock in progress.

P2A – Treated Water Pumping Station: Installation of chequer plate in progress.

P2A – Treated Water Pumping Station: Installation of cooper strip in progress.

P2A – Residual Thickening Tank: Fixing of scrapper central column in progress.

P2A – Permanent Bridge: Preparation of temporary access in progress.

P2A – Pipe Bridge B: Construction of pier columns in progress at Abutment A.

P2A – Outlet Structure B (Pond 1): Laying of rip-rap in progress.

P2A – Interconnection 2200mmØ MS Pipe (Stream A): Pipe laying in progress.

P2A – Treated Water 1.90m Ø MS Pipe: Construction of RC Interconnection Chamber in progress.

P2A – Drainage Arch Culvert: Back filling to RC Arch Culvert in progress.

P2A- Filter B: Site visit by Jawatankuasa Pilihan Khas Sumber Air Selangor.









































































P2A – Aerator & Pre-Oxidation Tank Stream A: Fixing of inlet valves in progress.

P2A – Aerator & Pre-Oxidation Tank Stream B: Installation of hose down pipe in progress.

P2A – Administration Building: External architectural works in progress.

P2A – Administration Building: Installation of air conditioner system in progress.

P2A – Administration Building: Installation of ceiling panels in progress.

P2A – Administration Building: Fixing of glass handrail mock-up in progress.

P2A – Chemical Building: External architectural steel work in progress.

P2A – Chemical Building: Installation of Fluoride Crusher systems at Fluoride Plant in progress.

P2A – Chemical Building: Installation of pump and pipes at Lime Service Tank in progress.

P2A – Chemical Building: Installation of handrailing at Lime Service Tank in progress.

P2A – Chemical Building: Installation of architectural wall cladding and fins in progress.

P2A – Chemical Building: Installation of pumps and pipes at Lime Mixing Tank in progress.

P2A – Consumer 33kV Switch House: Busbar compounding works for 33kV Panels in progress.

P2A – Walk Through Duct: RC structural works completed.

P2A – CWT Control Building Stream A: Construction of cable trench in progress.

P2A – CWT Control Building Stream B: Preparation for brick laying in progress.

P2A – Chlorine Building: External painting and architectural steel works in progress.

P2A – Chlorine Building: Installation of evaporator piping system in progress.

P2A – Wash Water Recovery Plant Stream A: Plastering work to building in progress.

P2A– Wash Water Recovery Plant Stream B: Painting work in progress.

P2A – Pre-Chlorine Injector House A: Construction of roof slab in progress.

P2A – Pre-Chlorine Injector House B: External painting in progress.

P2A – Filters Stream A: RC structural works in progress.

P2A – Filters Stream B: Painting work in progress.

P2A – Filters Stream B: Installation of filter slab (Tank no.6) in progress.

P2A – Filter Stream B: Installation of valve for washwater pipe in progress.

P2A – Filter Stream B: Laying of floor tiles at filter gallery area in progress.

P2A – Filter Stream B: Installation of chequer plate covers for cable trench in progress.

P2A – Filter Stream B: Installation of overhead crane in progress.

P2A – Filter Stream B: Installation of glass handrail mock-up at filter gallery in progress.

P2A – Clarifier Control Building Stream A: Construction of base slab and trenches in progress.

P2A – Clarifier Control Building Stream B: Undercoat painting in progress.

P2A – Clear Water Tank: Water tightness test at tank 4 in progress.

P2A – Workshop: External architectural steel work and painting in progress.

P2A – Process Control Building Stream A: RC structural works in progress.

P2A – Process Control Building Stream B: Painting work in progress.

P2A – Clarifier Stream A: RC structural works completed except RC staircases.

P2A – Clarifier Stream A: Installing slewing jibs mock-up at Tank A2 CT1 in progress.

P2A – Clarifier Stream A: Watertightness test at Tank A2 CT3 in progress.

P2A – Clarifier Stream A: Installation of Desludging Piping systems at Tank A2 CT3 in progress.

P2A – Clarifier Stream B: Installation of M&E equipment in progress.

P2A – Clarifier Stream B: Installation of Lamella Plate at Tank B1 CT1 in progress.

P2A – Clarifier Stream B: Installation of scum remover at Tank B1 CT3 in progress.

P2A –Clarifier Stream B: Installation of Pressure Switch at Tank B2 CT2 in progress.

P2A – Chemical Mixing Chamber Stream A: Installation of hand railing in progress.

P2A – Chemical Mixing Chamber Stream B: Installation of Static Mixers completed except dosing system.

P2A – Generator Building: Installation of louvers and painting in progress.

P2A – Generator Building: Installation of Air Intake/Exhaust system completed.

P2A – Generator Building: Installation of Generator Exhaust system completed.

P2A – Generator Building: Installation of Generator Piping system in progress.

P2A – Generator Building: Installation of acoustic wall C-channel / brackets in progress.

P2A – Generator Building: Installation of firefighting system in progress.

P2A – Generator Building: Installation of HT Panels in HT room in progress

P2A – Transformer Yard: Installation of cooling fins and termination of cables for transformers in progress.

P2A – Bulk Fuel Storage Area: Installation of Generator Daily Service Tanks and Water Storage Tank steel structure completed.

P2A – Bulk Fuel Storage Area: Fabrication of Diesel Bulk Fuel Tanks in progress.

P2A –Residuals Dewatering Building: Construction of foundation footings in progress.

P2A – Thickened Residuals Pumping Station: RC structural works in progress.

P2A – Residual Thickening Tank: Preparation for sludge pumps installation in progress.

P2A – Store: Installation of roofing steel truss system in progress.

P2A –Treated Water Pumping Station: Painting and plastering works in progress.

P2A – Treated Water Pumping Station: Installation of pumps and piping system in progress.

P2A – Treated Water Pumping Station: Positioning of motors in progress.

P2A – Treated Water Pumping Station: Installation of ventilation system in progress.

P2A – Treated Water Pumping Station: Installation of HT Panels and Cable Trays in HT room in progress.

P2A – Treated Water Pumping Station: Installing handrailing in progress.

P2A – Service Trench: Construction of external cable trench in progress.

P2A – Elevated Walkway: RC structural works in progress.

P2A – Outlet Structure B (Pond 1): Construction of outlet wall completed.

P2A – Permanent Bridge: External coating in progress

P2A – Pipe Bridge B: Construction of pile cap in progress at Abutment A.

P2A – Residual 900mmØ RC Pipe (Stream A): Construction of RC sump in progress.

P2A – Treated Water 1.90m Ø MS Pipe: Construction of RC Interconnection Chamber in progress.

P2A – Drainage Arch Culvert: Construction of RC Arch Culvert 6.5m x 2.0m in progress.

P2A – HSSE: 3rd Party Environmental Audit on 23 August 2017.

P2A – Clarifier Stream B: Site visit by Kementerian Wilayah Persekutuan on 24 August 2017.













































































P2A – Aerator & Pre-Oxidation Tank Stream A: Fixing of hand railing in progress.

P2A – Aerator & Pre-Oxidation Tank Stream B: Painting in progress.

P2A – Administration Building: Architectural works in progress.

P2A – Administration Building: Installation of air conditioner pipes in progress.

P2A – Administration Building: Installation of ceiling panel system in progress.

P2A – Administration Building: Installation of sanitary and cold water pipes in progress.

P2A – Chemical Building: External architectural steel work in progress.

P2A – Chemical Building: Installation of pumps and piping system at Fluoride Plant in progress.

P2A – Chemical Building: Installation of pump and pipes at Lime Service Tank in progress.

P2A – Chemical Building: Installation of recirculation pump at Lime Service Tank in progress.

P2A – Chemical Building: Installation of pumps and piping system at Potassium Plant in progress.

P2A – Chemical Building: Installation of roof ventilators and roofing steel work in progress.

P2A – Chemical Building: Installation of pump and pipes at Polyelectrolyte and Polyaluminium Chloride plant in progress.

P2A – Residual Emergency Lagoon: Final touch-up works in progress.

P2A – CWT Control Building Stream B: Construction of roof slab in progress.

P2A – Chlorine Building: External painting and architectural steel works in progress.

P2A – Chlorine Building: Installation of evaporator piping system in progress.

P2A – Wash Water Recovery Plant Stream A: Plastering work to building in progress.

P2A– Wash Water Recovery Plant Stream B: Plastering work to building in progress.

P2A – Clear Water Tank: Water tightness test at tank 4 in progress.

P2A – Consumer 33kV Switch House: Installation of louvers and painting in progress.

P2A – Pre-Chlorine Injector House A: Preparation for base slab and trenches in progress.

P2A – Pre-Chlorine Injector House B: Undercoat painting in progress.

P2A – Filters Stream A: RC structural works in progress.

P2A – Filters Stream B: Brickwork and plastering works at PCB area in progress.

P2A – Filters Stream B: Installation of filter slab (Tank no.8) in progress.

P2A – Filter Stream B: Installation of Washwater Pumps at PCB in progress.

P2A – Filter Stream B: Filter Slab uplift test (Tank no: 22) in progress.

P2A – Filter Stream B: Laying of floor tiles at UPS room in progress.

P2A – Clarifier Control Building Stream A: Preparation for base slab and trenches in progress.

P2A – Clarifier Control Building Stream B: Undercoat painting in progress.

P2A – Walk Through Duct: RC structural works in progress.

P2A – Workshop: Preparation for external architectural steel work and painting in progress.

P2A – Flood Detention Pond No.1: Construction of Inlet Structure in progress.

P2A – Flood Detention Pond No.2: Construction of Outlet Structure in progress.

P2A – Process Control Building Stream A: RC structural works in progress.

P2A – Process Control Building Stream B: Plastering work in progress.

P2A – Clarifier Stream A: RC structural works in progress.

P2A – Clarifier Stream B: Installation of M&E equipment in progress.

P2A – Clarifier Stream B: Installation of Lamella Plate at Tank B2 CT1 in progress.

P2A –Clarifier Stream B: Installing cable treys at Tank B1 CT2 in progress.

P2A – Chemical Mixing Chamber Stream A: Installing hand railing in progress.

P2A – Chemical Mixing Chamber Stream B: Installation of Static Mixers in progress.

P2A – Generator Building: Installation of louvers and painting in progress.

P2A – Generator Building: Installation of Air Intake/Exhaust system in progress.

P2A – Generator Building: Installation of Generator Piping System in progress.

P2A – Generator Building: Installation of Generator Exhaust system in progress.

P2A – Generator Building: Installation of acoustic wall C-channel / brackets in progress.

P2A –Residuals Dewatering Building: Preparation for foundation footings in progress.

P2A – Thickened Residuals Pumping Station: RC structural works in progress.

P2A – Store: Installation of roofing steel truss system in progress.

P2A –Treatment Plant Switch House Stream A: Painting in progress.

P2A –Treatment Plant Switch House Stream B: Painting in progress.

P2A – Bulk Fuel Storage Area: Installation of Generator Daily Service Tanks and Water Storage Tank steel structure in progress.

P2A – Bulk Fuel Storage Area: Fabrication of Diesel Bulk Fuel Tank in progress.

P2A – Bulk Fuel Storage Area: Fabrication of Water Tank in progress.

P2A – Bulk Fuel Storage Area: Cooling Towers installation in progress.

P2A –Treated Water Pumping Station: Waterproofing system and plastering works in progress.

P2A – Treated Water Pumping Station: Pre-installation/Alignment of Non-Return Valves in progress.

P2A – Treated Water Pumping Station: Pre-installation / Positioning and arranging the pump motor stools in progress.

P2A – Treated Water Pumping Station: Installation of cable trays in progress.

P2A – Residual Thickening Tank: Applying Calcium Silicate in progress.

P2A – Service Trench: Construction of external cable trench in progress.

P2A – Elevated Walkway: RC structural works in progress.

P2A – Outlet Structure B (Pond 1): Construction of outlet walls completed.

P2A – Permanent Bridge: Preparation for external coating in progress.

P2A – Pipe Bridge B: Construction of piers in progress at Abutment B.

P2A – Overflow 2.4mØ RC Pipe (Stream A): Pipe laying in progress.

P2A – Raw Water 3.0mØ MS Pipe: Preparation for hydrostatic test for Line C&D in progress.

P2A – Treated Water 1.90m Ø MS Pipe: Construction of RC Interconnection Chamber in progress.

P2A – Treated Water 1.75m Ø MS Pipe: Pipe laying in progress.

P2A – Drainage Arch Culvert: Construction of RC Arch Culvert 6.5m x 2.0m in progress.

P2A – M & E Equipment Installation: Cable laying from Transformers to Generator Building in progress.










































































P2A – Aerator & Pre-Oxidation Tank Stream A: Fixing of hand railing in progress.

P2A – Aerator & Pre-Oxidation Tank Stream B: Painting in progress.

P2A – Administration Building: Architectural works in progress.

P2A – Administration Building: Installation of sanitary pipes and air-vent duct in progress.

P2A – Administration Building: Apply Water Proofing System at Air Conditioner Pumping room in progress.

P2A – Administration Building: Installation of metal roofing sheets in progress.

P2A – Chemical Building: External architectural steel work in progress.

P2A – Chemical Building: External architectural steel work in progress.

P2A – Chemical Building: Installation of Upvc pipes at PACL Bulk Tank area in progress.

P2A – Chemical Building: Installation of Lime Mixing Tank in progress.

P2A – Chemical Building: Installation of pumps and piping system at Lime Service Tank and dosing area in progress.

P2A – Chemical Building: Installation of Skylight Roofing in progress.

P2A – Chemical Building: Installation of pipes for Dissolving Tanks in progress.

P2A – Chemical Building: Installation of Lighting & Small Power conduits at Polyelectrolyte and Polyaluminium Chloride Control Room in progress.

P2A – Residual Emergency Lagoon: Preparation for water tightness test in progress.

P2A – CWT Control Building Stream B: Rebars fixing for foundation slab in progress.

P2A – Chlorine Building: External painting and architectural steel works in progress.

P2A – Chlorine Building: Installation of louvers frames in progress.

P2A – Wash Water Recovery Plant Stream A: Water tightness test and brickwork in progress.

P2A– Wash Water Recovery Plant Stream B: Plastering work in progress.

P2A – Clear Water Tank: Water tightness test at tank 4 in progress.

P2A – Consumer 33kV Switch House: Installation of louvers and painting in progress.

P2A – Pre-Chlorine Injector House A: Preparation for base slab and trenches in progress.

P2A – Pre-Chlorine Injector House B: Plastering completed.

P2A – Filters Stream A: RC structural works in progress.

P2A – Filters Stream B: Brickwork and plastering works in progress.

P2A – Filters Stream B: Installation of cable tray support brackets in progress.

P2A – Filter Stream B: Installation of Washwater lifting pumps at PCB in progress.

P2A – Filter Stream B: Installation of filter slabs at Stream B2 Tank 5 in progress.

P2A – Filter Stream B: Pressure test for filter slab at Stream B2 Tank 17 in progress.

P2A – Filter Stream B: Installation of Air Scour Piping System in progress.

P2A – Clarifier Control Building Stream B: Brickwork and plastering works in progress.

P2A – Flood Detention Pond No.1: Construction of Inlet Structure in progress.

P2A – Process Control Building Stream B: Plastering work in progress.

P2A – Clarifier Stream A: RC structural works in progress.

P2A – Clarifier Stream B: Installation of M&E equipment in progress.

P2A – Clarifier Stream B: Installation of Lamella Trusses at Tank B1 CT2 in progress.

P2A – Clarifier Stream B: Installation of Lamella Plate at Tank B2 CT3 in progress.

P2A – Workshop: Preparation for painting in progress.

P2A – Thickened Residuals Pumping Station: RC structural works in progress.

P2A – Chemical Mixing Chamber Stream A: RC structural works in progress.

P2A – Chemical Mixing Chamber Stream B: Installation of Static Mixers in progress.

P2A – Generator Building: Installation of louvers and painting in progress.

P2A – Generator Building: Installation of Air Intake/Exhaust system in progress.

P2A – Generator Building: Installation of Generator Exhaust system in progress.

P2A – Generator Building: Installation of internal piping system in progress.

P2A –Treatment Plant Switch House Stream A: Painting in progress.

P2A –Treatment Plant Switch House Stream B: Painting in progress.

P2A – Store: Installation of roofing steel truss system in progress.

P2A – Residual Thickening Tank: Water tightness test in progress.

P2A – Bulk Fuel Storage Tank: Installation of Generator Daily Service Tanks and Water Storage Tank steel structure in progress.

P2A – Buck Fuel Storage Tank: Fabrication of Diesel Bulk Fuel Tank in progress.

P2A – Buck Fuel Storage Tank: Fabrication of Daily Fuel Tank pipes in progress

P2A – Buck Fuel Storage Tank: Cooling Towers installation in progress.

P2A –Treated Water Pumping Station: Waterproofing system and plastering works in progress.

P2A – Treated Water Pumping Station: Pre-installation/Alignment of Non Return Valves in progress.

P2A – Treated Water Pumping Station: Pre-installation / Positioning and arranging the pump motor stools in progress.

P2A –Residuals Dewatering Building: Preparation for foundation footings in progress.

P2A – Service Trench: Construction of external cable trench in progress.

P2A – Elevated Walkway: Construction of footings in progress.

P2A – Outlet Structure B Pond 1: Construction of walls in progress.

P2A – Permanent Bridge: Installation of handrails in progress.

P2A – Pipe Bridge B: Pile heads cutting in progress at Abutment A.

P2A – Pipe Bridge B: Construction of piers in progress at Abutment B.

P2A – Raw Water 3.0mØ MS Pipe: Pipes laying for Phase 2 Lines in progress.

P2A – Raw Water 3.0mØ MS Pipe (Line 2): Hydrostatic Test in progress.

P2A – Treated Water 1.90m Ø MS Pipe: Construction of RC Interconnection Chamber in progress.

P2A – Treated Water 3.0m Ø MS Pipe: Construction of Butterfly Valve Chamber in progress.

P2A – Treated Water 2.40m Ø MS Pipe: Construction of RC Inlet Valve Chambers and pipe laying in progress.

P2A – Drainage Arch Culvert Drain: Construction of RC Arch Culvert 6.5m x 2.0m in progress.







































































P2A – Aerator & Pre-Oxidation Tank Stream A: Fixing of hand railing in progress.

P2A – Aerator & Pre-Oxidation Tank Stream B: Painting in progress.

P2A – Administration Building: Architectural works in progress.

P2A – Administration Building: Installation of sanitary pipes in progress.

P2A – Administration Building: Installation of Air Conditioner System in progress.

P2A – Administration Building: Installation of metal roofing sheets in progress.

P2A – Chemical Building: External architectural steel work in progress.

P2A – Chemical Building: Installation of piping system at Potassium Permanganate Area in progress.

P2A – Chemical Building: Installation of pumps and piping system at Polyelectrolyte Thickening Storage area in progress.

P2A – Chemical Building: Installation of pumps and piping system at PACL and Polyelectrolyte Dosing area in progress.

P2A – Chemical Building: Installation of pumps and piping system at Lime Service Tank and Dosing area in progress.

P2A – Chemical Building: Laying of floor tiles in progress.

P2A – Chemical Building: Installation of Skylight Roofing in progress.

P2A – Chemical Building: Installation of Lighting & Small Power conduit pipes at Fluoride Plant in progress.

P2A – Consumer 33kV Switch House: Installation of louvers frame and painting in progress.

P2A – Residual Emergency Lagoon: Preparation for water tightness test in progress.

P2A – Chlorine Building: External painting and architectural steel works in progress.

P2A – CWT Control Building Stream B: Construction of internal cable trench in progress.

P2A – Wash Water Recovery Plant stream A: Fixing hand railing and brickwork in progress.

P2A– Wash Water Recovery Plant stream B: Fixing hand railing and brickwork in progress.

P2A – Clear Water Tank: Water tightness test in progress.

P2A – Clarifier Control Building Stream B: Brickwork and plastering in progress.

P2A – Filters Stream A: RC structural works in progress.

P2A – Filters Stream B: Brickwork in progress.

P2A – Filters Stream B: Installation of cable tray in progress.

P2A – Filter Stream B: Installation of washwater lifting pumps (EBARA) at PCB in progress.

P2A – Filter Stream B: Filter slab grouting at Stream B2 tank 19 in progress.

P2A – Filter Stream B: Installation of filter slabs at Stream B2 tank 9 in progress.

P2A – Filter Stream B: Installation of Washwater Valves in progress.

P2A – Filter Stream B: Installation of Air Scour Piping System in progress.

P2A – Flood Detention Pond No.1: Construction of Inlet Structure in progress.

P2A – Flood Detention Pond No.2: Construction of Outlet Structure in progress.

P2A – Process Control Building Stream A: RC structural works in progress.

P2A – Process Control Building Stream B: Brickwork in progress.

P2A – Clarifier Stream A: RC structural works in progress.

P2A – Clarifier Stream A: Fixing of desludging pipes at external wall in progress.

P2A – Clarifier Stream B: Installation of M&E equipment in progress.

P2A – Clarifier Stream B: Installation of Fire Hydrant Pipes at Tank B2 CT2 in progress.

P2A – Clarifier Stream B: Installation of Lamella Trusses at Tank B1 CT5 in progress.

P2A – Clarifier Stream B: Preparation for installation of cable trays at Tank B1 in progress.

P2A – Clarifier Stream B: Installation of Mixer at Tank B1 CT3 in progress.

P2A – Pre Chlorine Injector House: Plastering in progress.

P2A – Chemical Mixing Chamber Stream A: RC structural works in progress.

P2A – Chemical Mixing Chamber Stream B: Preparation for Static Mixer installation in progress.

P2A – Thickened Residuals Pumping Station: RC structural works in progress.

P2A – Generator Building: Installation of louvers frame and painting in progress.

P2A – Generator Building: Installation of Air Intake/Exhaust system in progress.

P2A – Generator Building: Installation of Generator Exhaust system in progress.

P2A – Generator Building: Installation of Generator Exhaust system (internal) in progress.

P2A – Generator Building: Cleaning/Rectifying of HT Panels in progress.

P2A – Workshop: Brickwork and walls plastering in progress.

P2A –Treatment Plant Switch House Stream A: Painting in progress.

P2A –Treatment Plant Switch House Stream B: Installation of windows in progress.

P2A – Store: Installation of roofing steel truss system in progress.

P2A – Residual Thickening Tank: RC structural work in progress.

P2A – Bulk Fuel Storage Tank: Installation of Generator Daily Service Tanks and Water Storage Tank steel structure in progress.

P2A – Buck Fuel Storage Tank: Fabrication of Diesel Bulk Fuel Tank in progress.

P2A – Treated Water Pumping Station: Waterproofing System and plastering works in progress.

P2A – Treated Water Pumping Station: Pre-installation / Lowering the Delivery Pumps onto the plinths in progress.

P2A –Residuals Dewatering Building: Preparation for foundation footings in progress.

P2A – Service Trench: Construction of external cable trench in progress.

P2A – Elevated Walkway: Construction of footing in progress.

P2A – Permanent Bridge: Construction of parapet walls and cable trenches in progress.

P2A – Pipe Bridge A: Piling in progress at Abutment A.

P2A – Pipe Bridge B: Excavation for pile cap in progress at Abutment A.

P2A – Pipe Bridge B: RC structure for pile cap in progress at Abutment B.

P2A – Outlet Structure B Pond 1: Casting of foundation base in progress.

P2A – Raw Water 3.0mØ MS Pipe: Pipes laying for Phase 2 Lines in progress.

P2A – Raw Water 3.0mØ MS Pipe (Line 2): Preparation for Hydrostatic Test in progress.

P2A – Treated Water 1.90m Ø MS Pipe: Construction of RC support for High Pressure Tee Off in progress.

P2A – Treated Water 2.5m Ø MS Pipe: Construction of Surge Vessel Supports in progress.

P2A – Treated Water 2.40m Ø MS Pipe: Construction of RC Inlet Valve Chambers in progress.

P2A – Drainage Arch Culvert Drain: Construction of RC Arch Culvert 6.5m x 2.0m in progress.










































































P2A – Aerator & Pre-Oxidation Tank Stream A: Fixing of hand railing in progress.

P2A – Aerator & Pre-Oxidation Tank Stream B: Painting in progress.

P2A – Administration Building: Architectural works in progress.

P2A – Administration Building: Installation of sanitary pipes in progress.

P2A – Administration Building: Installation of Air Conditioner Filters in progress.

P2A – Consumer 33kV Switch House: Installation of louvers frame and painting in progress.

P2A – Chemical Building: Painting and external architectural steel work in progress.

P2A – Chemical Building: External column and wall painting in progress.

P2A – Chemical Building: Installation of Fluorite Tanks and uPVC pipes in progress.

P2A – Chemical Building: Installation of Fluoride Mixing Tanks in progress.

P2A – Chemical Building: Installation of OH Crane at Fluoride Plant in progress.

P2A – Residual Emergency Lagoon: Preparation for water tightness test in progress.

P2A – Chlorine Building: External painting and architectural steel works in progress.

P2A – Chlorine Building: Installation of lighting & small power conduit pipes in progress.

P2A – Chlorine Building: Installation of floor tiles in progress.

P2A – CWT Control Building Stream B: Construction of internal cable trench in progress.

P2A – Wash Water Recovery Plant stream A: RC structural works and brickwork in progress.

P2A– Wash Water Recovery Plant stream B: Fixing hand railing and brickwork in progress.

P2A– Wash Water Recovery Plant stream B: Installation of Waterproofing System in progress.

P2A – Clear Water Tank: Water tightness test in progress.

P2A – Filters Stream A: RC structural works in progress.

P2A – Filters Stream B: RC structural works in progress.

P2A – Filters Stream B: Installation of Filter Slabs at Tank 22 & 24 in progress.

P2A – Filters Stream B: Installation of acoustic doors at Compressor Rooms in progress.

P2A – Filter Stream B: Installation of Backwash Suction Valves at PCB in progress.

P2A – Filter Stream B: Fixing of hand railing for walkway in progress.

P2A – Filter Stream B: Installation of wash water pipes in progress.

P2A – Filter Stream B: Installation of Air Scour inlet pipes in progress.

P2A – Flood Detention Pond No.1: Construction of Inlet Structure in progress.

P2A – Flood Detention Pond No.2: Construction of Outlet Structure in progress.

P2A – Process Control Building Stream A: RC structural works in progress.

P2A – Process Control Building Stream B: Brickworks in progress.

P2A – Clarifier Stream A: RC structural works in progress.

P2A – Clarifier Stream B: Installing M&E equipment in progress.

P2A – Clarifier Stream B: Fixing of hand railing for walkway at Tank B2 CT2 in progress.

P2A – Clarifier Stream B: Grouting for Lamella Trusses at Clarifier B1 CT1 in progress.

P2A – Clarifier Stream B: Preparation for Lamella grouting at Clarifier B2 CT3 in progress.

P2A – Clarifier Stream B: MSCL Sludge Valves installation at Clarifier B1 CT3 in progress.

P2A – Clarifier Stream B: Installation of uPVC desludging pipes at B1 CT3 in progress.

P2A – Clarifier Stream B: Installation of Mixer Shafts at B1 CT5 in progress.

P2A – Clarifier Stream B: Installation of Inlet Penstock at Clarifier B2 CT5 in progress.

P2A – Pre Chlorine Injector House: Brickworks in progress.

P2A – Chemical Mixing Chamber Stream A: RC structural works in progress.

P2A – Chemical Mixing Chamber Stream B: Water tightness test at T1 in progress.

P2A – Clarifier Control Building Stream B: RC structural works in progress.

P2A – Thickened Residuals Pumping Station: RC structural works in progress.

P2A – Generator Building: Installation of louvers frame and painting in progress.

P2A – Generator Building: Installation of Intake/Exhaust Piping system in progress.

P2A – Generator Building: Installation of Generator Exhaust Piping system in progress.

P2A – Generator Building: Installation of Generator Air Intake system in progress.

P2A –Treatment Plant Switch House Stream A: Painting in progress.

P2A –Treatment Plant Switch House Stream B: Painting in progress.

P2A – Workshop: Brickworks and walls plastering in progress.

P2A – Store: Installation of roofing steel truss system in progress.

P2A – Bulk Fuel Storage Tank: Installation of Generator Daily Service Tanks and Water Storage Tank steel structure in progress.

P2A – Buck Fuel Storage Tank: Fabrication of Diesel Bulk Fuel Tank in progress.

P2A – Residual Thickening Tank: RC structural work in progress.

P2A – Residual Thickening Tank: Construction of RC Inlet Valve Chamber C2 in progress.

P2A – Treated Water Pumping Station: Waterproofing System and plastering works in progress.

P2A – Treated Water Pumping Station: Waterproofing System and plastering works in progress.

P2A – Treated Water Pumping Station: Preparation for installation of pump sets in progress.

P2A –Residuals Dewatering Building: Preparation for foundation footings in progress.

P2A – Permanent Bridge: Construction of parapet walls and cable trenches in progress.

P2A – Permanent Bridge: Installation hand railing in progress.

P2A – Permanent Bridge: FDT test at Abutment B in progress.

P2A – Pipe Bridge B: Excavation for pile cap in progress at Abutment B.

P2A – Outlet Structure B Pond 1: Preparation for foundation base in progress.

P2A – Raw Water 3.0mØ MS Pipe (Line 2): Pipes laying in progress.

P2A – Raw Water 3.0mØ MS Pipe (Line 2): Preparation for Hydrostatic Test in progress.

P2A – Treated Water 1.90m Ø MS Pipe: Construction of RC support for High Pressure Tee Off in progress.

P2A – Treated Water 2.5m Ø MS Pipe: Construction of Surge Vessels Supports in progress.

P2A – Drainage L-Shape Drain: Installing 6.5m x 2.0m L-shape drain in progress.









































































P2A – Aerator & Pre-Oxidation Tank Stream A: Water tightness test and fixing of hand railing in progress.

P2A – Aerator & Pre-Oxidation Tank Stream B: Painting in progress.

P2A – Administration Building: Steel works and RC cable trenches in progress.

P2A – Administration Building: Waterproofing at rooftop in progress.

P2A – Chemical Building: Painting, brick laying and external steel work in progress.

P2A – Chemical Building: Installation of Service Water Tank in progress.

P2A – Chlorine Building: Perimeter drain, wall plastering and waterproofing in progress.

P2A – Chlorine Building: Installation of Extractor Fan in progress.

P2A – Residual Emergency Lagoon: Preparation for water tightness test in progress.

P2A – Consumer 33kV Switch House: Installation of louvers frame and painting in progress.

P2A – Clear Water Tank: Casting of roof slabs and water tightness test in progress.

P2A – Pre Chlorine Injector House: Brickworks in progress.

P2A – Wash Water Recovery Plant stream A: RC structural works in progress.

P2A– Wash Water Recovery Plant stream B: Installing Hand railing and water tightness test in progress.

P2A – Filters Stream A: RC structural works in progress.

P2A – Filters Stream B: RC structural works in progress.

P2A – Filters Stream B: Installation of Filter Slabs in progress.

P2A – Filter Stream B: Preparation and installing Backwash Suction Pump at filter gallery in progress.

P2A – Flood Detention Pond No.1: Construction of Inlet Structure in progress.

P2A – Flood Detention Pond No.2: Construction of Outlet Structure in progress.

P2A – Process Control Building Stream A: RC structural works in progress.

P2A – Process Control Building Stream B: RC staircase and brickwork in progress.

P2A – Clarifier Stream A: RC structural works in progress.

P2A – Clarifier Stream B: Installing M & E equipment in progress.

P2A – Clarifier Stream B: Installation of hand railings at Tank B1CT1 in progress.

P2A – Clarifier Stream B: Lamella Plate installation at Clarifier B2 CT5 in progress.

P2A – Clarifier Stream B: Installation of Sampling Pipes at Clarifier B2 CT1 in progress.

P2A – Clarifier Stream B: Preparation for M&E installation at Sub Stream B1 CT1 in progress.

P2A – Clarifier Control Building Stream B: RC structural work in progress.

P2A – Thickened Residuals Pumping Station: Fixing rebar for base slab in progress.

P2A – Chemical Mixing Chamber Stream A: RC structural works in progress.

P2A – Chemical Mixing Chamber Stream B: Water tightness test in progress.

P2A – Generator Building: Installation of louvers frame and painting in progress.

P2A – Generator Building: Installation of Intake/Exhaust Piping Systems in progress.

P2A – Generator Building: Pre-Installation of Vent Systems in progress.

P2A – Generator Building: Mock-Up Installation of Cable Trays in Generator Hall in progress.

P2A – Generator Building: Pre-Installation of Vent Systems in progress.

P2A – Workshop: Brickworks in progress.

P2A –Treatment Plant Switch House Stream A: Painting in progress.

P2A –Treatment Plant Switch House Stream A: Installation of exhaust silencers in progress.

P2A –Treatment Plant Switch House Stream B: Painting in progress.

P2A –Treatment Plant Switch House Stream B: Installation of Small power and Firefighting System in progress

P2A – Bulk Fuel Storage Tank: Installation of Generator Daily Service Tanks and Water Storage Tank steel structure in progress.

P2A – Buck Fuel Storage Tank: Fabrication of Diesel Bulk Fuel tank in progress.

P2A – Residual Thickening Tank: RC structural work in progress.

P2A – Residual Thickening Tank: Water tightness test at Tank T2 in progress.

P2A – Treated Water Pumping Station: Brick works and plastering works in progress.

P2A – Store: Installing roofing steel truss system in progress.

P2A – Permanent Bridge: Construction of parapet walls and cable trench in progress.

P2A – Pipe Bridge B: PDA test in progress at abutment A.

P2A – Pipe Bridge B: Excavation for pile cap in progress at abutment B.

P2A – Pipe Bridge B: Delivery of bridge segments at Abutment A in progress.

P2A – Raw Water 3.0mØ MS Pipe: Hydrostatic Test in progress at line A.

P2A – Raw Water 3.0mØ MS Pipe: Pipe laying in progress.

P2A – Interconnection 2.0mØ MS Pipe: Pipe laying from Clarifier to Filter in progress.

P2A Treated Water 1.75m Ø MS Pipe: Pipe laying in progress.

P2A – Treated Water 2.50m Ø MS Pipe: Construction of RC support for High Pressure Tee Off in progress.

P2A – Treated Water 2.5m Ø MS Pipe: Construction of Surge Vessels supports in progress.

P2A – Overflow 3.0m Ø RC Pipe: Construction of RC Overflow Chamber in progress.

P2A – Overflow 3.0m Ø RC Pipe: Construction of RC Scour Chamber in progress.

P2A –Wash water 1.35m Ø RC Pipe: Pipe laying and construction of RC manhole in progress.






























































P2A – Aerator & Pre-Oxidation Tank Stream A: Fixing of hand railing in progress.

P2A – Aerator & Pre-Oxidation Tank Stream B: Painting in progress.

P2A – Administration Building: Brickwork and wall plastering in progress.

P2A – Administration Building: Installation of external steel truss structure in progress.

P2A – Chemical Building: Painting, brick laying and wall plastering in progress.

P2A – Chemical Building: Waterproffing at rooftop in progress.

P2A – Chlorine Building: Perimeter drain, wall plastering and waterproofing in progress.

P2A – Chlorine Building: Installation of Scrubber Tower PVC pipe in progress.

P2A – Residual Emergency Lagoon: Preparation for water tightness test in progress.

P2A – Consumer 33kV Switch House: Installation of louvers frame and painting in progress.

P2A – Clear Water Tank: Casting of roof slabs in progress.

P2A – Clear Water Tank: Filling water for watertightness test for Tank no.3 in progress.

P2A – Washwater Recovery Plant stream A: RC structural works in progress.

P2A– Washwater Recovery Plant stream B: RC structural works in progress.

P2A – Filters Stream A: RC structural works in progress.

P2A – Filters Stream B: RC structural works in progress.

P2A – Filters Stream B: Installation of Filter Slabs in progress.

P2A – Filter Stream B: Installation of MS Air Scour Valve in progress.

P2A – Flood Detention Pond No.1: Construction of Inlet Structure in progress.

P2A – Flood Detention Pond No.2: Construction of outlet Structure in progress.

P2A – Process Control Building Stream A: RC structural works in progress.

P2A – Process Control Building Stream B: RC staircase and brickwork in progress.

P2A – Clarifier Stream A: RC structural works in progress.

P2A – Clarifier Stream B: Installing M & E equipment in progress

P2A – Clarifier Stream B: Installation of Handrailling B2 CT5 in progress.

P2A – Clarifier Stream B: Installation of Lamella plate at Clarifier B2 CT3 in progress.

P2A – Clarifier Stream B: Installation of Focculator Mixer at B2 FT3 in progress..

P2A – Clarifier Control Building Stream B: RC structural work in progress.

P2A – Chemical Mixing Chamber Stream A: RC structural works in progress.

P2A – Chemical Mixing Chamber Stream B: RC structural works in progress.

P2A – Generator Building: Perimeter drain and wall painting in progress.

P2A – Generator Building: Installation of Exhaust Gas Pipe in progress.

P2A –Treatment Plant Switch House Stream A: Painting in progress.

P2A –Treatment Plant Switch House Stream A: Installation of wiring cable in progress.

P2A –Treatment Plant Switch House Stream B: Painting in progress.

P2A –Treatment Plant Switch House Stream B: Installation of ducting main cable in progress.

P2A – Treated Water Pumping Station: Brick works and RC structural works in progress.

P2A – Treated Water Pumping Station: Installation of overhead crane in progress.

P2A – Buck Fuel Storage Tank: Installation of Generator Daily Service Tanks and Water Storage Tank steel structure in progress.

P2A – Buck Fuel Storage Tank: Fabrication of Diesel Bulk Fuel tank in progress.

P2A – Residual Thickening Tank: RC structural work in progress.

P2A – Workshop: RC structural works in progress.

P2A – Thickened Residuals Pumping Station: Fixing rebar for base slab in progress.

P2A –Residuals Dewatering Building: Borehole and testing soil in progress.

P2A – Store: Wall painting and perimeter drain in progress.

P2A – Pre Chlorine Injector House: RC structural works in progress.

P2A – Outlet Structure B Pond 1: Excavation in progress.

P2A – Pipe Bridge B: Piling works in progress at abutment A.

P2A – Raw Water 3.0mØ MS Pipe: Construction of Inter Connection Chamber in progress.

P2A – Raw Water 3.0mØ MS Pipe: Pipe laying in progress.

P2A – Treated Water 3.0m Ø MS Pipe: Pipe laying in progress.

P2A Treated Water 1.75m Ø MS Pipe: Pipe laying in progress.

P2A – Treated Water 1.75m Ø MS Pipe: Construction of Surge Vessels supports in progress.

P2A – Treated Water 2.9m Ø MS Pipe: Construction of Surge Vessels supports in progress.

P2A – Treated Water 20m Ø MS Pipe: Excavation of Flowmeter Chamber in progress.

P2A –Washwater 1.35m Ø RC Pipe: Pipe laying in progress.

P2A –Washwater 1.35m Ø RC Pipe: Pipe laying in progress.

P2A – Overflow 3.0m Ø RC Pipe: Construction of manhole structure in progress.

P2A –Drainage L-Shape Drain: Installing 6.5m x 2.0m L-shape drain in progress.

P2A –Drainage U-Shape Drain: Installing 1500mm x 1200mm U-drain in progress.

P2A – Permanent Bridge: Fixing formwork for parapet walls in progress.

P2A – Permanent Bridge: Preparation for stressing cable in progress.

P2A – M & E Equipment Installation: Exhaust pipe delivery for 6.6kV Generators.

P2A – M & E Equipment Delivery: Delivery of DC Chargers / Battery panels in progress.

P2A – M & E Equipment Installation: Presentation on ID and CCTV camera to AIS (23 Feb) at SMAJV meeting room.

P2A – Alternative access to Taman Penghulu: Site visit by MPKJ’s officer on 20 February 2017.

P2A – Thickened Residuals Pumping Station:: Site visit by BOD PAAB on 23 February 2017.

P2A – Clarifier Stream B: Site visit by BOD PAAB on 23 February 2017.





































































P2A – Aerator & Pre-Oxidation Tank Stream A: Fixing of hand railing in progress.

P2A – Aerator & Pre-Oxidation Tank Stream B: Painting in progress.

P2A – Administration Building: RC structural works for roof slab, brickwork and wall plastering in progress.

P2A – Administration Building: External C&S works in progress.

P2A – Chemical Building: Painting, brick laying and wall plastering in progress.

P2A – Chemical Building: Epoxy flooring in progress.

P2A – Chlorine Building: Perimeter drain, wall plastering and waterproofing in progress.

P2A – Chlorine Building: Installation of Overhead Crane in progress.

P2A – Residual Emergency Lagoon: Preparation for water tightness test in progress.

P2A – Consumer 33kV Switch House: Installation of louvers frame and painting in progress.

P2A – Clear Water Tank: Casting of slabs, walls and columns in progress.

P2A – Clear Water Tank: Filling water for watertightness test for Tank no.3 in progress.

P2A – Washwater Recovery Plant stream A: RC structural works in progress.

P2A– Washwater Recovery Plant stream B: RC structural works in progress.

P2A – Filters Stream A: RC structural works in progress.

P2A – Filters Stream B: RC structural works in progress.

P2A – Filters Stream B: Installation of Filter Slabs (B2) in progress.

P2A – Filter Stream B: Installation of Air Scour pipes in progress.

P2A – Flood Detention Pond No.1: Construction of Inlet Structure in progress.

P2A – Flood Detention Pond No.2: Construction of outlet Structure in progress.

P2A – Process Control Building Stream A: RC structural works in progress.

P2A – Process Control Building Stream B: RC structural works in progress.

P2A – Clarifier Stream A: RC structural works in progress.

P2A – Clarifier Stream B: RC structural works and watertightness test in progress.

P2A – Clarifier Stream B: MSCL sludge pipe installation at Clarifier B2 T1 in progress.

P2A – Clarifier Stream B: Installation of Lamella at Clarifier B2 T1 in progress.

P2A – Chemical Mixing Chamber Stream A: RC structural works in progress.

P2A – Chemical Mixing Chamber Stream B: RC structural works in progress.

P2A – Generator Building: Perimeter drain and wall painting in progress.

P2A – Generator Building: Installation of generator sets in progress.

P2A –Treatment Plant Switch House Stream A: Painting in progress.

P2A –Treatment Plant Switch House Stream B: Painting in progress.

P2A –Treatment Plant Switch House B: Installation of electrical conduit pipes in progress.

P2A – Treated Water Pumping Station: Brick works and RC structural works in progress.

P2A – Treated Water Pumping Station: Installation of overhead crane in progress.

P2A – Treated Water Pumping Station: Preparation for installation of pumps in progress.

P2A – Buck Fuel Storage Tank: Installation of Generator Daily Service tanks and Water storage tank steel structure in progress.

P2A – Residual Thickening Tank: RC structural work in progress.

P2A – Thickened Residuals Pumping Station: Lean concrete and formwork in progress.

P2A – Workshop: RC structural works in progress.

P2A – Store: Wall painting and perimeter drain in progress.

P2A – Store: Installation Overhead Crane in progress

P2A – Clarifier Control Building Stream B: RC structural work in progress.

P2A – RC Ramp at Outlet C: Construction of RC slab in progress.

P2A – Outlet Structure A Pond 2: RC structural works in progress.

P2A – Pre Chlorine Injector House: RC structural works in progress.

P2A – Pipe Bridge: MLT on initial pile in progress at abutment A.

P2A – Pipe Bridge: Piling works in progress at abutment B.

P2A – Raw Water 3.0mØ MS Pipe: Construction of Inter Connection Chamber in progress.

P2A – Interconnection 2.4m Ø MS Pipe Stream A: Pipe laying in progress.

P2A – Treated Water 3.0m Ø MS Pipe: Pipe laying in progress.

P2A – Treated Water 2.5m Ø MS Pipe: Construction of Surge Vessels supports in progress.

P2A – Treated Water 1.75m Ø MS Pipe: RC works for Valve Chamber in progress.

P2A – Overflow 2.1m Ø R.C Pipe: Installing RC pipe in progress.

P2A –Drainage L-Shape Drain: Installing 6.5m x 2.0m L-shape drain in progress.

P2A – Permanent Bridge: Fixing formwork for parapet walls in progress.

P2A – M & E Equipment temporary storage: Delivery of M&E equipment in progress.

P2A – M & E Equipment temporary storage: Delivery of M&E equipment in progress.

P2A – M & E Equipment FAT: FAT for Potassium Permanganate MCC in progress.

P2A – Filter B: Site visit by KSU KeTTHA.