2020
2019
2018
2017
2016
P2A –Clarifier Stream A: Installation of clarifier control panel at Clarifier A2 Tank 5 in progress.
P2A –Clarifier Stream B: Operation of Clarifier B1 Tank 5 for P4-Pumping Exercise in progress.
P2A– Residual Emergency Lagoon: Sodium silicate application in progress.
P2A – Treated Water 1.90mØ Pipeline: Backfilling in progress.
P2A– M&E External: Cable ducting work for SCADA and telecom cable at Washwater Recovery Plant A in progress.
P2A– M&E External: Installation of sampling pipe near Filter B in progress.
P2A– M&E External: HPRM pipe installation (DN 100) at Residual Thickening Tank in progress.
P2A– M&E External: HPRM pipe installation (DN 400) at Clarifier A in progress.
P2A– M&E External: Construction of external service trench at Filter A in progress.
P2A– M&E External: Installation of scour valve in progress.
P2A– M&E External: CWT-TWPS instrument cable installation works in progress.
P2A –Surge Vessel A: Cable termination works in progress.
P2A –Surge Vessel A: Painting works in progress.
P2A –Surge Vessel B: Cable termination works in progress.
P2A – Turfing: Preparation for turfing at Aerator A in progress.
P2A – Roadwork: Laying of subsoil at road 11 (Chemical Building) in progress.
P2A – Roadwork: CBR test at Carpark B in progress.
P2A – Roadwork: FDT test for road base at Carpark B in progress.
P2A – Roadwork: Spray prime coat at Carpark B in progress.
P2A – Site Visit: Site visit by UTMKL and University of Pretoria on 25/09/2018.
P2A – Site Visit: Site visit by SPAN on 27/09/2018.
P2A – Site Visit: Site visit by SPAN on 27/09/2018.
P2A–Administration Building: Energization preparation – Cleaning up transformers in progress.
P2A – Filters Stream B: Internal testing for washwater pump VFD panel in progress.
P2A–Chemical Building: Cable dressing works for air compressor at Potassium Permanganate Plant A in progress.
P2A – Filters Stream B: Cable & panel insulation test at PCB supervisory Panel B in progress.
P2A–Treated Water Pumping Station: Actuator cable termination works in progress.
P2A – Administration Building: Installation of laboratory furniture / benches in progress.
P2A–Chemical Building: Installation of electrical panel at Potassium control room in progress.
P2A – Clear Water Tank: Coating thickness test (tank 4) in progress.
P2A – Clear Water Tank: Installation of subsoil pipe and cordrain in progress.
Dec 18
Nov 18
Oct 18
Sep 18
Aug 18
Jul 18
Jun 18
May 18
Apr 18
Mar 18
Feb 18
Jan 18

P2A–Aerator A: Pre-installation of (E&I) panels and cabling work in progress.

P2A–Administration Building: Pressure test for water tap in progress.

P2A–Chemical Building: Dosing pipes termination works for Stream A in progress.

P2A–Chemical Building: Cables termination at PAC dosing pump Stream A in progress.

P2A–Chemical Building: Calibration of Poly Residual dosing pumps in progress.

P2A–Chemical Building: SCADA loop testing of PAC control panel Stream B in progress.

























































































































































P2A–Chemical Building: Installation of dosing pipes at walk through duct Stream A in progress.

P2A–Chemical Building: Installation of cable at walk though duct Stream A in progress.

P2A–Chemical Building: Collecting data for asset database system in progress.

P2A–Chemical Building: Cable termination at Lime Dosing Pumps Stream A in progress.

P2A–Chemical Building: Cable termination at Polyelectrolyte control system Stream A in progress.

P2A–Chemical Building: Internal inspection for cable termination for PAC control panel Stream B in progress.





























































































P2A –Administration Building: SCADA Server installation at Electrical Room in progress.

P2A –Administration Building: SCADA HMI pre-installation at Command Center in progress.

P2A–Chemical Building: Cable glanding for potassium preparation system Stream A in progress.

P2A–Chemical Building: Cable dressing at Potassium air compressor system Stream A in progress.

P2A–Chemical Building: Cable termination at Potassium permanganate control panel Stream A in progress.

P2A–Chemical Building: Installation of PAC dosing pumping system Stream A in progress.

P2A–Chemical Building: Cable termination inside walk through duck at Stream A in progress.




























































































































P2A–Aerator A: Installation of cable tray and cable termination work in progress.

P2A –Administration Building: Relay setting for 415V incomer no.2 in progress.

P2A–Chemical Building: Cable glanding for lime dosing pumps at Plant A in progress.

P2A–Chemical Building: Cabling work at walk through duck in progress.

P2A – Chemical Building: Pipe painting for service water pipe in progress.

P2A–Chemical Building: Functional test of electrical pump at lime dosing plant B in progress.

P2A – Chemical Building: Testing of electrical panel for lime dosing Plant B in progress.

P2A – Chemical Building: Cable glanding at Lime silo control panel Plant B in progress.

P2A – Chemical Building: Poly Residual Plant B SCADA/Instrument inspection in progress.

P2A–Chemical Building: Poly Residual Plant B SCADA/Instrument inspection in progress.

P2A–Chemical Building: Poly Residual Plant B SCADA/Instrument testing in progress.

P2A–Chemical Building: Functional test at Potassium preparation system plant B in progress.

P2A–Chemical Building: Functional test at Potassium control room Plant B in progress.

P2A–Chlorine Building: Cable dressing for chlorinator system Stream A in progress.

P2A – Chlorine Building: Cable termination for evaporator system Stream A in progress.

P2A–Chlorine Building: Cable termination for Chlorine control room panel Stream A in progress.

P2A–Chlorine Building: Cable termination for walkthrough duct control panel in progress.

P2A–Wash Water Recovery Plant A: Preparation for cable trays in progress.

P2A–Wash Water Recovery Plant A: Preparation for installation of penstock in progress.

P2A – Filters Stream A: Filter slab installation works at tank 7 in progress.

P2A – Filters Stream A: Bitumen sealing works at Tank 5 in progress.

P2A – Filters Stream A: Filter slabs grouting works at Tank 3 in progress.

P2A – Filters Stream A: Construction of PCB lower roof in progress.

P2A – Filters Stream A: Preparation for cable tray at PCB/Filter Gallery A in progress.

P2A – Filters Stream A: Inspection of acoustic panels at PCB A blower rooms in progress.

P2A – Filters Stream A: Leakage test for overflow channel in progress.

P2A – Filters Stream A: Installation of butterfly valve for backwash pipeline in progress.

P2A – Filters Stream B: Preparation for backwash testing of Filter B1 Tank 5 in progress

P2A – Filters Stream B: Internal testing for backwashing at Filter B1 Tank 5 in progress.

P2A – Filters Stream B: Internal testing for backwashing at Filter B1 Tank 5 in progress.

P2A – Filters Stream B: Backwash operation for Filter B1 Tank 5 in progress.

P2A –Clarifier Stream A: Preparation for Static Mixer installation at Clarifier A in progress.

P2A –Clarifier Stream A: Installation of inlet penstocks at Clarifier A2 Tank 5 in progress.

P2A –Clarifier Stream A: Installation of inlet penstocks at Clarifier A2 Tank 5 in progress.

P2A –Clarifier Stream A: Installation of Lamellae troughs at Clarifier A1 Tank 3 in progress.

P2A –Clarifier Stream A: Installation of clarifier control panel at Clarifier A2 Tank 5 in progress.

P2A –Clarifier Stream B: Operation of Clarifier B1 Tank 5 for P4-Pumping Exercise in progress.

P2A –Clarifier Stream B: Rectification work for desludging system in progress.

P2A –Clarifier Stream B: Testing of pneumatic actuator for desludging system in progress.

P2A– Thickened Residuals Pumping Station: Lighting & Small Power conduit installation works in progress.

P2A– Thickened Residuals Pumping Station: Pipe painting in progress.

P2A– Thickened Residuals Pumping Station: Installation of decanter feed pipe in progress.

P2A– Residuals Dewatering Building: Casting of roof parapet wall in progress.

P2A– Residuals Dewatering Building: Preparation for installation of Polymer dosing pumps and equipment in progress.

P2A– Residuals Dewatering Building: Installation of polymer preparation system in progress.

P2A– Residuals Dewatering Building: Installation of OH crane in progress.

P2A –Residual Storage Yard: Steel structure installation work in progress.

P2A –Residual Storage Yard: Concreting of foundation slab in progress.

P2A–Treated Water Pumping Station: TWPS/Surge vessels compressor internal test in progress.

P2A–Treated Water Pumping Station: BE1&2 pumping operation for P4 Pumping exercise (25 & 26 Sept 2018).

P2A- Guard House: Excavation for decorative wall construction in progress.

P2A – Overflow 1.2 M Ø Dia. pipe: Construction of manhole in progress.

P2A –Outlet 3.0mØ (CWT to TWPS): Construction of overflow chamber in progress.

P2A– Residual Emergency Lagoon: Sodium silicate application in progress.

P2A – Treated Water 1.90mØ Pipeline: Backfilling in progress.

P2A– M&E External: Cable ducting work for SCADA and telecom cable at Washwater Recovery Plant A in progress.

P2A– M&E External: Installation of sampling pipe near Filter B in progress.

P2A– M&E External: HPRM pipe installation (DN 100) at Residual Thickening Tank in progress.

P2A– M&E External: HPRM pipe installation (DN 400) at Clarifier A in progress.

P2A– M&E External: Cabling work at service trench (Chemical to Washwater Recovery Plant A) in progress.

P2A– M&E External: Installation of fire hydrant at Chlorine Building in progress.

P2A– M&E External: Installation of SCADA Network FO cable started (stream B area).

P2A– M&E External: Construction of external service trench at Filter A in progress.

P2A– M&E External: Construction of external service trench at Clarifier A in progress.

P2A– M&E External: Installation of scour valve in progress.

P2A– M&E External: CWT-TWPS instrument cable installation works in progress.

P2A –Surge Vessel A: Cable termination works in progress.

P2A –Surge Vessel A: Painting works in progress.

P2A –Surge Vessel B: Cable termination works in progress.

P2A –Sewerage: Construction of manhole and pipe laying in progress.

P2A –Sewerage: FDT test for sand bedding sewerage pipe in progress.

P2A – Turfing: Preparation for turfing at Aerator A in progress.

P2A – Roadwork: Laying of subsoil at road 11 (Chemical Building) in progress.

P2A – Roadwork: Laying of kerb at main road (Administration Building) in progress.

P2A – Roadwork: Joint survey for sub grade at Road 4 Stream A in progress.

P2A – Roadwork: CBR test at Carpark B in progress.

P2A – Roadwork: FDT test for road base at Carpark B in progress.

P2A – Roadwork: Spray prime coat at Carpark B in progress.

P2A – Site Visit: Site visit by UTMKL and University of Pretoria on 25/09/2018.

P2A – Site Visit: Site visit by SPAN on 27/09/2018.

P2A – Site Visit: Site visit by SPAN on 27/09/2018.


















































































P2A –Aerator A: Installation of valve actuators in progress.

P2A –Aerator B: Internal inspection for valve actuators in progress.

P2A –Aerator B: Electrical & SCADA panels internal tests in progress.

P2A –Aerator B: Cable termination work for water sampling equipment in progress.

P2A –Administration Building: Installation of sampling pipes at Riser Room in progress.

P2A–Administration Building: Energization preparation – Cleaning up transformers in progress.

P2A –Administration Building: HPRM tapping work (DN100) in progress.

P2A –Administration Building: Installation of carpet at prayer room in progress.

P2A–Chemical Building: Cable glanding works for lime dosing pumps at Plant A in progress.

P2A – Chemical Building: Cable dressing works for OS panel at Lime Plant A in progress.

P2A–Chemical Building: Cable termination works for PACL waste pump Plant A in progress.

P2A – Chemical Building: Cabling works in walk through duct Plant A in progress.

P2A – Chemical Building: Internal testing for lime slurry service tank Plant B in progress.

P2A – Chemical Building: Installation of Fluoride Dust Collector system Plant B in progress.

P2A – Chemical Building: Internal testing for Lime Plant B in progress.

P2A–Chemical Building: Cable dressing works for air dryer and chiller system at Lime Silo Plant B in progress.

P2A–Chemical Building: Installation of automatic open /close valve at lime slurry tank Plant B in progress.

P2A–Chemical Building: Internal testing at Poly Raw Water preparation systems Plant B in progress.

P2A–Chlorine Building: Cable termination for control room Plant A in progress.

P2A – Chlorine Building: Cables termination work for automatic weighting Plant A in progress.

P2A–Chlorine Building: Cable dressing work at drum storage area Plant A in progress.

P2A–Chlorine Building: Installation of external Emergency Shower at Plant B in progress.

P2A–Wash Water Recovery Plant A: Control cable termination works in progress.

P2A–Wash Water Recovery Plant B: Cable termination works for recycle supernatant pumps in progress.

P2A – Filters Stream A: Filter slab installation works at Filter A1 (tank 7) in progress.


P2A – Filters Stream A: Installation of acoustic wall panels at Blower Room in progress.

P2A – Filters Stream A: Cable tray works at PCB A in progress.

P2A – Filters Stream A: BS Lighting & Small Power conduit installation works at Transformer Room in progress.

P2A – Filters Stream A: Installation of penstock at clarified overflow channel in progress.

P2A – Filters Stream A: Alignment/plumb check for SS 1200 penstocks at PCB A holding tank in progress.

P2A – Filters Stream B: Internal testing for indicator valve actuator in progress.

P2A – Filters Stream B: Internal testing for supervisory panel Stream B in progress.

P2A – Filters Stream B: Installation of sampling pipe to test room in progress.

P2A – Filters Stream B: Internal testing for washwater pump VFD panel in progress.

P2A – Filters Stream B: Preparation for energization of PCB B – Testing and inspection of Switchgears in progress.

P2A –Clarifier Stream A: Cable termination at desludging system in progress.

P2A –Clarifier Stream A: Installation of lamella trusses at tank 1B in progress.

P2A –Clarifier Stream A: Installation of desludging system in progress.

P2A –Clarifier Stream A: Cable installation works in progress.

P2A –Clarifier Stream A: Cable tray installation works in progress.

P2A –Clarifier Stream B: Clarifier B2 desludging valve internal functional test in progress.

P2A– Thickened Residuals Pumping Station: Cable termination works at electrical panel in progress.

P2A– Thickened Residuals Pumping Station: Pump grouting works in progress.

P2A – Residuals Dewatering Building: Concreting for roof parapet wall in progress.

P2A – Residuals Dewatering Building: Preparation for plastering at first floor walls in progress.

P2A- Guard House: Ceiling works in progress.

P2A –Residual Storage Yard: Concreting for base slab in progress.

P2A–Treated Water Pumping Station: Pipe painting in progress.

P2A–Treated Water Pumping Station: Preparation for installation of monorail crane in progress.

P2A – TPSH B: Preparation for energization– Testing in progress.

P2A – Elevated walkway A: Construction of slab in progress.

P2A – Overflow 1.2 M Ø Dia. pipe: Construction of manhole in progress.

P2A –Outlet 3.0mØ (CWT to TWPS): Construction of scour valve chamber in progress.

P2A– Residual Emergency Lagoon: Installation of residual transfer pump in progress.

P2A – Treated Water 1.90mØ Pipeline: Backfilling in progress.

P2A– M&E External: Installation of HPRM pipes (DN 400) at Chlorine Building Stream A in progress.

P2A– M&E External: Building Services (CCTV/Door access networks) road crossing works at Store area in progress.

P2A– M&E External: BS road crossing works at Clarifier A in progress.

P2A– M&E External: HPRM pipe installation (FDT – Stream A) in progress.

P2A– M&E External: HPRM pipe installation (Holiday test – Stream A) in progress.

P2A– M&E External: Cabling work at service trench (Chemical to Pre-Chlorine Injection) in progress.

P2A– M&E External: Installation of street lighting poles in progress.

P2A– M&E External: Preparation for filling transformer oil for transformer no.2 in progress.

P2A– M&E External: HPRM hydrostatic test (TWPS – CWT B) for in progress

P2A– M&E External: Installation of washout pipe (DN400) for surge vessel in progress.

P2A – M&E External: Preparation for hydrostatic test (Washwater Recovery B) in progress.

P2A –Surge Vessel A: Cable termination works in progress.

P2A –Surge Vessel B: Pipe installation works in progress.

P2A –Surge Vessel C: Cable termination works in progress.

P2A – Turfing: Turfing on slope between Residual thickening Tank and Aerator A in progress.

P2A – Roadwork: Laying of subsoil pipe at main road (CWT-Pumping Station) in progress.

P2A – Roadwork: Spraying prime coat for road 13 (Chlorine Building) in progress.

P2A – Roadwork: Laying of binder course at main road (Administration Building) in progress.

P2A – Roadwork: Surveying work at Main road (CWT-TNB Substation) in progress.












































































P2A –Administration Building: Delivery of laboratory instruments in progress.

P2A –Administration Building: Installation of lift button and panel door in progress.

P2A –Administration Building: Installation of Command Center console furniture in progress.

P2A –Administration Building: Installation of wall partition and furniture at Administration Manager’s room in progress.

P2A – Chemical Building: Control cable glanding works for chemical preparation system at Potassium Plant A in progress.

P2A–Chemical Building: Control cable glanding works for Poly Raw Water Plant A in progress.

P2A–Chemical Building: Cable dressing works for air compressor at Potassium Permanganate Plant A in progress.

P2A – Chemical Building: Control cable glanding works for Potassium Plant A in progress.

P2A – Chemical Building: Internal checking for building service work at walk through duct Plant A in progress.

P2A – Chemical Building: PAC/Poly-Raw-Water (Instrument/Control) site test Plant B in progress.

P2A – Chemical Building: PAC tank instrumentation/load cell tests Plant B in progress.

P2A – Chemical Building: Internal testing for Lime Plant B in progress.

P2A – Chemical Building: Internal testing for lime dosing pumps Plant B in progress.

P2A–Chemical Building: PAC tank instrumentation test for Plant B in progress.

P2A–Chlorine Building: Cable tray work for automatic weighting Plant A in progress.

P2A P2A– Filters Stream A: Washwater pipe works at Filter A in progress.

P2A – Filters Stream A: Installation of cable trays in progress.

P2A – Filters Stream A: Pre-installation of electrical/control panels in progress.

P2A – Filters Stream B: Internal testing for valve actuator in progress.

P2A – Filters Stream B: Adjusting level of weir plate in progress.

P2A – Wash Water Recovery Plant B: Installation of access walkway in progress.

P2A – Wash Water Recovery Plant B: Cable termination works for submerge pump control panel in progress.

P2A – Filters Stream A: Installation of wall tiles at filtered water channel in progress.

P2A – Filters Stream A: Installation & levelling of Filter Slabs at Tank A3 in progress.

P2A – Filters Stream A: Filter slabs grouting works at Tank A13 in progress.

P2A–Clarifier Control Building B: Clarifier B2 MCC & instrument site test in progress.

P2A –Clarifier Stream A: Installation of sampling pipes in progress.

P2A –Clarifier Stream A: Installation of lamella troughs at Clarifier A5 in progress.

P2A –Clarifier Stream B: Internal testing for actuator in progress.

P2A –Clarifier Stream B: Pipe painting works in progress.

P2A – Filters Stream B: Closing the gap of weir plate at filter tank in progress.

P2A – Filters Stream B: Internal testing for washwater valves in progress.

P2A – Filters Stream B: Cable & panel insulation test at PCB supervisory Panel B in progress.

P2A – Filters Stream B: Internal testing for terminal electrode system in progress.

P2A – Clarifier Control Building B: Installation of battery cells in progress.

P2A – Clear water Tank Control building B: Installation of laboratory furniture and piping work in progress.

P2A – Residuals Dewatering Building: Installation of formwork for roof slab in progress.

P2A – Residuals Dewatering Building: Brickwork level 2 in progress.

P2A – Residuals Dewatering Building: Cable tray works in progress.

P2A- Guard House: Ceiling works in progress.

P2A –Clarifier Stream B: Clarifier B2 MCC & instrument site test in progress

P2A –Clarifier Stream B: Internal testing for Clarifier compress air lines at desludging system in progress.

P2A– Thickened Residuals Pumping Station: Installation of LV & MCC panels in progress.

P2A– Thickened Residuals Pumping Station: Piping works at pumping area in progress.

P2A – Residual Emergency Lagoon: Internal inspection for pump installation inside holding tank in progress.

P2A – Residuals Dewatering Building: Cable tray works in progress.

c

P2A- Guard House: Ceiling works in progress.

P2A –Residual Storage Yard: Fixing rebars for base slab in progress.

P2A–Treated Water Pumping Station: Installation of motor ventilation system in progress.

P2A – Pipe Bridge 2: Laying of rip-rap in progress.

P2A –Outlet 3.0mØ (CWT to TWPS): Installation of suction pipes in progress.

P2A –Outlet 3.0mØ (CWT to TWPS): Construction of scour valve chamber in progress.

P2A – Residuals Dewatering Building: Installation of formwork for roof slab in progress.

P2A – Residuals Dewatering Building: Brickwork level 2 in progress.

P2A– M&E External: Electrical earthing/grounding works at PCB B in progress.

P2A– M&E External: Electrical earthing/grounding works at PCB B in progress.

P2A– M&E External: HPRM tapping work for PAC & Poly Plant A in progress.

P2A – M&E External: Installation of valve actuators at Bukit Enggang line in progress.

P2A –Surge Vessel A: Piping and cable termination works in progress.

P2A –Surge Vessel B: Piping works in progress.

P2A –Surge Vessel C: Cable termination works for surge vessels in progress.

P2A – River Protection: Turfing on slopes in progress.

P2A – Turfing: Turfing in progress.

P2A – roadwork: Laying of subsoil pipe at road 13 in progress.

P2A – Roadwork: Joint survey and FDT test for sub-base level at Carpark B in progress.

P2A – Roadwork: Laying of road base at Carpark B in progress.

P2A – Roadwork: Laying of ACBC in progress.





































































P2A–Admin. Building: Sampling pipes installation at laboratory service trench in progress.

P2A –Administration Building: Internal testing for switchgear panel in progress.

P2A –Administration Building: Delivery of laboratory equipment & instrument in progress.

P2A –Administration Building: Installation ceiling fixed panel at entrance lobby in progress.

P2A – Chemical Building: Fabrication of inlet pipe for lime silo (A) in progress.

P2A – Chemical Building: Electrical control cable glanding works for Lime Plant A in progress.

P2A–Chemical Building: Control cable glanding works for Poly Raw Water Plant in progress.

P2A – Chemical Building: Control cable glanding works for Potassium Plant A in progress.

P2A–Chemical Building: Instrument cable arrangement & dressing works at Lime transfer area.

P2A–Chemical Building: Delivery of fluoride dust collectors.

P2A – Chemical Building: Internal testing of Lime Plant B in progress.

P2A – Chemical Building: Copper tape installation for earthing system in progress.

P2A – Chlorine Building: SCADA/Cable control cables termination work at pant (A) in progress.

P2A – Chlorine Building: Control & instrument cable termination works in progress.

P2A – Chlorine Building: Internal testing at Cholorinator room in progress.

P2A – Chlorine Building: Cable tying and marking at SCADA Control room in progress.

P2A–Wash Water Recovery Plant B: Cable termination for submersible pumps in progress.

P2A–Wash Water Recovery Plant B: Cable termination for sludge pumps in progress.

P2A – Wash Water Recovery Plant B: Anchor block grouting works in progress.

P2A – Wash Water Recovery Plant B: Cable termination works for control panels in progress.

P2A – TPSH Plant B: Busduct fire resistance sealing works at TPSH B in progress.

P2A – Clear Water Tank: Electrical & control cable termination works for CWT 3 & 4 in progress.

P2A – Filters Stream A: Installation of wall tiles at filtered water channel in progress.

P2A – Filters Stream A: Installation of filter slabs at Tank A20 in progress.

P2A – Filters Stream A: Slab levelling works at Filter A17 in progress.

P2A P2A– Filters Stream A: Bitumen application works for at Filter A15 in progress.

P2A – Filters Stream A: Fabrication of cable trays in progress.

P2A – Filters Stream A: Installation of washwater pipes & valves at PCB in progress.

P2A – Filters Stream A: Installation of blower equipment / piping at PCB in progress.

P2A – Filters Stream A: Installation of checkered plate at PCB actuator in progress.

P2A – Generator Building: Switchgear internal testing in progress.

P2A–Clarifier Control Building B: Installation of CCTV and access card in progress.

P2A – Process Control Building Stream A: External painting in progress.

P2A – Process Control Building Stream B: Turfing works in progress.

P2A –Clarifier Stream A: Installation of lamella support bracket at Tank 5 A1 in progress.

P2A –Clarifier Stream A: External painting in progress.

P2A –Clarifier Stream A: Installation of cable trays in progress.

P2A –Clarifier Stream A: Installation of sampling pipes in progress.

P2A –Clarifier Stream A: Preparation for water tightness test at tank 3 in progress.

P2A –Clarifier Stream B: Pipe painting works in progress.

P2A –Clarifier Stream B: Internal testing for flowswitch in progress.

P2A –Clarifier Stream B: Installation of high pressure main pipe in progress.

P2A –Clarifier Stream B: Clarifier sampling pipe works at Clarifier B in progress.

P2A– Thickened Residuals Pumping Station: Installation of centrifuge feed pumps in progress.

P2A – Residual Emergency Lagoon: Transfer pipes installation works in progress.

P2A – Residual Emergency Lagoon: Installation of transfer pipe fittings and valves in progress.

P2A – Residuals Dewatering Building: Brickworks in progress.

P2A – Residuals Dewatering Building: Internal plastering in progress.

P2A- Guard House: Glass windows and door installation in progress.

P2A – Elevated Walkway A: Painting in progress.

P2A –Treated Water Pumping Station: External works in progress.

P2A–Treated Water Pumping Station: Installation of motor ventilation system in progress.

P2A–Treated Water Pumping Station: Cable termination for ventilation system in progress.

P2A–Treated Water Pumping Station: Tightening bolts for valves in progress.

P2A–Treated Water Pumping Station: Cable termination for Mimic Control Panel in progress.

P2A –Stilling Basin: Construction of RC wall in progress.

P2A – Pipe Bridge 1: Painting touch-up works in progress.

P2A – Pipe Bridge 2: Painting touch-up works in progress.

P2A – Overflow Chamber No. 2A: Construction of RC manhole in progress.

P2A –Outlet 3.0mØ (CWT to TWPS): Installation of suction pipes in progress.

P2A – Interconnection 2.2m Ø (Filter A to CWT A): Pipeline No: 1 & 2 laying work in progress.

P2A – Treated Water 1.90mØ Pipeline: Construction of washout chamber in progress.

P2A –Raw Water 3.0mØ Pipeline: Bitumen coating for tee-off pipes at stilling basin in progress.

P2A– M&E External: HPRM PRV setting works in progress.

P2A– M&E External: Installation of HPM pipes (DN 400) at Filter A in progress.

P2A – M&E External: Installation of cover slab for service trench in progress.

P2A – M&E External: HPRM (High Pressure Main) pressure tests in progress.

P2A – M&E External: LV electrical earthing works at Generator Building in progress.

P2A – M&E External: Filtered water pipe pre-inspection in progress.

P2A – M&E External: Installation of CCTV under transmission line in progress.

P2A –Surge Vessel A: Compress-air piping (DN80) & cabling works in progress.

P2A –Surge Vessel B: Surge vessel level instrument installation works in progress.

P2A – Service Trench: Construction of service trench to Residual Thicknening Tank in progress.

P2A – River Protection: Installation of softrock in progress.

P2A – Sewerage: Construction of manhole at Chemical Building in progress.

P2A – Sewerage: Construction of manhole at Store in progress.

P2A – Roadwork: FDT test for sub-base at road 5 in progress.

P2A – Roadwork: Laying of sand for sub base of road 6 in progress.















































































P2A – Aerator A: Installation of manhole cover in progress.

P2A – Aerator B: Pattern test in progress.

P2A – Administration Building: Installation of fire alarm system in progress.

P2A – Administration Building: Preparation for installation of laboratory instruments.

P2A – Administration Building: Fixing of chairs at theater room in progress.

P2A –Chemical Building: Instrument cable dressing works at Potassium A in progress.

P2A – Chemical Building: Cable termination works for lime mixing tank (A) in progress.

P2A – Chemical Building: Internal testing of Polyelectrolyte Plant panel system in progress.

P2A–Chemical Building: Cable termination for polyelectrolyte receiver system in progress.

P2A – Chemical Building: Cable termination for lime dosing pumps (A) in progress.

P2A–Chemical Building: Internal testing of polyelectrolyte preparation system in progress.

P2A–Chemical Building: Cable termination for fluoride preparation system (A) in progress.

P2A – Chemical Building: Cable termination for poly residual dosing pumps (A) in progress.

P2A – Clear Water Tank: Installation of static mixer at tank 2 in progress.

P2A – Clear Water Tank: Installation of inlet penstocks at CWT / CCT (Tank 1 & 2) in progress

P2A – CWT Control Building Stream A: External painting work in progress.

P2A – CWT Control Building Stream B: Preparation for installation of cable trays in progress.

P2A – Chlorine Building: Piping installation for evaporator system plant (B) in progress.

P2A – Chlorine Building: Cabling works for scrubber plant (A) in progress.

P2A – Chlorine Building: Cabling works for chlorinator system plant (A) in progress.

P2A – Chlorine Building: SCADA/Control cable termination works at Plant (A) in progress.

P2A–Wash Water Recovery Plant B: Cable glanding & termination works in progress.

P2A–Wash Water Recovery Plant B: Pipe and valve painting works in progress.

P2A – Wash Water Recovery Plant B: Installation of service water pipe in progress.

P2A – Wash Water Recovery Plant B: Cable termination works for control panels in progress.

P2A – Pre-Chlorine Injector House B: Cabling termination for power panel in progress.

P2A – Filters Stream A: Installation of floor tiles at filtered water channel in progress.

P2A – Filters Stream A: Checking level and alignment for filter slabs at A14 & A16 in progress.

P2A – Filters Stream A: Installation of small power and lighting in progress.

P2A – Filters Stream A: Installation of filter slabs at tank A11 in progress.

P2A – Filters Stream A: Installation of transformer at PCB in progress.

P2A – Filters Stream A: Washwater pipe installation works at Filter A in progress.

P2A – Filters Stream A: Washwater valve installations at Filter A in progress.

P2A – Filters Stream B: Handrailing painting touch-up works in progress.

P2A – Filters Stream B: Cable termination for level electrode in progress.

P2A – Filters Stream B: Filter media stone charging at Tank 1 in progress.

P2A – Filters Stream B: Filter media sand charging at Tank 1 in progress.

P2A – Clarifier Control Building A: External painting works in progress.

P2A–Clarifier Control Building B: Internal testing for LCP & MCC panels in progress.

P2A – Clear Water Tank Control Building B: Instrument cabling works to CWT 3 &4 in progress.

P2A – Residual Emergency Lagoon: C&S external works in progress.

P2A – Process Control Building Stream A: Installation of aluminum window panels in progress.

P2A – Process Control Building Stream B: External architectural touch-up works in progress.

P2A –Clarifier Stream A: Installation of desludging pipes at Tank B3 in progress.

P2A –Clarifier Stream A: Prepare for water tightness test at inlet channel in progress.

P2A –Clarifier Stream A: Preparation for water tightness test at tank A3 in progress.

P2A –Clarifier Stream B: Pattern test for lamella truss tank A4 in progress.

P2A–Clarifier Stream B: Painting work to pipes in progress.

P2A – Residuals Dewatering Building: Structural works in progress.

P2A– Thickened Residuals Pumping Station: External painting in progress.

P2A- Guard House: Plastering work in progress.

P2A – Elevated Walkway A: Installation of handrailing in progress.

P2A –Stilling Basin: Fixing outlet tee for WTP Phase 2 in progress.

P2A –Treated Water Pumping Station: External painting works in progress.

P2A–Treated Water Pumping Station: Installation of motor ventilation system in progress.

P2A–Treated Water Pumping Station: Piping works for compressor system in progress.

P2A–Treated Water Pumping Station: Actuator cable termination works in progress.

P2A–Treated Water Pumping Station: Tightening bolts for non-return valve in progress.

P2A–Treated Water Pumping Station: Surge vessels compressor cabling works in progress.

P2A – Pipe Bridge 1: Construction of anchor block in progress.

P2A – Pipe Bridge 2: Painting in progress.

P2A – Overflow Chamber No. 2A: Construction of RC manhole in progress.

P2A – Overflow Manhole 12: Construction of RC manhole in progress.

P2A –Outlet 3.0m Ø (CWT to TWPS): Installation of suction pipes in progress.

P2A – Interconnection 2.2m Ø (Filter A to CWT A): Pipeline No: 1 &2 laying work in progress.

P2A–Treated Water 1.90m Ø MS Pipe: Fixing of PC covers to valve chamber in progress.

P2A – Treated Water 1.90m Ø MS Pipe: Pipe laying in progress.

P2A –M&E External: Installation of HPRM pipes (400Ø) at Clarifier A/ Filter A in progress.

P2A– M&E External: Installation of CWT – Admin Building sampling pipes in progress.

P2A – M&E External: Installation of PRV and HPRM pipes for Washwater B in progress

P2A –Surge Vessel A: Installation of Bukit Enggang Surge Vessels piping system in progress.

P2A –Surge Vessel B: Installation of Bukit Enggang Surge Vessels piping system in progress.

P2A – M&E External: HPRM tapping & PRV systems installation in progress.

P2A – Sewerage: Laying of clay pipe at Road 5 in progress.

P2A – Sewerage: Construction of inspection chamber in progress.

P2A – Service Trench: Construction of service trench to Clarifier (A) in progress.

P2A – M&E External: Installation of street lighting along the road 1 in progress.

P2A – M&E External: Surge vessel / instrument cabling works started at surge vessel area.

P2A – River Protection: Installation of softrock in progress.

P2A – Turfing: Turfing at Clarifier B area in progress.

P2A – Roadwork: FDT test at road 2 in progress.

P2A – Roadwork: CBR test at road 3 in progress.



















































































P2A – Administration Building: final touch-up for architectural work in progress.

P2A – Administration Building: CCTV signal cabling works in progress.

P2A – Administration Building: Installation of laboratory furniture / benches in progress.

P2A – Administration Building: Cable termination for lighting and small power in progress.

P2A – Administration Building: Installation of granite floor tiles at ramp area in progress.

P2A – Administration Building: SCADA UPS cabling works in progress

P2A – Administration Building: Mock-up installation for piping at Laboratory in progress.


P2A –Chemical Building: Internal testing for Poly Raw Water system (B) in progress.

P2A – Chemical Building: Dosing pumps calibration at Poly RW & PAC Plant in progress.

P2A – Chemical Building: Cable termination for Fluoride control panels (B) in progress.

P2A–Chemical Building: Installation of fire hydrant (B) in progress.

P2A – Chemical Building: Cable termination for lime dosing pumps (A) in progress

P2A–Chemical Building: Installation of electrical panel at Potassium control room in progress.


P2A – Chemical Building: Installation of cable trays at Lime Silo (A) in progress.

P2A – Clear Water Tank: Installation of Hosedown pipes at CWT Tank 1 & 2 in progress.

P2A – Clear Water Tank: Preparation for installation of penstocks at tank 1 in progress.

P2A – CWT Control Building Stream A: External painting work in progress.

P2A – CWT Control Building Stream B: Installation of cable trays in progress.

P2A – Chlorine Building: Cable termination works for chlorinators in progress.

P2A – Chlorine Building: Cabling works at Chlorine Plant A in progress.

P2A–Wash Water Recovery Plant B: Cabling works for penstock/actuators in progress.

P2A–Wash Water Recovery Plant B: Fixing of submersible mixer at holding tank in progress.

P2A – Wash Water Recovery Plant B: Cable installation works for washwater pumps in progress.

P2A – Wash Water Recovery Plant B: Cable installation for washwater control panel in progress.

P2A – Pre-Chlorine Injector House A: External service trench works in progress.

P2A – Pre-Chlorine Injector House B: Cable termination work for Injector MCC in progress.

P2A – Filters Stream A: Installation of glass handraling in progress.

P2A – Filters Stream A: Installation of silencers and acoustic doors at Blower Room in progress.

P2A – Filter Stream A: Rendering to filtered water channel in progress.

P2A – Filters Stream A: Installation of floor tiles at PCB in progress.

P2A – Filters Stream A: Installation of filter slab at tank A19 in progress.

P2A – Filters Stream A: Installation of cable trays in progress.

P2A – Filters Stream B: Cable termination at upper Filter Gallery in progress.

P2A – Filters Stream B: Internal testing for Filter MCC in progress.

P2A – Clarifier Control Building A: External painting works in progress.

P2A–Clarifier Control Building B: Internal testing for Air Compressor Control Panel in progress.

P2A – Workshop: Air pressure test for water reticulation pipe in progress.

P2A – Residual Emergency Lagoon: Installation of inlet penstocks in progress.

P2A – Process Control Building Stream A: Installation of aluminum window panels in progress.

P2A – Process Control Building Stream B: External architectural works in progress.

P2A – Clarifier Stream A: Water tightness test at Tank A3 in progress.

P2A–Clarifier Stream A: Water tightness test at mixing channel in progress.

P2A –Clarifier Stream A: Installation of desludging pipes at Tank B3 in progress.

P2A –Clarifier Stream B: Installation of Fiber Optics Patch Panels in progress.

P2A–Clarifier Stream B: Fabrication of stainless steel staircase in progress.

P2A–Clarifier Stream B: Internal testing for electric actuator by supplier in progress.

P2A – Generator Building: Cable dressing works at Fresh Air Fans Room in progress.

P2A – Generator Building: Re-painting epoxy flooring in progress.

P2A – TPSH B: Finish coating work for inert gas in progress.

P2A – TPSH B: Internal testing between TPSH B and Chemical Building connection in progress.

P2A – Residuals Dewatering Building: Structural works in progress.

P2A– Thickened Residuals Pumping Station: Water tightness test for tank 2 in progress.

P2A- Guard House: Installation of MS frames for roofing system in progress.

P2A – Elevated Walkway A: Construction of walkway slab in progress.

P2A –Stilling Basin: Fixing rebars for walls in progress.

P2A-Residual Thickening Tank: Internal testing for scraper blade rotation in progress.

P2A –Treated Water Pumping Station: External painting works in progress.

P2A–Treated Water Pumping Station: Installation of motor ventilation system in progress.

P2A–Treated Water Pumping Station: Testing of motor pump control panel in progress.

P2A–Treated Water Pumping Station: Installation of cable for roof exhaust fans in progress.

P2A – Treated Water Pumping Station: Internal testing for 6.6 kV Switchboard in progress.

P2A–Treated Water Pumping Station: Cable termination for air compressor control panel.

P2A – Pipe Bridge 1: Installation of Phase 2 raw water pipes in progress.

P2A – Pipe Bridge 2: Installation of Phase 2 raw water pipes in progress.

P2A – Overflow Chamber No. 2A: Construction of RC manhole in progress.

P2A – Inlet Chamber A2: Construction of RC manhole in progress.

P2A –Interconnection 2.2m Ø (Clarifier A to Filter A): Pipe laying work in progress.

P2A – Interconnection 2.2m Ø (Filter A to CWT A): Pipe laying work in progress.

P2A–Treated Water 1.90m Ø MS Pipe: Preparation for flowmeter installation in progress.

P2A – Treated Water 1.90m Ø MS Pipe: Pipe laying in progress.

P2A –M&E External: Installation of HPRM pipes (400Ø) at Emergency Lagoon area in progress.

P2A – M&E External: Installation of Fire Hydrant pipes (150Ø) for Filter B in progress.

P2A– M&E External: Installation of fire hydrant pipes (150Ø) for Generator Building in progress.

P2A – M&E External: Installation of PRV and HPRM pipes for Washwater B in progress.

P2A –Surge Vessel A: Installation of Bukit Enggang Surge Vessels piping system in progress.

P2A –Surge Vessel B: Installation of Bukit Enggang Surge Vessels piping system in progress.

P2A –Surge Vessel C: Installation of Hulu Langat Surge Vessels in progress.

P2A – M&E External: HPRM leakage tests at pumping main tapping points in progress.

P2A – Sewerage: Sewerage manhole installation (TNB switching station) in progress.

P2A – Sewerage: MP test at manhole location (Administration Building) in progress.

P2A – Service Trench: Construction of service trench to Clarifier (A) in progress.

P2A – M&E External: Laying of street lighting cable along the main road in progress.

P2A – M&E External: Submain cable laying works for Washwater B in progress.

P2A –River Protection: Installation of softrock in progress.

P2A – Turfing: Turfing at Clarifier B area in progress.

P2A- Roadwork: Joint survey for sub grade for road 4 in progress.

P2A- Roadwork: FDT test for sub-base of road 4 in progress.



























































































P2A – Aerator Stream B: Internal testing for Water Monitoring Rack in progress.

P2A – Aerator Stream B: Pipe installation for pre-chlorine dosing pump in progress.

P2A – Administration Building: Installation of laboratory analyzer rack in progress.

P2A – Administration Building: Installation of fixed furniture at laboratory room in progress.

P2A – Administration Building: Installation of granite tiles at lobby area in progress.

P2A – Administration Building: Installation of glass handrailing in progress.

P2A – Administration Building: Installation of Historian & Web and Database Server in progress.

P2A – Administration Building: Installation of wash basin accessories and fittings in progress.

P2A – Chemical Building: External architectural work in progress.

P2A – Chemical Building: Functionality/control test in progress for lime dosing system (B).

P2A– Chemical Building: Installation of Potassium Permanganate Preparation (B) in progress.

P2A –Chemical Building: Epoxy paint at Lime Plant drive through area in progress.

P2A – Chemical Building: Internal testing for Lime Plant Control Room (B) in progress.

P2A – Chemical Building: Internal testing for Lime Service Pump system (B) in progress.

P2A–Chemical Building: Installation of high pressure main at walk through duct (B) in progress.

P2A – Chemical Building: Lighting & small power works at walk through duct (B) in progress.

P2A – Chemical Building: Installation of cable trays at walk through duct (A) in progress.

P2A – Chemical Building: Cable termination for Fluoride Transfer Pump (B) in progress.

P2A – Clear Water Tank: Installation of hose down pipes for CWT 3&4 in progress.

P2A – Clear Water Tank: Installation of penstock at CWT tank 3 in progress.

P2A – CWT Control Building Stream A: External painting work in progress.

P2A – CWT Control Building Stream B: Lightning & small power work in progress.

P2A – Chlorine Building: Cable termination for LCP & SCADA control panels in progress.

P2A – Chlorine Building: Cable termination for ventilation fan motor starter in progress.

P2A–Wash Water Recovery Plant B: Installation of SV and supernatant pumps in progress.

P2A – Wash Water Recovery Plant B: Installation of residual submersible pumps in progress.

P2A – Wash Water Recovery Plant B: Installation of cable trays in progress.

P2A – Post-Chlorine Injector House B: Installation of dosing pipes and valves in progress.

P2A – Pre-Chlorine Injector House A: M&E works in progress.

P2A – Pre-Chlorine Injector House B: Installation of DB, hose-down pipe and PRV in progress.

P2A – Filters Stream A: Installation of glass handraling in progress.

P2A – Filters Stream A: Installation of wall tiles at PCB holding tank in progress.

P2A – Filter Stream A: Rendering for filtered water channel in progress.

P2A – Filters Stream B: Painting work for filtered water outlet main in progress.

P2A – Filters Stream B: Installation of drainage pumps and piping works in progress.

P2A – Filters Stream B: Weir plate adjustments in progress.

P2A – Clarifier Control Building A: Preparation for painting in progress.

P2A–Clarifier Control Building B: Internal testing for Clarifier MCC in progress

P2A – Workshop: Lighting & small power works in progress.

P2A – Store: Preparation for hydrostatic test for service water system in progress.

P2A – Process Control Building Stream A: Plastering works in progress.

P2A – Process Control Building Stream B: External architectural works in progress.

P2A – Clarifier Stream A: Watertightness test at tank A1T3 in progress.

P2A –Clarifier Stream B: Cable termination works at Poly Distribution Box in progress.

P2A –Clarifier Stream B: Internal testing for water flow at overflow chamber in progress.

P2A –Clarifier Stream B: Internal testing for Clarifier LCP system in progress.

P2A–Clarifier Stream B: Internal testing and setting of the Flocculator Mixers in progress.

P2A–Clarifier Stream B: Lighting & small power works in progress.

P2A – Generator Building: Installation of acoustic wall and ceiling panels in progress.

P2A – Generator Building: Cable termination work in progress.

P2A – TPSH-A: Pressure & insulation test of HT panels in progress.

P2A – TPSH-A: Fabrication & installation of Busbar in progress.

P2A – Residual Emergency Lagoon: Installation of inlet penstocks in progress.

P2A –Residuals Dewatering Building: Construction of RC columns and slabs in progress.

P2A – Thickened Residuals Pumping Station: Installation of overhead crane in progress.

P2A- Guard House: Installation of MS frames for roofing system in progress.

P2A – Elevated Walkway A: Construction of RC slab in progress.

P2A –Stilling Basin: Installation of cast-in pipes in progress.

P2A –Treated Water Pumping Station: External painting works in progress.

P2A–Treated Water Pumping Station: Installation of motor access platforms in progress.

P2A –Treated Water Pumping Station: Control cable dressing & tagging works in progress.

P2A–Treated Water Pumping Station: Installation of motor access platforms in progress.

P2A – Treated Water Pumping Station: Motor ventilation ducting works in progress.

P2A – Treated Water Pumping Station: Cable termination at air compressor bay in progress.

P2A – Treated Water Pumping Station: Installation of HL Pump accessories in progress.

P2A – Pipe Bridge 1: Installation of Phase 2 raw water pipes in progress.

P2A – Pipe Bridge 2: Installation of Phase 2 raw water pipes in progress.

P2A –River Protection: Installation of softrock in progress.

P2A – Raw Water 3.0m Ø MS Pipe: Internal testing for valve actuator in progress.

P2A – Scour Chamber No. 3A: Construction of RC manhole in progress.

P2A – Overflow Chamber No. 2A: Construction of RC manhole in progress.

P2A–Treated Water 1.90m Ø MS Pipe: Installation of valves at flowmeter chamber in progress.

P2A – Treated Water 1.90m Ø MS Pipe: Pipe laying in progress.

P2A –M&E External: Installation of thickener feed pipe (400mmØ) to Washwater A in progress.

P2A – M&E External: Installation of High Pressure Main (400mmØ) at Clarifier B in progress.

P2A – M&E External: Installation of fire hydrant (150mmØ) at Clarifier B in progress.

P2A – M&E External: Installation of High Pressure Main pipe at Surge Vessel area in progress.

P2A –Surge Vessel: Bukit Enggang Surge Vessels piping works in progress.

P2A – Sewerage: Manhole installation (TNB switching station) in progress.

P2A – M&E External: Installation of 6.6kV HT Cables (Stream B Loop) in progress.

P2A- Roadwork: Laying of street lighting cable along the main road in progress.

P2A- Roadwork: Installation of road kerb at carpark area in progress.

P2A- Roadwork: Construction of RC footing and stump for car park cover in progress.





















































































P2A – Aerator Stream B: Cabling works in progress.

P2A – Aerator Stream B: Raw water flowmeter pedestal panel installation in progress.

P2A – Administration Building: Installation of glass railing in progress.

P2A – Administration Building: Installation of fixed glass panels in progress.

P2A – Administration Building: Installation of built-in cabinets at General Office in progress.

P2A – Administration Building: Installation of stainless steel hand railing in progress.

P2A – Administration Building: Installation of inert gas at cylinder room in progress.

P2A – Administration Building: Light fittings installation works at lobby area in progress.

P2A – Chemical Building: External architectural work in progress.

P2A – Chemical Building: Cabling works at Lime Service Tank dosing area in progress.

P2A– Chemical Building: Firefighting System installation works in progress.

P2A – Chemical Building: Load cell cabling works for Lime Silo in progress.

P2A – Chemical Building: Cable termination works at Lime Plant Control Room in progress.

P2A – Chemical Building: Applying FRP lining on internal wall in progress.

P2A – Chemical Building: Panel testing at Potassium Permanganate Plant MCC in progress.

P2A – Chemical Building: Installation of waste pipe (Stream B) in progress.

P2A – Clear Water Tank: Coating thickness test (tank 4) in progress.

P2A – Clear Water Tank: Installation of subsoil pipe and cordrain in progress.

P2A – CWT Control Building Stream A: External plastering work in progress.

P2A – CWT Control Building Stream B: External painting in progress.

P2A – Chlorine Building: LCP & SCADA (control) cable termination works in progress.

P2A – Chlorine Building: Instrument / detector cable termination works in progress.

P2A – Wash Water Recovery Plant A: Cabling works in progress.

P2A– Wash Water Recovery Plant B: Installation of cable trays in progress.

2A – Pre-Chlorine Injector House B: Installation of chemical dosing pipes in progress.

P2A – Filters Stream A: Installation of fixed glass panel in progress.

P2A – Filters Stream A: Installation of fixed glass panel in progress.

P2A – Filters Stream A: External painting in progress.

P2A – Filters Stream B: Concrete surface repairing in progress.

P2A – Filter Stream B: Cable gland & termination works for Control Panels in progress.

P2A – Filters Stream B: Bitumen application at Filter B Tank 2 in progress.

P2A – Clarifier Control Building A: Internal plastering works in progress.

P2A–Clarifier Control Building B: Internal cabling & light fitting works in progress.

P2A – Workshop: Installation of lighting and small power cable in progress.

P2A – Store: Internal cabling for firefighting system in progress.

P2A – Process Control Building Stream A: Plastering works in progress.

P2A – Process Control Building Stream B: Painting work and perimeter drain in progress.

P2A – Clarifier Stream A: Installation of PVC sludge pipes at B1T1 in progress.

P2A –Clarifier Stream A: Preparation for water tightness test at Mixing Chanel in progress.

P2A –Clarifier Stream B: Cabling works at Clarifier B1 in progress.

P2A –Clarifier Stream B: Installation of scum pipes in progress.

P2A – Generator Building: Installation of acoustic wall and ceiling panels in progress.

P2A – Generator Building: Installation of ventilation ducting at HV switchroom in progress.

P2A – Generator Building: Building services works at Generator Control room in progress.

P2A – Residual Emergency Lagoon: Installation of penstocks and actuators in progress.

P2A –Residuals Dewatering Building: Construction of RC columns and slabs in progress.

P2A – Thickened Residuals Pumping Station: External plastering in progress.

P2A- Guard House: External plastering works in progress.

P2A –Treated Water Pumping Station: External plastering works in progress.

P2A –Treated Water Pumping Station: Motor platform installation works in progress.

P2A – Treated Water Pumping Station: Relay setting for compressor MCC in progress.

P2A – Treated Water Pumping Station: Control cable termination works in progress.

P2A – Treated Water Pumping Station: HT Cable termination works in progress.

P2A – Treated Water Pumping Station: Mock-up motor ventilation ducting works in progress.

P2A –Stilling Basin: Construction of wall and floor slab in progress.

P2A – Elevated Walkway B: Painting work in progress.

P2A – Pipe Bridge 1: Installation of Phase 2 raw water pipes in progress.

P2A – Pipe Bridge 2: Installation of Phase 2 raw water pipes in progress.

P2A – Overflow Chamber No. 3A: Construction of RC manhole in progress.

P2A – Treated Water 1.90m Ø MS Pipe: Construction of RC flowmeter chamber in progress.

P2A – Treated Water 1.90m Ø MS Pipe: Hacking and removal of hard material in progress.

P2A – Raw Water 3.0m Ø MS Pipe: External painting for interconnection pipe in progress.

P2A –Supernatant 700mmØ MS Pipe: Sand bedding at Aerator A in progress.

P2A – M&E External: Installation of High Pressure Main (DN350) in progress.

P2A – M&E External: High pressure main ring pipe works (DN 150) in progress.

P2A – M&E External: Installation of 6.6kV HT cables (Stream B Loop) in progress.

P2A – M&E External: Installation of 6.6kV HT Cables (Stream B Loop) in progress.

P2A –External M&E: Construction of service trench (Filter A) in progress.

P2A –External M&E: Installation of cover slab service trench (Clarifier B) in progress.

P2A –Surge Vessel: Installation of gate valves for Bukit Enggang Surge Vessels in progress.

P2A – Sewerage: Manhole installation (TNB switching station) in progress.

P2A- Roadwork: Installation of subsoil drain at road 2 in progress.

P2A- Roadwork: FDT test for car park 2 (administration building) in progress.










































































P2A – Aerator Stream B: Electrical & control cable termination works in progress.

P2A – Aerator Stream B: Installation of potassium dosing pipes in progress.

P2A – Administration Building: Fixing of external glass wall in progress.

P2A – Administration Building: Installation of PRV and incoming pipes in progress.

P2A – Administration Building: Mock-up installation for cubicle partition at toilet in progress.

P2A – Administration Building: Installation of stainless steel hand railing in progress.

P2A – Administration Building: Elevator cladding works in progress.

P2A – Administration Building: Installation of wall tiles at toilet area in progress.

P2A – Chemical Building: External architectural work in progress.

P2A – Chemical Building: Cabling works at Lime Service Tank dosing area in progress.

P2A– Chemical Building: Piping works at lime silos area in progress.

P2A – Chemical Building: Installation of Potassium Permanganate Storage System in progress.

P2A – Chemical Building: Cabling works at Lime Plant Control Room in progress.

P2A – Chemical Building: Cabling works at Polyelectrolyte Preparation System in progress.

P2A– TPSH-A: Installation of acoustic wall and ceiling in progress.

P2A– TPSH-B: Installation of acoustic wall and ceiling in progress.

P2A – Clear Water Tank: Installation of penstock in progress.

P2A – Consumer 33kV Switch House: Pressure tests for 33kV Switchgears completed.

P2A – CWT Control Building Stream A: Construction of perimeter drains in progress.

P2A – CWT Control Building Stream B: Lighting and small power works in progress.

P2A – Chlorine Building: External piping works for firefighting system in progress.

P2A – Wash Water Recovery Plant Stream A: Installation of Inlet Penstocks at washwater recovery tanks in progress.

P2A– Wash Water Recovery Plant Stream B: Installation of wash water pipes and valves in progress.

P2A– Wash Water Recovery Plant Stream B: Installation of wash water pipes and valves in progress.

P2A – Pre-Chlorine Injector House A: Painting in progress.

P2A – Filters Stream A: Water tightness test at Tank 6 in progress.

P2A – Pre-Chlorine Injector House B: Installation of pre-chlorine injection pipes in progress.

P2A – Filters Stream A: Brick laying to external architectural feature wall in progress.

P2A – Filters Stream A: Construction of RC support for washwater pipe in progress.

P2A – Filters Stream A: Plastering to brick wall in progress.

P2A – Filter Stream B: Control cable termination works in progress.

P2A – Filters Stream B: Installation of wall and floor tiles inside the filtered water channel in progress.

P2A – Filter Stream B: Installation of glass railing in progress.

P2A – Filter Stream B: Painting to timber railing in progress.

P2A – Clarifier Control Building A: Brickwork in progress.

P2A–Clarifier Control Building B: Piping works in progress.

P2A – Workshop: Installation of architectural roof fascia in progress.

P2A – Store: External piping works for firefighting system in progress.

P2A – Process Control Building Stream A: Plastering works in progress.

P2A – Process Control Building Stream B: Painting work and perimeter drain in progress.

P2A – Clarifier Stream A: Installation of PVC sludge pipes at B1T3 in progress.

P2A –Clarifier Stream A: Preparation for water tightness test at A1T3 in progress.

P2A –Clarifier Stream A: Installation of mixer shaft and fan in progress.

P2A –Clarifier Stream B: Panel & Instrument cable termination works in progress.

P2A – Generator Building: External architectural works in progress.

P2A – Generator Building: Installation of acoustic ceiling panels in progress.

P2A – Generator Building: Cabling works for air conditioning system in progress.

P2A – Generator Building: Cabling works for 6.6kV Main Switchboard in progress.

P2A – Generator Building: Installation of firefighting system in progress.

P2A – Generator Building: Lighting and small power works in progress.

P2A – Bulk Fuel Storage Area: Cabling works at control panel in progress.

P2A – Residual Emergency Lagoon: Earthwork for access road in progress.

P2A –Residuals Dewatering Building: Construction of RC columns and slabs in progress.

P2A – Thickened Residuals Pumping Station: Water tightness test at tank1 in progress.

P2A –Walk Through Duct A: Construction of slabs in progress.

P2A –Transformer Yard: Final inspection prior to energization in progress.

P2A –Treated Water Pumping Station: Construction of apron slabs in progress.

P2A –Treated Water Pumping Station: Installation of firefighting system and cabling works in progress.

P2A – Treated Water Pumping Station: Cable glanding & termination works in progress.

P2A – Treated Water Pumping Station: Control cable termination works in progress.

P2A – Treated Water Pumping Station: Cable glanding & termination works at 415kV main switchboard in progress.

P2A – Pipe Bridge 1: Installation of Phase 2 raw water pipes in progress.

P2A – Elevated Walkway B: Construction of RC piers in progress.

P2A – Overflow 3.0m Ø RC Pipe: Construction of RC sump in progress.

P2A – Overflow Chamber No. 2A: Construction of RC manhole in progress.

P2A – Treated Water 1.90m Ø MS Pipe: Construction of RC flowmeter chamber in progress.

P2A- Guard House: Brickwork in progress.

P2A – Raw Water 3.0m Ø MS Pipe: Installation of interconnection pipe in progress.

P2A – M&E External: Mock up installation for submersible pump in progress.

P2A – M&E External: Cabling works at generator house area in progress.

P2A –External M&E: Clarifier B Sub-Main cable installation in progress.

P2A –External M&E: Laying of High Pressure Main near Administration Building in progress.

P2A- Roadwork: Preparation for sub-grade level in progress.

P2A- Roadwork: Preparation for sub-grade level in progress.

P2A- M & E Equipment Installation: Service Cable testing (for energization of Consumer SS) at SSU completed.

P2A – Site Visit: Site visit by JICA to WTP on 25/01/2018.