P2A – Administration Building: final touch-up for architectural work in progress.
P2A – Administration Building: CCTV signal cabling works in progress.
P2A – Administration Building: Installation of laboratory furniture / benches in progress.
P2A – Administration Building: Cable termination for lighting and small power in progress.
P2A – Administration Building: Installation of granite floor tiles at ramp area in progress.
P2A – Administration Building: SCADA UPS cabling works in progress
P2A – Administration Building: Mock-up installation for piping at Laboratory in progress.
P2A –Chemical Building: Internal testing for Poly Raw Water system (B) in progress.
P2A – Chemical Building: Dosing pumps calibration at Poly RW & PAC Plant in progress.
P2A – Chemical Building: Cable termination for Fluoride control panels (B) in progress.
P2A–Chemical Building: Installation of fire hydrant (B) in progress.
P2A – Chemical Building: Cable termination for lime dosing pumps (A) in progress
P2A–Chemical Building: Installation of electrical panel at Potassium control room in progress.
P2A – Chemical Building: Installation of cable trays at Lime Silo (A) in progress.
P2A – Clear Water Tank: Installation of Hosedown pipes at CWT Tank 1 & 2 in progress.
P2A – Clear Water Tank: Preparation for installation of penstocks at tank 1 in progress.
P2A – CWT Control Building Stream A: External painting work in progress.
P2A – CWT Control Building Stream B: Installation of cable trays in progress.
P2A – Chlorine Building: Cable termination works for chlorinators in progress.
P2A – Chlorine Building: Cabling works at Chlorine Plant A in progress.
P2A–Wash Water Recovery Plant B: Cabling works for penstock/actuators in progress.
P2A–Wash Water Recovery Plant B: Fixing of submersible mixer at holding tank in progress.
P2A – Wash Water Recovery Plant B: Cable installation works for washwater pumps in progress.
P2A – Wash Water Recovery Plant B: Cable installation for washwater control panel in progress.
P2A – Pre-Chlorine Injector House A: External service trench works in progress.
P2A – Pre-Chlorine Injector House B: Cable termination work for Injector MCC in progress.
P2A – Filters Stream A: Installation of glass handraling in progress.
P2A – Filters Stream A: Installation of silencers and acoustic doors at Blower Room in progress.
P2A – Filter Stream A: Rendering to filtered water channel in progress.
P2A – Filters Stream A: Installation of floor tiles at PCB in progress.
P2A – Filters Stream A: Installation of filter slab at tank A19 in progress.
P2A – Filters Stream A: Installation of cable trays in progress.
P2A – Filters Stream B: Cable termination at upper Filter Gallery in progress.
P2A – Filters Stream B: Internal testing for Filter MCC in progress.
P2A – Clarifier Control Building A: External painting works in progress.
P2A–Clarifier Control Building B: Internal testing for Air Compressor Control Panel in progress.
P2A – Workshop: Air pressure test for water reticulation pipe in progress.
P2A – Residual Emergency Lagoon: Installation of inlet penstocks in progress.
P2A – Process Control Building Stream A: Installation of aluminum window panels in progress.
P2A – Process Control Building Stream B: External architectural works in progress.
P2A – Clarifier Stream A: Water tightness test at Tank A3 in progress.
P2A–Clarifier Stream A: Water tightness test at mixing channel in progress.
P2A –Clarifier Stream A: Installation of desludging pipes at Tank B3 in progress.
P2A –Clarifier Stream B: Installation of Fiber Optics Patch Panels in progress.
P2A–Clarifier Stream B: Fabrication of stainless steel staircase in progress.
P2A–Clarifier Stream B: Internal testing for electric actuator by supplier in progress.
P2A – Generator Building: Cable dressing works at Fresh Air Fans Room in progress.
P2A – Generator Building: Re-painting epoxy flooring in progress.
P2A – TPSH B: Finish coating work for inert gas in progress.
P2A – TPSH B: Internal testing between TPSH B and Chemical Building connection in progress.
P2A – Residuals Dewatering Building: Structural works in progress.
P2A– Thickened Residuals Pumping Station: Water tightness test for tank 2 in progress.
P2A- Guard House: Installation of MS frames for roofing system in progress.
P2A – Elevated Walkway A: Construction of walkway slab in progress.
P2A –Stilling Basin: Fixing rebars for walls in progress.
P2A-Residual Thickening Tank: Internal testing for scraper blade rotation in progress.
P2A –Treated Water Pumping Station: External painting works in progress.
P2A–Treated Water Pumping Station: Installation of motor ventilation system in progress.
P2A–Treated Water Pumping Station: Testing of motor pump control panel in progress.
P2A–Treated Water Pumping Station: Installation of cable for roof exhaust fans in progress.
P2A – Treated Water Pumping Station: Internal testing for 6.6 kV Switchboard in progress.
P2A–Treated Water Pumping Station: Cable termination for air compressor control panel.
P2A – Pipe Bridge 1: Installation of Phase 2 raw water pipes in progress.
P2A – Pipe Bridge 2: Installation of Phase 2 raw water pipes in progress.
P2A – Overflow Chamber No. 2A: Construction of RC manhole in progress.
P2A – Inlet Chamber A2: Construction of RC manhole in progress.
P2A –Interconnection 2.2m Ø (Clarifier A to Filter A): Pipe laying work in progress.
P2A – Interconnection 2.2m Ø (Filter A to CWT A): Pipe laying work in progress.
P2A–Treated Water 1.90m Ø MS Pipe: Preparation for flowmeter installation in progress.
P2A – Treated Water 1.90m Ø MS Pipe: Pipe laying in progress.
P2A –M&E External: Installation of HPRM pipes (400Ø) at Emergency Lagoon area in progress.
P2A – M&E External: Installation of Fire Hydrant pipes (150Ø) for Filter B in progress.
P2A– M&E External: Installation of fire hydrant pipes (150Ø) for Generator Building in progress.
P2A – M&E External: Installation of PRV and HPRM pipes for Washwater B in progress.
P2A –Surge Vessel A: Installation of Bukit Enggang Surge Vessels piping system in progress.
P2A –Surge Vessel B: Installation of Bukit Enggang Surge Vessels piping system in progress.
P2A –Surge Vessel C: Installation of Hulu Langat Surge Vessels in progress.
P2A – M&E External: HPRM leakage tests at pumping main tapping points in progress.
P2A – Sewerage: Sewerage manhole installation (TNB switching station) in progress.
P2A – Sewerage: MP test at manhole location (Administration Building) in progress.
P2A – Service Trench: Construction of service trench to Clarifier (A) in progress.
P2A – M&E External: Laying of street lighting cable along the main road in progress.
P2A – M&E External: Submain cable laying works for Washwater B in progress.
P2A –River Protection: Installation of softrock in progress.
P2A – Turfing: Turfing at Clarifier B area in progress.
P2A- Roadwork: Joint survey for sub grade for road 4 in progress.
P2A- Roadwork: FDT test for sub-base of road 4 in progress.