Dec 16
Nov 16
Oct 16
Sep 16
Aug 16

P4 – Reservoir Platform Phase 2: Filling embankment at CH-50 in Progress

P4 – Reservoir Platform Phase 1: Rock excavation at CH350 in progress.

P4 – Reservoir Platform Phase 1: Rock excavation at CH330 in progress.

P4 – Reservoir Platform: Construction of cascading spillway at CH50 in progress

P4 – Reservoir Platform: Close turfing at slope CH70 in progress.

P4 – Reservoir Platform: Rock drilling for blasting works at CH370 in progress.

P4 – Main Flood Detention Pond: Bulk excavation in at CH480 in progress.

P4 – Main Flood Detention Pond: Laying crusher run at slope at CH400 in progress.

P4 – Main Flood Detention Pond: Laying crusher run at slope at CH400 completed

P4 – Main Flood Detention Pond: Construction of inlet structure wing wall in progress.

P4 – Main Flood Detention Pond: Construction of inlet structure wing wall completed

P4 – Main Flood Detention Pond: Construction of inlet RC sump wall in progress.

P4 – Main Access Road: Construction of berm drain at CH400 RHS in progress.

P4 – Main Access Road: Turfing at CH480 LHS in progress.

P4 – Main Access Road: Filling embankment at CH480 LHS in progress

P4 – U-Drain 1800mm x 900mm: Construction of U-Drain in progress.

P4 – Casting yard: Concreting block drain 300mm in progress

P4 – Pipe Storage Yard: Repairing 1900mm pipes in progress.



















P4 – Reservoir Platform Phase 2: Filling embankment at CH-50 in progress

P4 – Reservoir Platform Phase 1 & Phase 2: Filling embankment at CH 260 – CH-50 in progress

P4 – Reservoir Platform Phase 1: Rock blasting at CH250 completed.

P4 – Reservoir Platform Phase 1: Rock excavation at CH250 in progress

P4 – Reservoir Platform Phase 1: Rock excavation at CH350 in progress.

P4 – Reservoir Platform: Construction of berm drain and slope turfing at CH 130 in progress.

P4 – Main Flood Detention Pond: Turfing at slope at CH530 in progress.

P4 – Main Flood Detention Pond: Turfing at slope at CH600 in progress.

P4 – Main Flood Detention Pond: Construction of berm drain at CH500 in progress.

P4 – Main Flood Detention Pond: Casting of inlet structure RC sump base slab in progress.

P4 – Flood Detention Pond A: Removing unsuitable material in progress.

P4 – Flood Detention Pond B: Construction of block drain 300mm at CH340 in progress.

P4 – Flood Detention Pond B: Construction of cascading drain at CH290 in progress.

P4 – Main Access Road: Filling embankment at CH400 RHS in progress.

P4 – Main Access Road: Slope turfing at CH180 RHS in progress.

P4 – Main Access Road: Construction of berm drain at CH470 LHS in progress.

P4 – Main Access Road: Construction of interceptor drain at CH400 LHS in progress.

P4 – Casting yard: Casting of block drain in progress.

P4 – Overflow inlet structure (spillway): Mackintosh Probe test in progress

P4 – Pipe storage yard: Pipe repairing works in progress.





















P4 – Reservoir Platform Phase 1 & 2: Filling embankment at CH 260- CH -20 in progress.

P4 – Reservoir Platform Phase 1 & 2: Filling embankment at CH -50 in progress.

P4 – Reservoir Platform Phase 1 & 2: Trimming slope at CH20 in progress.

P4 – Reservoir Platform Phase 1 & 2: Turfing at slope at CH-30 in progress.

P4 – Reservoir Platform Phase 1: Excavation at CH240 in progress.

P4 – Reservoir Platform Phase 1: Excavation at CH320 in progress.

P4 – Reservoir Platform Phase 2: Rock breaking at CH180 in progress.

P4 – Reservoir Platform Phase 2: Preparation of trial rock blasting at CH 170.

P4 – Reservoir Platform Phase 2: Trial rock blasting at CH 170 completed.

P4 – Reservoir Platform Phase 2: Boring rock for blasting works in progress.

P4 – Main Detention Pond: Site clearing for u-drain in progress.

P4 – Main Detention Pond: Removing Unsuitable Material at CH550 in progress.

P4 – Main Detention Pond: Laying of crasher run for slope protection at CH120 in progress.

P4 – Main Detention Pond: Excavation for berm drain at CH160 in progress.

P4 – Main Detention Pond: Trimming slope at CH600 in progress.

P4 – Main Detention Pond: Turfing at slope at CH600 in progress.

P4 – Main Detention Pond: Reconstruct berm drain (NCR) at CH500 in progress.

P4 – Main Detention Pond: Removing unsuitable material at CH720 in progress.

P4 – Detention Pond B: Spread top soil at CH220 in progress.

P4 – Detention Pond B: Close turfing at slope at CH 150 in progress.

P4 – Main Access Road: Filling embankment at CH460 in progress.

P4 – Main Access Road: Construction of cascading spillway at CH450 in progress.

P4 – Casting yard: Casting of block drain in progress

P4 – Buildtest Laboratory: Tensile and bending test for rebars at independent laboratory.

























P4 – Reservoir Platform Phase 1&2: Filling embankment at CH260 to CH-100 in progress.

P4 – Reservoir Platform Phase 1&2: Filling embankment at CH260 to CH-100 in progress.

P4 – Reservoir Platform: Field density test for filling layer at CH260 to CH-100 in progress.

P4 – Reservoir Platform: Casting of berm drain at Ch-100 in progress.

P4 – Main Access Road: Filling embankment at CH400 in progress.

P4 – Main Flood Detention Pond: Casting of berm drain at CH500 in progress.

P4 – Main Flood Detention Pond: Removing USM in progress.

P4 – Detention Pond B Access: Casting of berm drain in progress.









P4 – Reservoir Platform: Macintosh Probe Testing at reservoir foundation in progress.

P4 – Reservoir Platform: Macintosh Probe Testing at reservoir foundation in progress.

P4 – Package 2A Pipes Storage Yards: Shifting of Pipes from Package 2A to Package 4 area.

P4 – Package 2A Pipe Storage Yards: Shifting of pipes to Package 4 area in progress.

P4 – Package 2A Pipe Storage Yards: Shifting of pipes to Package 4 Platform in progress.

P4 – Package 4 Pipe Bridge Platform: Pipes shifted from Package 2a stored at P4 Platform.

P4 – Site Entrance 2: Delivery of rebar T16 temporary stored at Site Entrance 2 gate.

P4 – Site Entrance 2: Delivery of rebar T16 temporary stored at Site Entrance 2 gate.

P4 – Sediment Basin 2: Slope repairing in progress.

P4 – Sediment Basin 2: Slope repairing completed.

P4 – Sediment Basin 5: Installation of silt fence at Sediment Basin 5 still in progress

P4 – Sediment Basin 4: Installation of silt fence at Sediment Basin 4 in progress.

P4-Earthwork