Pakej 5 : Paip Air Terawat Utama dari Kolam Air Imbangan Bukit Enggang ke Kolam Air Langat Sedia Ada dan Air Terawat Utama dari Loji Rawatan Air Langat 2 ke Kolam Air Imbangan Hulu Langat 2017
P5 – 1.75m Ø Pipeline: Pipe laying work reaching CH3115 at Taman Sri Nanding.
P5 – 2.00m Ø Pipeline: Pipe laying work reaching CH1581 at Jalan Hulu Langat Jaya.
P5 – 2.00m Ø Pipeline: Trench excavation (CH783 to CH793) at Jalan Pahlawan 22/3 in progress.
P5 – 2.00m Ø Pipeline: Backfilling work in progress at Jacking Pit C (Jalan Dato Alias).
P5 – 2.00m Ø Pipeline: Pipe connection to jacking pipe in progress at Pit B (Jalan Dato Alias).
P5 – 2.00m Ø Pipeline: Pipe connection to jacking pipe at Pit A (Jalan Hulu Langat) in progress.
P5 – 2.00m Ø Pipeline: Trench excavation (CH694 to CH714) at Jalan Pahlawan 22/3 in progress.
P 5 – 1.75m Ø Pipeline: Pipe laying work reaching CH4702 at Desa Saujana Langat.
P5 – 1.75m Ø Pipeline: Pipe jacking work (Pit E to Pit D) at Desa Saujana Langat in progress.
P5 – 1.75m Ø Pipeline: Pipe jacking work (Pit C to Pit B) at Desa Saujana Langat in progress.
– 2.00m Ø Pipeline: Pipe composite no.20 for pipe jacking work from Pit C (Ch.2117m) to Pit B (Ch.2207m), currently jacking 58.5m/87m at Jalan Dato Alias
P5 – 1.75m Ø Pipeline: Concrete surround (crossing EKVE) from CH4349 to CH4329 in progress.
P 5 – 2.00m Ø Pipeline: Pipe laying work reaching CH674 at Jalan Pahlawan 22/3.
P5–2.00m Ø Pipeline: Internal welding for composite pipes along Jalan Dato Alias in progress.
P5 – 2.00m Ø Pipeline: Pipe jacking from Pit A to Pit B across Jalan Hulu Langat in progress.
P5 – 2.00m Ø Pipeline: Pipe composite no.20 for pipe jacking work from Pit C (Ch.2117m) to Pit B (Ch.2207m), currently jacking 58.5m/87m at Jalan Dato Alias
P5 – 1.75m Ø Pipeline: Preparation for concrete surround 90⁰ bend at CH4360 (EKVE area).
P5 – 1.75m Ø Pipeline: Construction of Jacking Pit C at CH4819 (Jalan Saujana 1) in progress.
P5 – 1.75m Ø Pipeline: Pipe laying work reaching CH4209 at Kampung Sungai Michu.
P5 – 1.75m Ø Pipeline: Pipe laying work reaching CH2885 at Jalan Intan, Taman Sri Nanding.
P 5 – 2.00m Ø Pipeline: : Pipe jacking work from Pit C to Pit B along Jalan Dato Alias in progress.
P5–2.00mØ Pipeline: Pipe jacking work from Pit A to Pit B accross Jalan Hulu Langat in progress.
P5 –2.00mØ Pipeline: Reinstatement of drain (CH525 -CH610) at Jln Pahlawan 22/3 in progress.
P5 – 1.75m Ø Pipeline: Pipe laying work reaching CH4570 at Desa Saujana Langat – EKVE.
P5 – 1.75m Ø Pipeline: Pipe laying work reaching CH2704 at Taman Sri Nanding.
P5 – 1.75m Ø Pipeline: Pipe laying work reaching CH4580 at Desa Saujana Langat – EKVE.
P5 – 2.00m Ø Pipeline: Pipe jacking work from Pit C to Pit B along Jalan Dato Alias in progress.
P5 – 1.75m Ø Pipeline: Pipe laying work reaching CH4143 at downstream of Sg.Michu.
P5 – 2.00m Ø Pipeline: Discussion with Jalan Pahlawan 22/3 committee members for pipe laying work between CH621 to CH825.
P5 – 1.75m Ø Pipeline: Welding of AV tee for pipe overcrossing Sg.Michu at CH4078 in progress.
P5 – 1.75mØ Pipeline: Preparation for construction of AV Chamber at CH3975 in progress.
P5 – 2.00mØ Pipeline: Trench excavation at Jalan Pahlawan (CH595 to CH605) in progress.
P5 – 2.00mØ Pipeline: Preparation for pipe jacking work at Pit C (Jalan Dato Alias) in progress.
P5 – 2.00m Ø Pipeline: Pipe laying work at Kampung Melaka (CH1849) in progress.
P5 – 2.00m Ø Pipeline: Deepening Pit A for pipe jacking accross Jalan Hulu Langat in progress.
P5 – 2.00mØ Pipeline: Stone pitching work at CH973 to CH974 (Sg.Langat) in progress.
P5 – 2.00mØ Pipeline: Excavation work between CH504 to CH514 at Jalan Pahlawan in progress.
P5 – 2.00m Ø Pipeline : Pipe jacking work at Pit C CH2114 at Jalan Dato Alias in progress.
P5 – 2.00m Ø Pipeline: Road reinstatement at Jalan Mas Jaya (CH2450-CH2425) in progress.
P5 – 1.75m Ø Pipeline: Casting of pile cap for steel truss overcrossing Sg.Michu in progress.
P5 – 2.00m Ø Pipeline : Pipe laying at CH2036 (Kampung Melaka) in progress.
P5 – 2.00m Ø Pipeline : Preparation for pipe jacking work at Jacking Pit C (Jalan Dato Alias).
P5 – 2.00m Ø Pipeline: Gabions and stone pitching for Sg Langat protection works in progress.
P5 – 1.75m Ø Pipeline: Construction of column pier for steel truss overcrossing
(Sg.Michu) at CH4044 in progress.
P5 – 2.00mØ Pipeline: Reinstatement of existing drain at Jalan Mas Jaya in progress.
P5 – 2.00mØ Pipeline: Pipe laying (CH-831 – CH-801) at Persiaran Mahkota Cheras 1 in progress.
P5 – 2.00m Ø Pipeline: Pipe jacking works across Jalan Hulu Langat in progress.
P5 – 1.75m Ø Pipeline: Piling work for washout chamber at Sungai Michu in progress.
P5 – 1.75m Ø Pipeline: Pipe laying work (CH2654) at Jalan Intan in progress.
P5–2.00mØ Pipeline: Backfilling work (CH-831-CH-805) at Persiaran Mahkota Cheras in progress
P5 – 2.00m Ø Pipeline: Preparation for pipe laying work at CH1900 to CH1775 in progress.
P5 – 2.00m Ø Pipeline: Backfilling work (CH2284) at Jalan Mas Jaya in progress.
P5 – 2.00mØ Pipeline: Reinstatement of road kerb at Persiaran Mahkota Cheras 1 in progress.
P5 – 2.00mØ Pipeline: Pipe laying at CH2356 (Jalan Mas Jaya) in progress.
P5 – 2.00mØ Pipeline: Pit excavation for preparing jacking pit at Jalan Dato Alias in progress.
P5 – 2.00m Ø Pipeline: Mackintosh Probe test between CH1825 to CH1895 in progress.
P5 – 2.00mØ Pipeline: Pipe laying work at CH-722 (Persiaran Mahkota Cheras 1) in progress.
P5 – 1.75mØ Pipeline: Ppipe laying work from CH2403 at Jalan Delima in progress.
P5 – 1.75mØ Pipeline: Excavation for S-Bend at CH2473 (Jalan Delima) in progress.
P5 – 2.00m Ø Pipeline: Pipe laying at CH-737 (Persiaran Mahkota Cheras 1) in progress.
P5 – 2.00mØ Pipeline: Construction of receiving pit for pipe jacking across Jalan Hulu Langat.
P5 – 2.00m Ø Pipeline: Construction of washout chamber at CH2875 in progress.
P5 – 2.00mØ Pipeline: Pipe laying work at CH2350 (Jalan Mas Jaya) in progress.