P6 – 1.50m ⌀ Pipeline: Pipe Laying at CH2030m – CH2090m at Jalan Indah Utama in progress.

P6 – Jalan Indah Utama: Site visit by MPAJ’s officers at CH2030.

P6 – 1.50m ⌀ Pipeline: Pipe Laying at CH2090m – CH2140m at Jalan Indah Utama in progress.

P6 – Jalan Indah Utama: Site Inspection with Traffic Light Controller (MPAJ’s Panel Contractor).

P6 – Buildcon Ampang: Concrete Cube compression test 7days for Thrust Block in progress.

P6 – 1.50m ⌀ Pipeline: Concreting work for Thrust Block (HB) at CH 961 in progress.







P6 – Taman Bukit Indah: Road diversion at Jalan Indah Utama in progress.

P6 – Taman Bukit Indah: Unloading of 1.50m ⌀ Pipe at Jalan Indah Utama in progress.

P6 – Taman Bukit Indah: Piloting work at Jalan Indah Utama witnessed by TNB in progress.

P6 – 1.50m ⌀ Pipeline: Pipe Laying at CH1686 – CH1688 at Jalan Indah Utama in progress.

P6 – 1.50m ⌀ Pipeline: Pipe Laying at CH1686 – CH1688 at Jalan Indah Utama in progress.

P6 – CSRK-KTAT Site Office: Technical Meeting No.9/2016 in progress.

P6 – 1.50m ⌀ Pipeline: Pipe Laying at CH CH1688 – CH1703 at Jalan Indah Utama in progress.

P6 – Hanson Cheras Quarry: Marshall Test in progress









P6– Sungai Ampang : Installation of Air Valve Tee (CH900) in progress.

P6– Sungai Ampang : Preparation of S Bend (CH850) in progress.

P6– Sungai Ampang : Pipe Laying work (CH820) in progress.

P6– Sungai Ampang : MPAJ Site Visit (CH800m).

P6– Batching Plant : Concrete cube test trial mix G25 (Buildcon Ampang)

P6– Taman Kosas: Erection of hoarding and barrier along (CH 1700-CH1600) completed.







P6 – Sungai Ampang : Site Clearing and Excavation for access road at CH350 in progress.

P6 – Sungai Ampang : Weekly toolbox meeting in progress.

P6 – Sungai Ampang : Pipe Laying work at CH390 in progress.

P6 – Sungai Ampang : Pipe Laying work at CH370 in progress.





P6 – 1.5m Ø Pipeline: Pipe delivery in progress at CH 850.

P6 – 1.5m Ø Pipeline: Fittings delivery in progress at CH 600.

P6 – 1.5m Ø Pipeline: Lab test for Welders Qualification Test.

P6 – 1.5m Ø Pipeline: Lab test for Welders Qualification Test.

P6 – 1.5m Ø Pipeline: Pegging of pipeline alignment at CH 450 in progress.