Open Menu
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Pakej 6 : Paip Air Terawat Utama dari Kolam Air Ampang ke Kolam Air AU3 2017
print
2020
2019
2018
2017
2016
Dec 17
Nov 17
Oct 17
Sep 17
Aug 17
Jul 17
Jun 17
May 17
Apr 17
Mar 17
Feb 17
Jan 17
P6 – HSSE: HSSE weekly toolbox meeting at Jalan 1, AU3 Keramat (DBKL Area).
P6 – 1.50m ⌀ Pipeline: Joint survey with Bridgex and KMU for pipe alignment at Jalan AU3.
P6 – 1.50m ⌀ Pipeline: Pipe laying in progress at CH8450 to CH8460 along Jalan 1.
P6 –1.50m ⌀ Pipeline: Piloting work in progress at CH9090 (Jalan 10/56).
P6 – 1.50m ⌀ Pipeline: Piloting work in progress at CH9200 (Jalan AU3 Keramat).
P6 – 1.50m ⌀ pipeline: Concrete surround at CH2225 to CH2215 (Jalan Bukit Indah) in progress.
P6 – Laksana Wibawa Factory: Pre-delivery inspection for 1.50m ⌀ pipes in progress.
P6 – 1.50m ⌀ Pipeline: Pipe laying in progress at CH8490 to CH8500 along Jalan 1.
P6 – MPAJ: Progress Presentation to MPAJ for all projects under MPAJ.
P6 – TNB HQ: Coordination meeting with TNB HQ (Operation and Maintenance Department).
P6 – Jalan Memanda 27: Mackintosh probe test in progress.
P6 – Jalan Bukit Indah: 24 Hour leakage test for jacking pipeline completed.
P6 – CSRK-KTAT P6: Technical Meeting No. 12/2017.
P6 – CSRK-KTAT P6: HSSE Committee Meeting.
P6 – Apartment Permai Puteri: Meeting with Lawyer and JMB Permai Puteri.
P6 – Jalan Kempas: Delivery of Butterfly Valve for interconnection chamber.
P6 – MPAJ: Discussion with MPAJ Engineering Department on 23 October 2017.
P6 – 1.50m ⌀ Pipeline: Pipe laying in progress at SUKE Interface Area (Sg. Ampang CH4994).
P6 – Behind Rajaraswari Temple: Site Visit with SUKE and KTAT on interfacing issue.
P6 – Sg. Ampang: On-site Safety Training about confined space and excavation work.
P6 – Koperasi Anak Selangor: Meeting with Kosas on 26 October 2017 regarding the IRDK issue.
P6 – CSRK-KTAT P6: Technical Meeting No. 11/2017 in progress.
P6 – CSRK-KTAT P6: HSSE Committee Meeting No. 10/2017 in progress.
P6 – 1.50m ⌀ Pipeline: End Cap at receiving pit for pressure test at CH2345.
P6 – Sg. Ampang: Delivery of pipes in progress.
P6 – Buildcon Ampang: Cube Compression Test in progress.
P6 – LRAL2 KTAT P6 Site Office: Technical Meeting No.10/2017 on 28 Sep 2017.
P6 – LRAL2 KTAT P6 Site Office: HSSE Committee Meeting No.9/2017.
P6 – SK Ampang: Public Engagement for Zone C (Jalan Kempas) on 30 Sep 2017.
P6 – Sg. Ampang: Site Clearing in progress for CH5100 to CH5300.
P6 – PIMSB P6 Site Office: Risk Management Committee Meeting No. 05/2017.
P6 – 1.50m ⌀ Pipeline: Pipe laying in progress at SUKE interface area (Sg. Ampang CH4640).
P6 – Jalan Bukit Indah: Internal welding for composite jacking pipe in progress.
P6 – CSRK-KTAT P6 Site Office: Joint Site evaluation for IPC17.
P6 – Jalan Bukit Belacan: Interfacing site meeting with EKVE.
P6 – Sg. Ampang: Interfacing site meeting with SUKE.
P6 – Sg. Ampang: Delivery of MS Pipes (1500mm diameter) in progress.
P6 – MPAJ: Meeting with MPAJ (Engineering Department), CSRK-KTAT and PIMSB.
P6 – Jln. Kosas Utama: Erection or temporary full barrier and hoarding in progress.
P6 – Sg. Ampang: Refreshment induction to all worker at new site area.
P6 – P6 Site Office: Safety Committee Meeting No. 7/2017
P6 – CSRK-KTAT P6 Site Office: Meeting No. 3 for preparation of Zone C Public Engagement.
P6 – Sg. Ampang: Mobilization and Site Clearing at CH4600 to CH4800 in progress.
P6 – 1.50m ⌀ Pipeline: Pipe laying work in progress at Sg. Ampang (CH4600 to CH4650).
P6 – JKR Gombak: Meeting with JKR Gombak, CSRK-KTAT and PIMSB.
P6 – Jalan Kosas 2: Preparation for laying of Crusher Run at CH3050 to CH3100 in progress.
P6 – 1.50m ⌀ Pipeline: Pipe Delivery in progress at CH4925 to CH4950 (Sg. Ampang).
P6 – PIM Site Office: HSSE Committee Meeting No.6/2017.
P6 – Air Selangor Gombak Office: Meeting with Air Selangor at Bandar Baru Selayang.
P6 – JKR Gombak Office: MRR2 Coordination Meeting.
P6 – Jalan Kosas 2: Laying of crusher run (roadbase) along CH 3130 to CH3170 in progress.
P6 – Jalan Bukit Indah Utama: Construction of receiving pit at CH2346 in progress.
P6 – Jalan Kosas 2: Erection of barriers and hoardings in progress.
P6 – 1.50 m ⌀ Pipe: Pre-delivery inspection for MS pipes at Laksana Wibawa Factory.
P6 – 1.50m ⌀ Pipeline: Preparation for laying of 22˚ bend at CH3078 (Jalan Kosas 2) in progress.
P6 – CSRK-KTAT Site Office: Technical Meeting No.6/2017
P6 – Buildcon Ampang: Concrete cube compression test for Thrust Block (7 days).
P6 – Jalan Bukit Indah: Sheet piles installation for jacking pit at CH2307 in progress.
P6 – Jalan Bukit Indah: Excavation for jacking pit at CH2307 in progress.
P6 – 1.50m ⌀ Pipeline: Pipe laying work at CH2468 along Jalan Kosas Utama in progress.
P6 – 1.50m ⌀ Pipeline: Pipe laying work at CH2458 along Jalan Kosas Utama in progress.
P6 – D’Palma Hotel: Meeting with Ahli Majlis and Ketua Kampung of Kg Melayu Ampang.
P6 – 1.50m ⌀ Pipeline: Pipe laying work at CH2468 along Jalan Kosas Utama in progress.
P6 – Jalan Kosas Utama: Piloting work for Jacking Pit at CH2350 in progress.
P6 – 1.50m ⌀ Pipeline: Preparation for CCTV sewer line inspection at Jalan Kosas 2 in progress.
P6 – G-Cast Serendah Factory: Pre-delivery inspection for composite jacking pipe in progress.
P6 – 1.50m ⌀ Pipeline: Pipe laying work at CH2418 along Jalan Kosas Utama in progress.
P6 – 1.50m ⌀ Pipeline: Pipe laying work at CH2735 – CH2725 ( Jln Kosas 2) in progress.
P6 –1.50m ⌀ Pipeline: Premix for diversion to shop lots in progress at CH2660 (Jalan Kosas 2).
P6 – Jalan Kosas 2: Laying and compacting of roadbase crusher run at CH2900 in progress.
P6 – 1.50m ⌀ Pipeline: Pipe laying work at CH2716 – CH2706 (Jln. Kosas 2) in progress.
P6 – 1.50m ⌀ Pipeline: Concreting work of V.T. Block for 45 bend at CH332.
P6 – PIM Site Office: HSSE Committee Meeting No.2/2017.
P6 – 1.50m ⌀ Pipeline: Concreting work of H.T. Block for 45 bend at CH 317.
P6 – Jalan Indah Utama: Weekly toolbox meeting
P6 – Buildcon Ampang: Concrete cube compression test for Thrust Block in progress.
P6 – LLM: Meeting with LLM & SUKE team on interfacing issues.
P6 – Site Office: Technical Meeting No.1/2017
P6 – Buildcon Ampang: Concrete Cube Compression Test in progress.
P6 – Jalan Kosas 2: Weekly Toolbox Meeting in progress.
P6 – Jalan Kosas 2: Reinstatement of 2-Way traffic in progress..
P6 – Jalan Kosas 2 : Reinstatement of 2-Way traffic in progress.
P6 – Jalan Kosas 2 : Site visit by PAAB’s Project Director.
P6 – Site visit among CSRK-KTAT/ PIMSB with SUKE’s contractor (Cantilever) at CH5000.