Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Pakej 6 : Paip Air Terawat Utama dari Kolam Air Ampang ke Kolam Air AU3 2018
print
2020
2019
2018
2017
2016
Dec 18
Nov 18
Oct 18
Sep 18
Aug 18
Jul 18
Jun 18
May 18
Apr 18
Mar 18
Feb 18
Jan 18
P6 – Technical: Mill and pave (road reinstatement) at Jalan Bukit Indah in progress.
P6 – Technical: Pipe laying at CH 4204 – CH 4194 in progress.
P6 – Technical: Discussion with SUKE’s contractor at Kg Dato Mufti for interfacing works.
P6 – Technical: Rectification of speed hump at Jalan Kosas 2.
P6 – Technical: Piloting work at AU3, Keramat (DBKL Area) in progress.
P6 – Technical: Site clearing for temporary access at CH 100m in progress.
P6 – Technical: Pipe laying works at CH7841 – CH7851 in progress.
P6 – Technical: Meeting with MPAJ regarding interfacing with SUKE and Liberty Arc.
P6 – Technical: Discussion with Ketua Kampung ( Kg. Bukit Sungai Puteh).
P6 – Technical: Site discussion with SUKE at Lot PT23.
P6 – Technical: Site visit with LUAS’s officer.
P6 – Technical: Concreting work for trust block of 11.25⁰ bend at CH7819 in progress.
P6 – HSSE: Weekly toolbox meeting.
P6 – Technical: Site discussion at Kim Koo Hardware.
P6 – Technical: Mobilisation of breaker excavator at Lot 841(The garage).
P6 – Technical: Quarterly Risk Management Meeting No.3/2018.
P6 – Technical: Reinstatement of existing road at Jalan 1 (Taman Sri Ukay) in progress.
P6 – Technical: Pipe laying work (CH4621 – CH4601) in progress.
P6 – HSSE: HSSE Committee Meeting No.9/2018
P6 – Technical: Meeting with Kementerian Pendidikan Malaysia for way leave at SK Ampang.
P6 – HSSE: Routine inspection of webbing sling before pipe delivery.
P6 – General: Transferring extra short piece and bend to Contractor’s storage yard.
P6 – HSSE: Housekeeping at SK Ampang compound in progress.
P6 – Reinstatement Works: Reinstatement of chain link fencing at SK Ampang in progress.
P6–Reinstatement Works: Reinstatement of full brick fencing at SMK Taman Kosas in progress.
P6 – 1.52m Ø Pipeline: Air Pressure Test (CH5950) at Lorong Kerja Air Lama in progress.
P6 – General: Monthly Progress Meeting No.6/2018.
P6 – Technical: Progress Meeting with MPAJ Engineering Department.
P6 – HSSE: Weekly Toolbox Meeting.
P6 – Technical: Site discussion for interfacing issue at MRR2.
P6 – Public Engagement: Project briefing to new Adun YB Lembah Jaya.
of 2000Ø pipes 20˚ bend at Line G to H in progress.
P6 – Reinstatement Works: Reinstatement of Turfing at Apartment Permai Puteri in progress.
P6 – HSSE: Weekly Toolbox Meeting.
P6 – QAQC: Additional Mackintosh Probe Test at IRDK bridge in progress.
P6–Reinstatement Works: Reinstatement of Road Kerb at Apartment Permai Puteri in progress.
P6 – Reinstatement Works: Reinstatement of Razor Barb Wire at Apartment Permai Puteri.
P6 – QAQC: Cube Compression Test at Buildcon Plant.
P6 – Authority: Coordination meeting with LLM for interfacing issue with SUKE.
P6 – HSSE: Weekly Toolbox Meeting
P6 – HSSE: Safety Committee Meeting No.5/2018
P6 – Authority: Meeting with JPS Selangor for squatter issue at Jalan Merbau.
P6 – Reinstatement Works: Reinstatement of existing drainage at SMK Kosas in progress.
P6 – Survey Work: Joint Survey for as-built IPC26.
P6 – HSSE: Weekly Toolbox Meeting.
P6 – Interfacing with SUKE: Interfacing meeting with PAAB, SUKE and CSRK-KTAT.
P6 – HSSE: HSSE Committee Meeting No. 4/2018.
P6 – 1.52m Ø Pipeline: Pipe laying work at CH769.10 at Bukit Belacan in progress.
Array
P6 – Pipeline: Pipe laying work in progress ending at CH5530 (Jalan Memanda 27).
P6 –Pipeline: Joint As Built for IPC25 (March 2018) at Jalan Memanda 27.
P6 –Pipeline: Pipe internal collar welding at Bukit Belacan in progress.
P6 –QAQC: Cube Compression test at Buildcon Ampang in progress.
P6 –HSSE: Weekly Toolbox Meeting at Jalan Memanda 27.
P6 –Authority: Progress meeting with MPAJ and KTAT at MPAJ Engineering Department.
P6 –HSSE: HSSE Committee Meeting No. 3/2018.
P6 –General: Quarterly risk management meeting no.1/2018.
P6 – Authoruty: Meeting with MPAJ, Engineering Department.
P6 –HSSE: Weekly toolbox meeting at Jalan Kosas Utama.
P6 – Pipeline: Piling work for overcrossing monsoon drain at CH5330 (Jalan Memanda 27).
P6 –Authority: Site Visit by SPAN and IWK at Jalan Kosas 2.
P6 – Pilotting Works: Piloting work at CH5400 (Jalan Memanda 27) in progress.
P6 –Reinstatement Works: Rectification of drainage at CH2375 to CH2550 (SMK Taman Kosas).
P6 –HSSE: Weekly safety toolbox meeting at Jalan Bunga Anggerik 1.
P6 –Reinstatement Works: Rectification of L-shaped monsoon drain at CH5100 (Sg. Ampang).
P6 – P6 CSRK-KTAT Site Office: Technical Meeting No.1/2018.
P6 – 1.50m ⌀ Pipeline: Pipe laying in progress at CH7205 to CH7195 (Jalan Bunga Anggerik 1).
P6 – 1.50m ⌀ Pipeline: Delivery of pipes and fitting at (Jalan Bunga Anggerik 1).
P6 – 1.50m ⌀ Pipeline: Pipe jacking in progress at CH769 to CH789 (Jln. Bukit Belacan, Ampang).
P6 – 1.50m ⌀ Pipeline: Unloading work for 24 nos. of piles at Jln. Mamanda 27.
P6 –Reinstatement Works: Laying of wearing course at Jalan Bukit Indah Utama in progress.