P6 –HSSE: HSSE Committee Meeting No. 3/2018.
Dec 18
Nov 18
Oct 18
Sep 18
Aug 18
Jul 18
Jun 18
May 18
Apr 18
Mar 18
Feb 18
Jan 18

P6 – Technical: Mill and pave (road reinstatement) at Jalan Bukit Indah in progress.

P6 – Technical: Pipe laying at CH 4204 – CH 4194 in progress.

P6 – Technical: Discussion with SUKE’s contractor at Kg Dato Mufti for interfacing works.

P6 – Technical: Rectification of speed hump at Jalan Kosas 2.

P6 – Technical: Piloting work at AU3, Keramat (DBKL Area) in progress.






P6 – Technical: Site clearing for temporary access at CH 100m in progress.

P6 – Technical: Pipe laying works at CH7841 – CH7851 in progress.

P6 – Technical: Meeting with MPAJ regarding interfacing with SUKE and Liberty Arc.

P6 – Technical: Discussion with Ketua Kampung ( Kg. Bukit Sungai Puteh).

P6 – Technical: Site discussion with SUKE at Lot PT23.






P6 – Technical: Site visit with LUAS’s officer.

P6 – Technical: Concreting work for trust block of 11.25⁰ bend at CH7819 in progress.

P6 – HSSE: Weekly toolbox meeting.

P6 – Technical: Site discussion at Kim Koo Hardware.

P6 – Technical: Mobilisation of breaker excavator at Lot 841(The garage).






P6 – Technical: Quarterly Risk Management Meeting No.3/2018.

P6 – Technical: Reinstatement of existing road at Jalan 1 (Taman Sri Ukay) in progress.

P6 – Technical: Pipe laying work (CH4621 – CH4601) in progress.

P6 – HSSE: HSSE Committee Meeting No.9/2018





P6 – Technical: Meeting with Kementerian Pendidikan Malaysia for way leave at SK Ampang.

P6 – HSSE: Routine inspection of webbing sling before pipe delivery.

P6 – General: Transferring extra short piece and bend to Contractor’s storage yard.

P6 – HSSE: Housekeeping at SK Ampang compound in progress.

P6 – Reinstatement Works: Reinstatement of chain link fencing at SK Ampang in progress.

P6–Reinstatement Works: Reinstatement of full brick fencing at SMK Taman Kosas in progress.







P6 – 1.52m Ø Pipeline: Air Pressure Test (CH5950) at Lorong Kerja Air Lama in progress.

P6 – General: Monthly Progress Meeting No.6/2018.

P6 – Technical: Progress Meeting with MPAJ Engineering Department.

P6 – HSSE: Weekly Toolbox Meeting.

P6 – Technical: Site discussion for interfacing issue at MRR2.

P6 – Public Engagement: Project briefing to new Adun YB Lembah Jaya.
of 2000Ø pipes 20˚ bend at Line G to H in progress.
of 2000Ø pipes 20˚ bend at Line G to H in progress.







P6 – Reinstatement Works: Reinstatement of Turfing at Apartment Permai Puteri in progress.

P6 – HSSE: Weekly Toolbox Meeting.

P6 – QAQC: Additional Mackintosh Probe Test at IRDK bridge in progress.

P6–Reinstatement Works: Reinstatement of Road Kerb at Apartment Permai Puteri in progress.

P6 – Reinstatement Works: Reinstatement of Razor Barb Wire at Apartment Permai Puteri.

P6 – QAQC: Cube Compression Test at Buildcon Plant.







P6 – Authority: Coordination meeting with LLM for interfacing issue with SUKE.

P6 – HSSE: Weekly Toolbox Meeting

P6 – HSSE: Safety Committee Meeting No.5/2018

P6 – Authority: Meeting with JPS Selangor for squatter issue at Jalan Merbau.

P6 – Reinstatement Works: Reinstatement of existing drainage at SMK Kosas in progress.






P6 – Survey Work: Joint Survey for as-built IPC26.

P6 – HSSE: Weekly Toolbox Meeting.

P6 – Interfacing with SUKE: Interfacing meeting with PAAB, SUKE and CSRK-KTAT.

P6 – HSSE: HSSE Committee Meeting No. 4/2018.

P6 – 1.52m Ø Pipeline: Pipe laying work at CH769.10 at Bukit Belacan in progress.
Array






P6 – Pipeline: Pipe laying work in progress ending at CH5530 (Jalan Memanda 27).

P6 –Pipeline: Joint As Built for IPC25 (March 2018) at Jalan Memanda 27.

P6 –Pipeline: Pipe internal collar welding at Bukit Belacan in progress.

P6 –QAQC: Cube Compression test at Buildcon Ampang in progress.

P6 –HSSE: Weekly Toolbox Meeting at Jalan Memanda 27.

P6 –Authority: Progress meeting with MPAJ and KTAT at MPAJ Engineering Department.

P6 –HSSE: HSSE Committee Meeting No. 3/2018.

P6 –General: Quarterly risk management meeting no.1/2018.













P6 – Authoruty: Meeting with MPAJ, Engineering Department.

P6 –HSSE: Weekly toolbox meeting at Jalan Kosas Utama.

P6 – Pipeline: Piling work for overcrossing monsoon drain at CH5330 (Jalan Memanda 27).

P6 –Authority: Site Visit by SPAN and IWK at Jalan Kosas 2.

P6 – Pilotting Works: Piloting work at CH5400 (Jalan Memanda 27) in progress.






P6 –Reinstatement Works: Rectification of drainage at CH2375 to CH2550 (SMK Taman Kosas).

P6 –HSSE: Weekly safety toolbox meeting at Jalan Bunga Anggerik 1.

P6 –Reinstatement Works: Rectification of L-shaped monsoon drain at CH5100 (Sg. Ampang).

P6 – P6 CSRK-KTAT Site Office: Technical Meeting No.1/2018.

P6 – 1.50m ⌀ Pipeline: Pipe laying in progress at CH7205 to CH7195 (Jalan Bunga Anggerik 1).

P6 – 1.50m ⌀ Pipeline: Delivery of pipes and fitting at (Jalan Bunga Anggerik 1).

P6 – 1.50m ⌀ Pipeline: Pipe jacking in progress at CH769 to CH789 (Jln. Bukit Belacan, Ampang).

P6 – 1.50m ⌀ Pipeline: Unloading work for 24 nos. of piles at Jln. Mamanda 27.

P6 –Reinstatement Works: Laying of wearing course at Jalan Bukit Indah Utama in progress.