P6 – Technical: Excavation for receiving pit at Jalan Bunga Anggerik in progress.
P6 – Technical: Pipe transfer from Jalan Memanda to Jalan 1, Sri Ukay.
P6 – Technical: Excavation of receiving pit for pipe jacking at MIGS.
Dec 19
Nov 19
Oct 19
Sep 19
Aug 19
Jul 19
Jun 19
May 19
Apr 19
Mar 19
Feb 19
Jan 19













P6 – Technical: Pipe laying works at Jalan Hillview (rock excavation) in progress.

P6 – Technical: Pipe laying at Sg. Ampang in progress.

P6 – HSSE: Housekeeping at Jalan Kempas in progress.

P6 – Technical: Meeting with RAPID.

P6 – Technical: Pipe laying works at CH8092 to CH8102 (Jalan Hillview) in progress.

P6 – Technical: Meeting with TNB regarding relocation works at MRR2.

P6 – Technical: Pipe laying works at CH7280 to CH7270 (Kim Koo) in progress.

P6 – Technical: Road reinstatement work at Jalan Hillview in progress.

P6 – Technical: RC Work for saddle support at Sg. Ampang Crossing in progress.

P6 – HSSE: Installation of netting at receiving pit MIGS.











P6 – Technical: Reinstatement of drainage at Jalan 1, Sri Ukay in progress.

P6 – Technical: Daily toolbox briefing.

P6 – Technical: Concreting work for saddle support beam and column at CH125.

P6 – Technical: Site visit with LUAS regarding KB renewal.

P6 – Technical: Site visit with JKR regarding work permit application.

P6 – Technical: Fabrication of S-bend at Sg. Ampang.

P6 – Technical: Welding work of internal collar for pipe jacking at Jalan Bunga Anggerik.








P6 – Technical: Daily toolbox briefing at Rumah Kempas.

P6 – Technical: Pipe jacking works at Jalan Bunga Anggerik in progress.

P6 – Technical: Pipe laying work at Sg. Ampang in progress.

P6 – Technical: Delivery of jacking pipes to Padang AU3, Keramat in progress.

P6 – Technical: Pipes delivery at Padang AU3, Keramat in progress.

P6 – Technical: Laying of 45˚ bend at Liberty Arc in progress.







P6 – Technical: Unloading fittings at Padang AU3, Keramat.

P6 – Technical: Welding for external collar of washout tee at Jalan 1, Sri Ukay.

P6 – Technical: Welding for external collar of washout tee at Jalan 1, Sri Ukay.

P6 – Technical: Excavation for receiving pit at Jalan Bunga Anggerik in progress.

P6 – Technical: Welding for internal collar of pipe jacking at MIGS.






P6 – Technical: Casting of thrust block for 65˚ bend at Jalan 1 in progress.

P6 – Technical: Transferring piling material from stockpile Sg. Ampang to CH150.

P6 – Technical: Site visit with TNB regarding TNB pole relocation from Jln Pimping to Jln Pakat.

P6 – Technical: Pipe laying at Jalan 1 (CH 8391 to CH 8381) in progress.

P6 – Technical: Pipe jacking at MIGS (Pipe no 14 – 42m / 54m) CH5850 to CH5892 in progress.

P6–Technical: Reinstatement of drainage at Ampang Saujana Reservoir (Jln Dahlia, B. Belacan).

P6 – Technical: Pipe laying works at Jalan 1 (pipe jacking connection, CH8369 to CH 8379).

P6 – Technical: Road reinstatement work at Jalan 1, premix work in progress.









P6 – Technical: Welding for pipe laying work at Jalan Pimping in progress.

P6 – Technical: Pipe laying work at Jalan Pimping in progress.

P6 – Technical: Piloting work at road side of MRR2 in progress.

P6 – HSSE: Scaffolding inspection by OYK Scaffold.

P6 – Technical: Excavation of jacking pit at MIGS in progress.

P6 – Technical: Welding work for internal collar of pipe jacking at Jalan 1, Sri Ukay.







P6 – Technical: Piloting works at Jalan 1, Sri Ukay in progress.

P6 – Technical: Pipe laying at CH6880-CH6870 in progress.

P6 – Technical: Pipe transfer from Jalan Memanda to Jalan 1, Sri Ukay.

P6 – HSSE: Weekly toolbox briefing at Jalan Kempas.

P6 – Technical: Excavation of receiving pit for pipe jacking at MIGS.






P6 – Technical: Mobilisation of machineries to Jalan Pimping 1, Ukay Heights in progress.

P6 – Technical: Pipe laying at CH6231.80 – CH6361.80 in progress.

P6 – Technical: Piloting works at Jalan Kempas in progress.

P6 – Technical: Pipe jacking works at Jalan 1, Sri Ukay in progress.





P6 – Technical: Excavation for jacking pit at Jalan 1, Taman Sri Ukay in progress.

P6 – Technical: Delivery of pipe fittings to Lot 378 in progress.

P6 – Technical: Meeting with Ketua Kampung (Kg Bukit Sungai Puteh).

P6 – Technical: Pipe laying work at CH60 – CH58 in progress.





P6 – Technical: Construction of washout chamber at CH250m, Bukit Belacan in progress.

P6 – Technical: Reinstatement work at SK Ampang in progress.

P6 – Technical: Installation of signboard at MIGS, Jalan Kerja Air Lama.

P6 – Technical: Pipe laying at CH7363 to CH7383 (MRR2) in progress.

P6 – Technical: Pipe laying at CH7383 to CH7413 in progress.

P6 – Technical: Meeting with Liberty Arc at Liberty Arc Site Office.







P6 – Technical: Reinstatement work at SK Ampang in progress.

P6 – Technical: Monthly Progress Meeting No.1/2019.

P6 – Technical: Meeting with SK Ampang.

P6 – Technical: Mobilisation of machineries to Bukit Belacan.

P6 – Technical: Piloting work at Au3, Keramat (DBKL Area) in progress.