P7 – Private Lot (12728-12730): Dumping of extra earth from reservoir platform in progress.
Dec 17
Nov 17
Oct 17
Sep 17
Aug 17
Jul 17
Jun 17
May 17
Apr 17
Mar 17
Feb 17
Jan 17

P7 – Reservoir Platform Phase 1(Approximate level 117): Rock excavation in progress.

P7 – Box culvert C2: Concreting work for base slab from CH70 to CH80 in progress.

P7 – Box Culvert C1 : Removal of unsuitable material at access road in progress.

P7 – Reservoir Platform Phase 1(Approximate level 120): Bulk excavation in progress.

P7 – Box Culvert C1 : Filling work from CH10 to CH80 in progress.

P7 – Box culvert C2: Construction of Box Culvert from CH52 to CH70 in progress.

P7 – Reservoir Platform Phase 1(Approximate level 117): Bulk excavation in progress.

P7 – Reservoir Platform Phase 2(Approximate level 125): Bulk excavation in progress.









P7 – Private Lot (12729): Dumping of excess material to dump site in progress.

P7 – Box culvert C1: Removal of USM from CH20 to CH60 in progress.

P7 – Box culvert C2: Installation of rebar and formwork from CH30 to CH52 in progress.

P7 – Box culvert C1: Fixing rebar and formwork at wall to soffit from CH85 to CH105 in progress.

P7 – Reservoir Platform Phase 2(Approximate level 125): Bulk excavation in progress.

P7 – Reservoir Platform Phase 1(Approximate level 120): Rock excavation and removal in progress.

P7 –Enviromental Works: Maintenance and desilting for temporary silt trap in progress.

P7 – Box culvert C1: Back filling from CH20 to CH60 in progress.

P7 – Box culvert C2: Iin-situ CBR test at CH60 in progress.

P7 – Box culvert C1: Field Density Test (FDT) at CH30 in progress.











P7 – Reservoir Platform Phase 1: Filling and compacting work at USM South area in progress.

P7 – Reservoir Platform Phase 1: Bulk excavation to RL130m in progress.

P7 – Reservoir Platform Phase 1: Watering turf on turfing area in progress.

P7 – Reservoir Platform Phase 1: Bulk excavation to RL133m in progress.

P7 – Box culvert C1: Removal of unsuitable material in progress.

P7 – Box culvert C1: Casting of top slab from CH107 to CH138 in progress.

P7 – HSSE: Excavation of temporary silt trap in progress.

P7 – Reservoir Platform Phase 1: Drilling work for rock blasting at platform RL120m in progress.

P7 – Box culvert C2: Installation of rebar and formwork from CH10 to CH25 in progress.










P7 – Box culvert C1: Rock hacking from CH90 to CH 100 in progress.

P7 – Box culvert C1 : Laying of crusher run for construction of temporary access road in progress.

P7 – Private Lot (12729): Dumping of excess earth to dump site in progress.

P7 – Reservoir Platform Phase 1: Field Density Test (FDT) prior to further filling work in progress.

P7 – Reservoir Platform Phase 1: Joint inspection by JMG and PDRM for trial blasting.

P7 – Reservoir Platform Phase 1: Rock removal after blasting at RL120m in progress.

P7 – Reservoir Platform Phase 1: Construction of cascading drain on permanent slope in progress.

P7 – Reservoir Platform Phase 1: Site clearing and removal of top soil at USM South area in progress.

P7 – Reservoir Platform Phase 1(USM South area): Earth filling at USM South area in progress.

P7 – Box culvert C1: Construction of Box Culvert C1 from wingwall 2 to CH128 in progress.

P7 – Box culvert C2: Construction of Box Culvert C2 from wingwall to CH10 in progress.

P7 – Box culvert C1: Filling work from CH0 to CH20 in progress.

P7 – Reservoir Platform Phase 1: Turfing on trimmed slope at USM North-West area in progress.














P7 – Box culvert C1: Rock hacking from CH80 to CH90 in progress.

P7 – Reservoir Platform: Driving of 380mm RC piles at platform RL117m in progress.

P7 – Reservoir Platform Phase 1: Turfing work on permanent slope in progress.

P7 – Box culvert C1: Backfilling from CH0 to CH50 in progress.

P7 – Reservoir Platform Phase 1: Bulk excavation to platform RL130m in progress.

P7 – Box culvert C1: Casting of wall and top slab from CH55 to CH70 in progress.

P7 – Box culvert C1: Installation of filter material from CH0 to C40 in progress.

P7 – Box culvert C1: Excavation for Box Culvert C1 wing wall 2 in progress.

P7 – Reservoir Platform Phase 1: Construction of berm drain on permanent slope in progress.

P7 – Reservoir Platform Phase 1(USM South area): Filling with suitable material in progress.











P7 – Reservoir Platform: Bulk excavation to RL134m in progress.

P7 – HSSE: Installation of additional layer of gabion at check dam downstream Box Culvert C2.

P7 – Box culvert C1: Construction of wall and top slab from CH 21 to CH 34 in progress.

P7 – Box culvert C1: Rectification on concrete surface at wingwall in progress.

P7 – Reservoir Platform Phase 1: Field Density Test (FDT) in progress.

P7 – Reservoir Platform Phase 1: Mackintosh Probe Testing in progress.

P7 – Private Lot (12729): Dumping of extra earth from reservoir platform in progress.

P7 – Reservoir Platform: Delivery of concrete block for preparation of piling load test (MLT) in progress









P7 – Box Culvert C1: Excavation at Box Culvert C1 alignment CH40 to CH60 in progress.

P7 – Reservoir Platform: Bulk excavation to RL130m in progress.

P7 – General: Maintenance of temporary access road in progress.

P7 –General: Maintenance and desilting work at check dam (Box Culvert C2) in progress.

P7 – General: Temporary slope protection work in progress.

P7 – Reservoir Platform: Bulk excavation to RL125m in progress.

P7 – Box Culvert C1: Construction of Box Culvert C1 in progress.

P7 – Box Culvert C1: Rock excavatiion at Box Culvert C1 (CH40 to CH60) in progress.









P7 – Reservoir Platform: Close turfing on slope (RL133.50m to RL138.00m) in progress.

P7 – Reservoir Platform Phase 1: Bulk excavation to RL124m in progress.

P7 – Private Lot (12729): Dumping of excess material to dumping ground in progress.

P7 – Box culvert C1: Construction of box culvert at CH21 – CH34 in progress.

P7 – Reservoir Platform Phase 1: Removing of top soil at RL120m in progress.

P7 – Box Culvert C2: Maintenance of silt trap in progress.







P7 – Reservoir Platform Phase 1: Bulk excavation to RL 135m in progress.

P7 – Reservoir Platform Phase 1: Bulk excavation to RL 135m in progress.

P7 – Private Lot (12728-12730): Dumping of extra earth to permanent dump site in progress.

P7 – Private Lot (12728-12730): Dumping of extra earth to permanent dump site in progress.

P7 – Reservoir Platform Phase 1: Bulk excavation to RL 135m in progress.

P7 – Reservoir Platform Phase: Bulk excavation to RL 135m in progress.







P7 – Reservoir Platform Phase 1: Bulk excavation at level 142m in progress.

P7 – Private Lot (12728-12730): Dumping of extra earth from reservoir platform in progress.

P7 – Box Culvert: Preparing haul road for excavation work at box culvert C2 in progress.

P7 – Reservoir Platform Phase 1: Bulk excavation at level 142m in progress.

P7 – Private Lot (12718-12717): Dumping of extra earth from reservoir platform in progress.

P7 – Reservoir Platform Phase 1: Bulk excavation at level 142m in progress.







P7 – Reservoir Platform Phase 1: Earthwork in progress.

P7 – Reservoir Platform Phase 1: Earthwork in progress

P7 – Box Culvert C1 Alignment: Site clearing in progress.

P7 – Reservoir Platform Phase 1: FDT test in progress at filling area.

P7 – Environmental Works: Monthly water sampling at downstream of Sg. Michu by Environmental Consultant.

P7 – Environmental Works: Quarterly air monitoring at nearest residential area by Environmental Consultant.

P7 – Reservoir Platform Phase 1: Earthwork in progress.








P7 – Access Road: Preparation for stream diversion for construction of box culvert.

P7 – Reservoir Platform Phase 1: Earthwork in progress.

P7 – Reservoir Platform Phase 1: Earthwork in progress.

P7 – Earth Dumpsite at Private Lot: Earthwork in progress.

P7 – Earth Dumpsite at Private Lot: Construction of silt trap in progress.

P7 – Concrete Batching Plant: Making concrete cube for cube test.