P7 – Pipeline: Laying of 1750mmØ inlet pipe in progress.
P7 – Detention Pond: Preparation for lean concrete at Inlet Manhole A in progress.
P7 – Reservoir Compartment 1: Backfilling at Inlet Chamber No. 1 in progress.
P7 – Reservoir Compartment 2: Rock hacking at Outlet Chamber No. 2 in progress.
P7 – Pipeline : Rock hacking for outlet pipe alignment in progress.
Dec 18
Nov 18
Oct 18
Sep 18
Aug 18
Jul 18
Jun 18
May 18
Apr 18
Mar 18
Feb 18
Jan 18

P7 – Reservoir Compartment 1: Fixing rebar at 1st lift wall in progress.

P7 – Reservoir Compartment 1: Fixing rebar at roof slab in progress.

P7 – Reservoir Compartment 1: Casting 2nd lift wall in progress.

P7 – Reservoir Compartment 2: Fixing rebar at 2nd lift wall in progress.

P7 – Reservoir Compartment 2: Casting of roof slab in progress.

P7 – Reservoir Compartment 2: Fixing rebars at base slab in progress.

P7 – Detention Pond: Construction of inlet section of detention pond in progress.

P7 – Pipeline: Laying of 1750mmØ inlet pipe in progress.

P7 – Pipeline: Rock hacking and drilling at scour pipe alignment in progress.

P7 – Switch House: Brick laying in progress.

P7 – Drainage: Casting of V-shape cascading drain in progress.












P7 – Reservoir Compartment 1: Fixing formwork for column (second lift) in progress.

P7 – Reservoir Compartment 1: Fixing rebar at base slab in progress.

P7 – Reservoir Compartment 2: Installation of rebar and formwork for RC staircase in progress.

P7 – Reservoir Compartment 2: Erecting formwork at wall (first lift) in progress.

P7 – Reservoir Compartment 2: Leveling single size aggregates for foundation in progress.

P7 – Reservoir Compartment 2: Base preparation for Overflow Chamber in progress.

P7 – Pipeline: Laying of 1200mmØ inlet pipe from Inlet Chamber No 1 to reservoir in progress.

P7 – Pipeline: Rock excavation at 1800mmØ RC pipe (Manhole C) in progress.

P7 – Switch House: Installation of formwork for roof fascia in progress.

P7 – Detention Pond: Construction of Inlet Structure to Detention Pond in progress.











P7 – Reservoir Compartment 1: Casting of reservoir compartment 1 base slab in progress.

P7–Reservoir Compartment 2: Leveling and compacting single size aggregates in progress.

P7 – Reservoir Compartment 2: Installation rebar and formwork for roof slab in progress.

P7 – Pipeline: Preparation for concrete thrust block at 1750mmØ vertical bend in progress.

P7 – Pipeline: Laying of 1750mmØ inlet pipeline in progress.

P7 – Pipeline: Construction of air valve chamber in progress.

P7 – Detention Pond: Preparation for lean concrete at Inlet Manhole A in progress.

P7 – Drainage Work: Casting of cascading drain base in progress.









P7 – Reservoir Compartment 1: Installation of rebar at base slab in progress.

P7 – Reservoir Compartment 1: Casting of column second lift in progress.

P7 – Reservoir Compartment 1: Backfilling at Inlet Chamber No. 1 in progress.

P7 – Reservoir Compartment 2: Installation of rebar and formwork at roof slab in progress.

P7 – Switch House: Column casting completed.

P7 – Pipeline: Construction of Inlet Flowmeter Chamber in progress.

P7 – Reservoir Compartment 1: Spreading aggregate for reservoir base is in progress.

P7 – Pipeline: Rock hacking for 1800mmØ RC pipe trench from MH B to MH A CH290 in progress.









P7 – Detention Pond : Laying of rubble pitching in progress.

P7 – Reservoir Compartment 1: Rock hacking at Overflow Chamber in progress.

P7 – Reservoir Compartment 1: Construction of Scour Chamber No. 1 in progress.

P7 – Reservoir Compartment 1: Fixing rebar and formwork for roof slab in progress.

P7 – Reservoir Compartment 2: Fixing rebar for walls in progress.

P7 – Reservoir Compartment 2: Fixing rebar for base slab in progress.

P7 – Reservoir Compartment 2: Erection formwork for columns in progress.

P7 – Pipeline: Fixing 1200mmØ cast-in pipe at Inlet Chamber No. 2 in progress.

P7 – Pipeline: Laying of 1800mmØ RC Pipes at Manhole B in progress.

P7 – Switch House: Installation of rebar and formwork for base slab in progress.











P7 – Detention Pond : Laying of rubble pitching and turfing on slopes in progress.

P7 – Reservoir Compartment 1: Installation of rebar for walls and columns in progress.

P7 – Reservoir Compartment 1: Casting of slabs in progress.

P7 – Reservoir Compartment 1: Fixing formwork for 2nd lift column in progress.

P7 – Reservoir Compartment 2: Construction of Inlet Chamber No. 2 in progress.

P7 – Reservoir Compartment 2: Rock hacking at Outlet Chamber No. 2 in progress.

P7 – Reservoir Compartment 2: Reservoir compartment 2 structural work in progress.

P7 – Reservoir Compartment 2: Laying single size aggregates in progress.

P7 – Pipeline: Laying of 1750mmØ inlet pipeline in progress.

P7 – Switch House: Installation of rebar and formwork for service trench in progress.











P7 – Detention Pond: Drainage and turfing works at detention pond slopes in progress.

P7- Detention Pond : Bulk excavation to approximate level 103m in progress.

P7 – Reservoir Compartment 2: Laying and leveling of aggregates in progress.

P7 – Reservoir Compartment 2: Overview of reservoir compartment 2 structural work.

P7 – Reservoir Compartment 1: Construction 0f Inlet Chamber No. 1 in progress.

P7 – Reservoir Compartment 1: Installation of rebar and formwork for base slab and columns.

P7 – Pipeline : Pipe laying for 1750mmØ inlet pipe in progress.

P7 – Pipeline : Rock hacking for outlet pipe alignment in progress.









Access Road Embankment : Filling work to approximate level 105m in progress.

Access Road Embankment : Turing work on completed slopes in progress.

P7 – Reservoir Compartment 2: Rock excavation at reservoir wall base in progress.

P7 – Reservoir Compartment 1: Installation of rebar and formwork in progress.

P7 – Reservoir Platform Phase 1: Installation half round drain on permanent slope.

P7 – Pipework: Rock hacking at inlet pipeline alignment in progress.

P7 – Pipework: Pipe laying for 1700mmø bypass pipeline in progress.

P7 – Pipework: Rock hacking at outlet pipeline alignment in progress.

P7 – HSSE: Quarterly Environment Audit No. 2/2018










P7 – Reservoir Platform: Rock excavation in progress.

P7 – Reservoir Compartment 1: Fixing rebars and formwork at reservoir base slab in progress.

P7 – Pipeline: Excavation for open trench pipe laying at outlet pipe alignment in progress.

P7 – Reservoir Compartment 1: Lean concrete in progress.

P7 – Access Road Embankment: Filing work approximate level 99m in progress.

P7 – Pipework: Pipe laying for 1700ø by-pass pipeline in progress.

P7 – Pipeline: Rock hacking at by-pass pipeline alignment in progress.

P7 – Detention Pond: Bulk excavation (approximate level 110m) in progress.

P7 – Reservoir Platform: Overview reservoir compartment 1 structural work.










P7 – Reservoir: Rock excavation at Reservoir platform Phase 1 in progress.

P7 – Reservoir: Drilling prior to rock blasting at Reservoir platform Phase 1 in progress.

P7 – Reservoir: Installation of rebars at reservoir base slab and column in progress.

P7 – Reservoir: Joint survey for reservoir sub base level in progress.

P7 – Reservoir: Rock hacking to reservoir structure base level in progress.

P7 – Reservoir: Excavation of sedimentation basin at Reservoir platform Phase 2 in progress.

P7 – Reservoir: Bulk excavation at Reservoir platform Phase 2 in progress.

P7 – Access Road: Filing work at Road Embankment approximate level 96m in progress.

P7 – Access Road: Turfing work on embankment slope in progress.

P7 – Box culvert C1: Construction of access manhole in progress.











P7 – Access Road Embankment: Turfing on completed slope in progress.

P7 – Reservoir Platform Phase 2: Excavation to platform RL120m in progress.

P7 – Reservoir Platform Phase 1: Rock excavation at platform RL116m in progress.

P7 – Reservoir Platform Phase 1: Excavation at piling area to wall base foundation in progress.

P7 – Reservoir Platform Phase 1: Rock drilling at Reservoir platform RL116m in progress.

P7 – Access Road Embankment: Filling of access road embankment RL90m in progress.

P7 – HSSE: Maintenance and desilting work at temporary silt trap in progress.

P7 – Drainage: Construction of cascading drain at reservoir permanent slope in progress.

P7 – Box culvert C2: Filling and compacting work at Box Culvert C2 RL95m in progress.

P7 – Access Road Embankment: Laying of BRC for construction of berm drain in progress.











P7 – Access Road Embankment: Filling and compaction work at access road to RL90m in progress.

P7 – HSSE: Quarterly Environment Audit in progress.

P7 – Reservoir Platform Phase 1(Approximate level 116): Rock excavation in progress.

P7 – Reservoir Platform Phase 1: Drilling and charging work prior to rock blasting in progress.

P7 – Reservoir Platform Phase 1: Maintenance of temporary access road in progress.

P7 – Box culvert C1: Installation of rebar and formwork at access manhole in progress.

P7 – Box culvert C2: Dismantling of formwork from CH80 to CH92 in progress.