Open Menu
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Pakej 9 : Kolam Air AU3 Berkapasiti 28 Juta Liter 2017
print
2019
2018
2017
2016
Dec 17
Nov 17
Oct 17
Sep 17
Aug 17
Jul 17
Jun 17
May 17
Apr 17
Mar 17
Feb 17
Jan 17
P9 – Phase 1 Reservoir: Formwork installation in progress for scour chamber.
P9 – RE Wall 1: Installation of precast panels in progress.
P9 – Phase 1 Reservoir: Fixing of rebars in progress (Roof slab Zone RA2).
P9 – Drainage works: Excavation work in progress for 450mm diameter pipe culvert.
P9 – Phase 1 Reservoir: Construction of overflow chamber in progress.
P9 – HSSE: Weekly Toolbox Meeting in progress.
P9 – HSSE: HSSE training (Fire drill and fire extinguisher training).
P9 – QAQC: Concrete cube test in progress.
P9 – HSSE: Weekly Toolbox Meeting
P9 – Pipe Laying: Backfilling work for 600mm Dia. MS Pipe in progress.
P9 – Phase 1 Reservoir: Installation of lightning protection system in progress (Roof Slab – Zone RB1)
P9 – Pipe Laying: Backfilling work for 600mm Dia. MS Pipe in progress
P9 – RC Chamber: Fixing rebars in progress (Overflow Chamber).
P9 – RE Wall 1: Backfilling with crusher run in progress.
P9 – Phase 1 Reservoir: Concreting works in progress (Roof Slab – Zone RB1).
P9 – RE Wall 1: Backfilling with crusher run in progress.
P9 – HSSE: Install and maintenance of safety barricade and signage in progress.
P9 – Overall: Site walk with PIMSB and CSRK-RCSB.
P9 – M&E: Installation of lightning arrester at Reservoir in progress.
P9 – Phase 1 Reservoir: Rebars installation in progress (Roof Slab Zone RC2).
P9 – RE Wall 1: Backfilling with crusher run in progress.
P9 – RE Wall 1: Installation of steel tendons in progress.
P9 – Phase 1 Reservoir: Concreting works in progress (Roof Slab Zone RC2).
P9 – Switch Room: Brickworks in progress.
P9 – Phase 1 Reservoir: Installation of support scaffolding for roof slab in progress.
P9 – Drainage Works: Construction of RC Sump in progress.
P9 – Phase 1 Reservoir: Concreting work in progress (Column head Zone B5).
P9 – Phase 2 Platform: Earthwork (import & backfill) in progress.
P9 – Detention pond: Excavation work for base slab in progress.
P9 – RE Wall 1: Installation of precast panels in progress.
P9 – RE Wall 1: Installation of precast panels in progress.
P9 – Phase 1 Reservoir: Dismantling of formwork in progress (Roof slab Zone RA3).
P9 – Phase 1 Reservoir: Concreting work in progress (Wall Zone A1 – 3rd Lift).
P9 – Phase 1 Reservoir: Installation of rebars in progress (Roof slab Zone RC3).
P9 – RC Chamber: Backfilling to overflow chamber in progress.
P9 – Phase 1 Reservoir: Fixing formwork and rebars in progress (Wall C3 – 3rd Lift)
P9 – Phase 1 Reservoir: Fixing rebars in progress (Roof Slab – Zone RA1).
P9 – Switch Room: Fixing formwork for roof slab in progress.
P9 – RE Wall 1: Installation of precast panel in progress
P9 – Phase 1 Reservoir: Concreting work in progress (Wall Zone C2 – 3rd Lift).
P9 – Drainage Works: Construction of RC Sump in progress.
P9 – Phase 1 Reservoir: Concreting work in progress (Column Zone B3 – 1st Lift).
P9 – RE Wall 1: Installation of precast panel in progress.
P9 – Phase 1 Reservoir: Concreting work in progress (Wall Zone B1 – 2nd Lift).
P9 – HSSE: Weekly Toolbox Meeting.
P9 – Phase 1 Reservoir: Formwork installation in progress (Wall Zone C1-1st Lift).
P9 – QAQC: Slump test before concreting.
P9 – Phase 1 Reservoir: Concreting work in progress (Wall Zone C3 – 1st Lift).
P9 – Detention Pond: Excavation for base slab in progress.
P9 – Phase 1 Reservoir: Installation of formwork in progress (Column Zone C6 – 3rd Lift).
P9 – Switch room: Installation of formwork and cable ducts in progress.
P9 – RE Wall 1: Installation of precast panel in progress.
P9 – QA/QC: Mackintosh Probe for foundation of RE Wall 1 in progress.
P9 – Reservoir Phase 1: Fixing rebars and formwork in progress (Slab Zone C1).
P9 – Reservoir Phase 1: Construction of walls in progress (Wall Zone C9-2nd Lift).
P9 – RE Wall 1: Cutting down existing slope for RE Wall 1 working area in progress
P9 – RE Wall 1: Backfilling with crusher run in progress.
P9 – Switch Room: Construction of RC Footing in progress.
P9 – Reservoir: Fixing rebars and formwork in progress (Slab Zone C3).
P9 – Reservoir: Fixing formwork in progress (Wall Zone A1).
P9 – Reservoir: Concreting work in progress (Wall Zone A3).
P9 – RE Wall 2: Backfilling with crusher run in progress.
P9 – RE Wall 1: Soil replacement for base foundation in progress.
P9 – RE Wall 1: Preparation of working platform for RE Wall 1 in progress.
P9 – Pipe Works: QAQC inspection for delivered pipes in progress.
P9 – Reservoir Phase 1: Fixing rebars for walls and columns in progress.
P9 – Reservoir Phase 1: Fixing rebars and formwork for walls and columns in progress.
P9 – Reservoir: Installation of outlet pipes in progress.
P9 – Re Wall 2: Installation of precast panels and backfilling with crusher run in progress.
P9 – Re Wall 1: Cutting down existing slope for RE Wall platform in progress.
P9 – Reservoir Phase 1: Wall panel A4 completed
P9 – Reservoir Phase 1: Reinforcement bar in progress (Slab panel C5 and C6).
P9 – Reservoir Phase 1: Formwork in progress (Wall panel A8).
P9 – Re Wall 2: Installation of precast panel in progress.
P9 – Reservoir Phase 1: Reinforcement bar & formwork in progress for RC Slab (Panel A8 & A9)
P9 – Reservoir Phase 1: Concreting work for sump pit (panel A2 & A3).
P9 – Reservoir Phase 1: Reinforcement bar and formwork in progress for 2nd lift Wall (panel A4 & A5)
P9 – Re Wall 2: Installation of precast panel in progress
P9 – RE Wall 2: Installation of precast panel in progress
P9 – Overall: QAQC inspection for delivered pipes in progress.
P9 – Reservoir Phase 1: Fixing reinforcement bar for 1st lift wall (Panel B 5) in progress.
P9 – Reservoir Phase 1: Fixing formwork in progress for inlet sump (panel A8).
P9 – Reservoir Phase 1: Fixing reinforcement bar and MS pipe installation in progress for spare outlet sump (panel C6).
P9 – RE Wall 2: Precast panel installation in progress.
P9 – RE Wall Phase 1: Earthwork (cut & fill) at RE Wall 1 area in progress.