P9 – Drainage Works: Construction of 300mm cascade drain on top of RE Wall in progress.
P9 – Pipe Laying Works: Compaction for backfilling earth in progress.
P9 – Phase 1 Reservoir: Repairing works to the leaked structure in progress.
P9 – Phase 1 Reservoir: Impounding water into compartment 1 for water tightness test in progress.
P9 – Phase 1 Reservoir: Impounding water into compartment 1 for leakage test in progress.
P9 – Drainage Works: Concreting works for 600mm PC Block drain in progress.
P9 – Fencing: Installation of barb wire fence in progress.
P9 – HSSE: Road cleaning to the existing public road in progress.
P9 – Phase 1 Reservoir: Filling water for leakage test in progress.
P9 – Phase 1 Reservoir: Filling water for leakage test in progress.
P9 – HSSE: Weekly Toolbox Meeting in progress.
P9 – Drainage Works: Construction of 300 PC Block drain in progress.
Dec 18
Nov 18
Oct 18
Sep 18
Aug 18
Jul 18
Jun 18
May 18
Apr 18
Mar 18
Feb 18
Jan 18

P9 – Phase 1 Reservoir: Repairing works to the leaked wall at compartment 2 in progress.

P9 – Barb Wire Fence: Installation of precast RC pole for barb wire fence in progress.

P9 – Drainage Works: Excavation for 600mm RC culvert from MH17 to MH18 in progress.

P9 – Earthwork: Installation of FIBROMAT blanket on slope in progress.

P9 – Pipe Laying Works: Pipe laying for 1100mmØ MS pipe from altitude valve chamber.

P9 – Drainage Works: Construction of 300mm cascade drain on top of RE Wall in progress.

P9 – QA/QC: Inspection of delivered material (900mmØ Altitude valve) in progress.

P9 – Drainage Works: Concreting works for RC sump (MH17) progress.









P9 – Phase 1 Reservoir: Impounding water into compartment 1 for water tightness test in progress.

P9 – RC Chamber: Installation of 900mmØ short piece Altitude Valve chamber in progress.

P9 – Pipe Laying Works: Casting of thrust block for 900mmØ pipe completed.

P9 – RC Chamber: Construction of Altitude Valve chamber in progress.

P9 – Pipe Laying Works: Compaction for backfilling earth in progress.

P9 – Phase 1 Reservoir: Repairing works to the leaked structure in progress.

P9 – Pipe Laying Works: Welding works for 700mmØ MS pipe in progress.

P9 – Earthwork/Site Formation: Closed turfing to the slope formation in progress.









P9 – Earthwork: Close turfing to the slope at Phase 2 area in progress.

P9 – Phase 1 Reservoir: Rectification work to stop leaking at compartment 1 in progress.

P9 – Phase 1 Reservoir: Impounding water into compartment 1 for water tightness test in progress.

P9 – HSSE: Fogging for mosquito control at workers quarter in progress.

P9 – Pipe Laying Works: Laying of 1500mmØ MS taper pipe in progress.

P9 – Drainage Works: Casting of toe drain on top of RE Wall 1 in progress.

P9 – RC Chamber: Casting of Altitude Valve chamber in progress.








P9 – Earthwork: Closed turfing to the slope on top of RE Wall 1 in progress.

P9 – Pipe Laying: Backfilling works to pipe trench in progress.

P9 – Phase 1 Reservoir: Impounding water into compartment 1 for leakage test in progress.

P9 – Pipe Laying Works: Welding to concentric taper (1500mmØ to 1200mmØ) in progress.

P9 – Pipe Laying Works: Welding works for 1500mmØ MS pipe in progress.

P9 – Earthwork: Backfilling to top of RE Wall 1 in progress.

P9 – Phase 1 Reservoir: Installation of temporary end cap to the 1100mmØ inlet pipe for structure leakage test in progress.

P9 – RC Chamber: Construction of Flowmeter Chamber in progress.

P9 – Valve installation: Installation of 1100mm Butterfly valve at outlet chamber in progress.

P9 – Phase 1 Reservoir: Repair works to the leaked structure in progress.











P9 – Earthwork: Backfilling with earth to top of RE Wall 1 in progress.

P9 – Turfing Works: Closed turfing for slope formation on top of RE Wall 1 in progress.

P9 – QA/QC: Mockup for PU injection for repairing structure leakage in progress.

P9 – QA/QC: Mockup for PU injection for repairing structure leakage in progress.

P9 – Drainage Works: Erecting brick wall for 600mm cascade drain in progress.

P9 – RC Chamber: Concreting works for Pipeline Bypass Chamber in progress.

P9 – Phase 1 Reservoir: Impounding water for leakage test in progress.

P9 – Drainage works: Concreting works for 600mm PC Block drain in progress.









P9 – Pipe Laying Works: Material delivery in progress.

P9 – Drainage Works: Concreting works for 600mm PC Block drain in progress.

P9 – Drainage Works: Concreting works for RC Sump (MH 9) in progress.

P9 – Fencing: Installation of barb wire fence in progress.

P9 – HSSE: Road cleaning to the existing public road in progress.

P9 – Pipe Laying Works: Sand backfilling to 1500mmØ pipeline in progress.

P9 – Pipe Laying Works: Welding works for 1500mmØ MS pipe in progress.

P9 – Phase 1 Reservoir: Filling water for leakage test in progress.









P9 – Anti-climb Fence: Inspection of work done with IOW in progress.

P9 – Phase 1 Reservoir: Inspection prior to filling up water for leakage test in progress.

P9 – Phase 1 Reservoir: Filling water for leakage test in progress.

P9 – RC Chamber: Concreting works for interconnection chamber in progress.

P9 – Risk Management: Risk Management Committee Meeting (Q2/2018) in progress.

P9 – Valve Installation: Installation of 1100mm Butterfly Valve for outlet pipe in progress.

P9 – Anti-climb Fence: Installation of galvanized mild steel poles in progress.

P9 – Pipe Laying Works: Backfilling work for 1500mmØ pipeline in progress.

P9 – Drainage Works: Concreting works for RC Sump (MH 18) in progress.










P9 – Pipeline: Pipe laying for 1500mmØ outlet pipe in progress.

P9 – QAQC: Inspection for delivered pipes in progress.

P9 – Drainage Works: Construction of RC sump (MH 18) in progress.

P9 – Detention Pond: Concreting works for wall in progress.

P9 – Pipeline: Concreting works for thrust block in progress.

P9 – Detention Pond: Erecting formworks for walls in progress.

P9 – Perimeter Ant-climb Fence: Installation of GMS poles in progress.








P9 – HSSE: Weekly Toolbox Meeting in progress.

P9 – Switch Room: Inspection of Telemetry & Instrument panel in progress.

P9 – Drainage Works: Concreting works for 300mm PC Block drain in progress.

P9 – Detention Pond: Installation of reinforcement bar and formwork in progress.

P9 – RC Chamber: Concreting works for outlet chamber in progress.

P9 – RC Chamber: Concreting works for Interconnection chamber in progress.

P9 – Detention Pond: Concreting works for base slab in progress.

P9 – Drainage Works: Plastering works for 300mm PC Block drain in progress.

P9 – Phase 1 Reservoir: Rectification of defects and cleaning works in progress.










P9 – Drainage Works: Plastering works for 600mm PC Block drain in progress.

P9 – Drainage Works: Construction of 300 PC Block drain in progress.

P9 – RE Wall 1: Installation of precast panel in progress.

P9 – QAQC: Concrete cube compression test in progress.

P9 – Phase 1 Reservoir: Rectification works for defects of RC structure in progress.

P9 – Pipe Works: Welding works for 1500mmØ MS pipes in progress.

P9 – RE Wall 1: Laying of steel tendon in progress.

P9 – RC Chamber: Construction of outlet chamber in progress.









P9 – Drainage Works: Concreting works for RC Sump (MH2) in progress.

P9 – RC Chamber: Construction of Scour Chamber in progress.

P9 – Drainage Woks: Installation of 300mm PC Block drain in progress.

P9 – Phase1 Reservoir: Concreting works for external staircase in progress.

P9 – Drainage Works: Concreting works for 300mm PC Block drain in progress.

P9 – QAQC: Concrete cube compression test in progress.







P9 – Earthwork Phase 2: Slope formation and turfing works in progress.

P9 – RE Wall 1: Installation of precast panels in progress.

P9 – Drainage Works: Material delivery for 600mm PC Block drain in progress.

P9 – Drainage Works: Installation of rebars and formwork for RC sump in progress.

P9 – HSSE: Mosquito fogging at site accommodation area in progress.

P9 – Reservoir Phase 1: Dismantling formwork in progress inside compartment 1.

P9 – QAQC: Concrete cube compression test in progress.

P9 – Switch Room: Painting works in progress.

P9 – HSSE: Weekly Toolbox Meeting in progress.

P9 – RC Chamber: Installation of rebars and formwork in progress for Overflow Chamber.