Open Menu
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Pakej 15 :Existing Bukit Dengkil Reservoir 2018
print
2019
2018
2017
Dec 18
Nov 18
Oct 18
Sep 18
Aug 18
Jul 18
Jun 18
May 18
Apr 18
Mar 18
Feb 18
Jan 18
P15- Existing Langat BR: Laying of 150mmØ to air valve chamber No.4 at Line B-C in progress.
P15- Existing Langat BR: Construction of air valve chamber No.4 at Line B-C in progress.
P15- Existing Langat BR: Fabrication of bend for connection tee Line 10 at IC 8 in progress.
P15- Existing Langat BR: Cleaning existing chamber at Line G-H in progress.
P15- Existing Langat BR: Expose and cleaning existing chamber at IC 8 in progress.
P15- Existing Langat BR: Delivery ofl butterfly valve and air valve to site store yard in progress.
P15- Existing Langat BR: Laying of short piece to butterfly valve chamber No.2 in progress.
P15- Existing Langat BR: Construction of butterfly valve chamber at Line B-C in progress.
P15- Existing Langat BR: Casting to wall of washout chamber chamber at Line B-C in progress.
P15- Interconnection 8 (IC 8): Piling work for saddle support in progress.
P15- Interconnection 8 (IC 8): Piling work for trust block foundation in progress.
P15- Interconnection 8 (IC 8): PDA test to piling point for saddle support in progress.
P15- Interconnection 8 (IC 8): Preparation for line stopping work (Line 10) in progress.
P15- Interconnection 8 (IC 8): Reinstatement work to slope area in progress.
P15- Existing Langat BR: Air Test at Line B to C in progress.
P15- Existing Langat BR: Concreting work for apron slab at Switch House in progress.
P15- Interconnection 7 (IC7): Construction of Butterfly Valve Chamber No. 2 in progress.
P15- Interconnection 7 (IC 7): Installation of temporary bypass at IC7 in progress.
P15- Existing Langat BR: Construction of butterfly valve chamber for Line B-C in progress.
P15- Existing Langat BR: Wrapping to welding joints (Line F-G) in progress.
P15- Existing Langat BR: Laying of 20˚ bend to Line G-H in progress.
P15- Existing Langat BR: Delivery of precast washout chamber in progress.
P15- Interconnection 8 (IC 8): Laying of crusher run for temporary access to IC 8 in progress.
P15- Existing Langat BR: Delivery of pipes in progress.
P15- Existing Langat BR: Plastering work for reinstatement of existing chamber in progress.
P15-Existing Langat BR: Fabrication of 60˚ bend and 1600X1200 reducer (Line B – C) in progress.
P15- Existing Langat BR: Construction of Air Valve Chamber No. 2 in progress.
P15- QA/QC: Factory Acceptance Test for Sluice Valve and Butterfly Valve at VAG Factory.
P15- Existing Langat BR: Construction of Air Valve Chamber No. 3 in progress.
P15- Existing Langat BR: Backfilling work in progress for Line G to H.
P15- Interconnection 7 (IC7): Construction of Valve and Flowmeter Chambers in progress.
P15- Existing Langat BR: Weekly Safety Toolbox Briefing.
P15- Existing Langat BR: Installation of vermin netting at Switch House in progress.
P15- Existing Langat BR : Safety Walkabout.
P15- Existing Langat BR: Installation of DN2000 x DN1600 tee at Line B to C in progress.
P15- Existing Langat BR: Installation of 2000Ø pipes 20˚ bend at Line G to H in progress.
P15- Existing Langat BR: Fabrication of 10˚ bend and short pieces for Pipeline Line F to G.
P15- Existing Langat BR: Laying of 60˚ bend and short piece for pipeline Line F to G.
P15- Existing Langat BR: Wall casting for flowmeter chamber in progress.
P15- Inlet Chamber: Water tightness test in progress.
P15-Existing Langat BR: Laying short piece to flowmeter chamber from Point A to B in progress.
P15- Existing Langat BR: Air test for short piece welded joint from Point A to B.
P15- Existing Langat BR: Laying straight pipe and 30˚ bend from Point D to E in progress.
P15- Existing Langat BR: Site visit from PAAB and CSRK.
P15- Existing Langat BR: Excavation for flowmeter chamber in progress.
P15- Existing Langat BR: Site visit from PAAB and CSRK.
P15- Existing Langat BR: Casting of 2nd lift wall to inlet chamber in progress.
P2A –Chemical Building: Internal testing for Poly Raw Water system (B) in progress.
P2A – Chemical Building: Dosing pumps calibration at Poly RW & PAC Plant in progress.
P2A – Chemical Building: Cable termination for Fluoride control panels (B) in progress.
P15- IC 8: Casting of thrust block for 45˚ bend from Point A to Point B in progress.
P15- Switch House: Casting of roof beam and slab in progress.
P15 – IC 7: Casting of base slab for valve and flowmeter chamber in progress.
PP15 – IC 8: Construction of inlet chamber No.1 in progress.
P15 – IC 8: Pipe laying from Point F to Point G in progress.
P15 – IC 8: Construction of valve chamber No.1 in progress.
P15- IC 8: Installation of starter bars into existing base in progress.
P15 – IC 8: Concstruction of control room in progress.
P15 – IC 8: Construction of Inlet Chamber No.1 in progress.
P15 – IC 8: Pipe laying from point C to point E in progress.
P15- IC 8: Trench excavation for pipe laying from point A to Point B in progress.
P15- IC 8: Trench excavation for pipe laying from point A to Point B in progress.
P15- IC 8: Excavation for inlet chamber No. 1 in progress.
P15- IC 8: Rebar preparation for inlet and valve chamber No. 1 in progress.