P5 – 1.75m Ø Pipeline: Safety Meeting No.4/ 2020 conducted at CSRK-KTAT Package 5 Meeting Room.
Dec 20
Nov 20
Oct 20
Sep 20
Aug 20
Jul 20
Jun 20
May 20
Apr 20
Mar 20
Feb 20
Jan 20

P5 – 1.75m Ø Pipeline: Install formwork for 2nd lift wall of washout chamber is in progress at Ch.1750m Jalan Kuari Sg. Long.














P5 – 1.75m Ø Pipeline: Welding work for access tee is in progress at Ch.5203m Adit 4.












P5 – 1.75m Ø Pipeline: Removing sheetpile is in progress at Ch.1450m Jalan Kuari Sg. Long.

P5 – 1.75m Ø Pipeline: Reinstate Telekom pole is in progress at Ch.1450m Jalan Kuari Sg. Long.

P5 – 1.75m Ø Pipeline: Reinstate slope is in progress at Ch.1450m Jalan Kuari Sg. Long.

P5 – 1.75m Ø Pipeline: Driven sheetpile for washout chamber is in progress at Ch.1450m Jalan Kuari Sg. Long.

P5 – 1.75m Ø Pipeline: Driven sheetpile for washout chamber is in progress at Ch.1450m Jalan Kuari Sg. Long.






P5 – 1.75m Ø Pipeline: Mobilize machineries for construct washout chamber at Ch.1750m Jalan Kuari Sg. Long.

P5 – 1.75m Ø Pipeline: Remove end cap to install access tee at Ch.5203m Adit 4.

P5 – 1.75m Ø Pipeline: Install access tee to connect pipeline gap at Ch.5203m Adit 4.




P5 – 2.00m Ø Pipeline: Repair resident houses is in progress at Casa Residence.

P5 – 2.00m Ø Pipeline: Repair resident houses is in progress at Casa Residence.

P5 – 1.75m Ø Pipeline: Clear shrub and repair earth drain due to public complaint to PAAB at Kg Sg. Michu Ch.4020m.

P5 – 1.75m Ø Pipeline: Prepare & install equipment for pressure and water leakage test at Ch.4011m downstream Sg. Michu.





P5 – 1.75m Ø Pipeline: Pumping water for pressure and leakage test at Ch.5203m Adit 4.

P5 – 2.00m Ø Pipeline: Repair resident houses is in progress at Casa Residence.

P5 – 1.75m Ø Pipeline: Joint site visit with Air Selangor pertaining changing of AC pipe to MS pipe at Arina Seafood & Jalan Kuari Sg. Long.

P5 – 1.75m Ø Pipeline: Safety Meeting No.4/ 2020 conducted at CSRK-KTAT Package 5 Meeting Room.





P5 – 1.75m Ø Pipeline: Reinstatement work at Casa Residence in progress.

P5 – 1.75m Ø Pipeline: Repair of damaged Telekom cable at CH3700 (Jln Hulu Langat) in progress.

P5 – 1.75m Ø Pipeline: Pumping water for pressure leakage test at CH5203 (Adit 4).

P5 – 1.75m Ø Pipeline: Reinstatement work at CH3800 near Arina Seafood in progress.

P5 – 1.75m Ø Pipeline: Monthly Progress Meeting No.3/2020 at CSRK-KTAT P5 Site Office.






P5–1.75m Ø Pipeline: Displaying safety notice to prevent covid-19 at CH3802 near Arina Seafood.

P5 – 1.75m Ø Pipeline: Relocation of TNB cable at CH3800 near Arina Seafood in progress.

P5 – 1.75m Ø Pipeline: Relocation of TNB cable at CH3800 near Arina Seafood in progress.

P5 – 1.75m Ø Pipeline: Relocation work of TNB cable at CH3800 near Arina Seafood in progress.




No Progress due to MCO

P5 – 1.75m Ø Pipeline: Casting of trust block for 30⁰ HB at CH3820 near Arina Seafood.

P5–2.00mØ Pipeline: Driving of temporary sheetpile at CH3817 near Arina Seafood in progress.

P5 – 1.75m Ø Pipeline: Installation of convex mirror at S-bend location (Tmn Hulu Langat Jaya).

P5 – 1.75m Ø Pipeline: Pipe laying reaching CH3808 near Arina Seafood.





P5–1.75mØ Pipeline: Pipe laying from CH3844 to CH3834 near Arina Seafood in progress.

P5–1.75mØ Pipeline: Removing sheetpiles as pipelaying completed (CH1763, Jln Kuari Sg. Long).

P5–2.00mØ Pipeline: Backfilling for pipe trench at CH1763 (Jalan Kuari Sg. Long) in progress.

P5–1.75mØ Pipeline: Driving sheet pile for pipe trench at CH3834 near Arina Seafood in progress.

P5–1.75m Ø Pipeline: Pipe laying reaching CH3426 near Arina Seafood.






P5–1.75mØ Pipeline: Tidy up the site after CNY break at CH1720 (Jln Kuari Sg. Long).

P5–1.75mØ Pipeline: Repair works at CH5010-CH4900 Jln Hulu Langat-Ampang (JKR comments).

P5–1.75mØ Pipeline: Mobilization of machineries at CH3480 (Jln Hulu Langat – Arina Seafood).

P5–1.75mØ Pipeline: Mobilization of machineries at CH1750 Jln Hulu Langat – Jln Kuari Sg. Long.