Open Menu
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Pakej 7 : Kolam Air Imbangan Hulu Langat Berkapasiti 92 Juta Liter
print
2020
2019
2018
2017
2016
Sep 20
Aug 20
Jul 20
Jun 20
May 20
Apr 20
Mar 20
Feb 20
Jan 20
P7 – Inspection: Inspection for completion of Works at generator room
P7 – Inspection: Inspection for completion of Works at main switch room
P7 – Video Recording: Monthly video recording of the works in progress
P7 – Earthworks: Turfing work at slope near road embankment in progress
P7 – Site Inspection: Defect inspection at external wall of reservoir
P7 – Site Inspection: Defect inspection at internal compartment of reservoir
P7 – Site View: View at inlet area of reservoir phase 1
P7 – Site View: View at inlet area of reservoir phase 1
P7 – Site View: View at inlet area of reservoir phase 1
P7 – Site View: View at inlet area of reservoir phase 1
P7 – Earthwork Monitoring: Soil instrumentation monitoring for inclinometer in progress.
P7 – Earthwork Monitoring: Soil instrumentation monitoring for inclinometer in progress.
P7 – Site View: Entrance to Hulu Langat reservoir site
P7 – Site View: TNB compact sub-station
P7 – Site View: Access road to detention pond
P7 – Site View: Detention pond
No Progress due to MCO
P7 – Drainage: Maintenance of berm drain in progress.
P7 – Drainage: Maintenance of berm drain in progress.
P7 – Turfing: Re-turfing 0n slope near detention pond in progress.
P7 – Turfing: Re-turfing on slope near detention pond in progress.
P7 – Drainage: Housekeeping and cleaning of drainage sump in progress
P7 – M&E Works: Functional test for Supervisory and OS panel in progress.
P7- M&E Works: Functional test for lightings and alarm system at guard house in progress
P7 – M&E Works: Functional test for valves actuators in progress.
P7 – Turfing: Watering the turfing in progress.
P7 – Housekeeping & Clearing: Clearing of construction waste material in progress.
P7 – Roadworks: Rectification of access road in progress