Pakej | Location | Description | Duration | Activity | Contact | View |
---|---|---|---|---|---|---|
Pakej 6 |
Jalan Lingkaran Tengah 2 (MRR2) arah Ampang/ Jalan Kerja Ayer Lama | Penutupan Lorong Kiri di hadapan bangunan Kaunsel Ekonomi China dari CH.6350 ke CH.6400 (50m) | 22/07/2022 hingga 15/09/2022 (12.00am to 11.59pm) |
Korekan jalan untuk pemasangan paip 1500mm garispusat secara ‘pipe jacking’ | Kontraktor: iINFRA Sdn Bhd Mohd Zakuan Ariffin Mohd Zulhanis Rosli |
|
Pakej 5 | Jalan Hulu Langat FT3210 (Jalan Kuari Sg Long towardsTaman Lagenda Suria) |
Lane Closure for 325m length (CH1650m to CH1975m) |
28/12/2019 till 10/4/2020 9.00am to 6.00pm |
Road Diversion.Laying 1.75m dia. pipe by open excavation methodand road reinstatement. |
Contractor: Jaks Sdn. Bhd. Nurul Hasmaliza Ismail Safety Officer : 012-9468667 Lye Fook Wah |
Pakej 5 | Jalan Hulu Langat FT3210 (Jalan Kuari Sg Long towardsTaman Lagenda Suria) |
Lane closure 225m length (CH3400 to CH 3625) |
28/01/2020 till 5/5/2020 9.00am to 6.00pm |
Utilities relocation. Laying 1.75m dia. pipe by open excavation method and reinstatement of road pavement. |
Contractor: Jaks Sdn. Bhd. Nurul Hasmaliza Ismail Safety Officer : 012-9468667 Lye Fook Wah |
Pakej 5 | Jalan Hulu Langat FT3210 (Taman Sri Nanding to Teratak Nanding) |
Road Diversion 95m length (CH3675 to CH 3770) |
23/10/2019 till 15/3/2020 9.00am to 6.00pm |
Road Diversion.Laying 1.75m dia. pipe by open excavation method and road reinstatement. |
Contractor: Jaks Sdn. Bhd. Nurul Hasmaliza Ismail Safety Officer : 012-9468667 Lye Fook Wah |
Pakej 6 | Jalan AU3/1 dan Jalan AU3/12 | Lane Closure length 218m (CH. 8867.00 to CH. 9085.00) |
2/1/2020(Pending) till 1/3/2020 (Pending) (8.00am to 6.00pm) |
Laying 1.5mm dia. MS Pipe by excavation open trench method and reinstatement of metalled road | ||
Pakej 6 | JPS reserve at IRDK Land | (CH. 1330.00 to CH. 1475.00); 145m | 5/5/2020 till 5/6/2020 (8.00am to 6.00pm) |
Laying 1.5mm dia. MS Pipe by excavation open trench method | In progress. TMP not required | |
Pakej 6 | JPS reserve Sg Ampang, connection to overcrossing | (CH. 4325.00 to CH. 4375.00); 50m | 7/5/2020 till 15/6/2020 (8.00am to 6.00pm) |
Laying 1.5mm dia. MS Pipe by excavation open trench method | In progress. TMP not required | |
Pakej 6 | PT23 to Jalan Hillview | (CH. 7900.00 to CH. 7980.00); 80m | 3/2/2020 till 5/4/2020 (8.00am to 6.00pm) |
Laying 1.5mm dia. MS Pipe by excavation open trench method | In progress. TMP not required | |
Pakej 11 | Jalan Mawar | Lane closure 63m. Provide temporary diversion 1-way traffic. (Ch 2512m – Ch 2625M) |
29/1/2020 till 30/6/2020 (8.00am to 6.00pm) |
Laying 2.50m dia. MS Pipe by excavation open trench method and reinstatement of metalled road | Contractor: Pembinaan Ikhasas-Merak Sdn. Bhd. PIMSB Site Office: 03-91075675 Project Manager : 019-2658430 |
|
Pakej 11 | Persiaran Taman Perindustrian Kinrara | One way road closure length 250meter. Provide 1-way contra lane traffic – (CH. 3250 – CH. 3500) |
19/12/2020 till 28/2/2021 (8.00am to 6.00pm) |
Laying 1.950m dia. MS Pipe by excavation open trench at under the road. | Contractor: Pembinaan Ikhasas-Merak Sdn. Bhd. PIMSB Site Office: 03-91075675 Project Manager : 019-2658430 |
|
Pakej 11 | Lebuhraya Bukit Jalil | Road Reserve / Raod shoulder closure (175m length) (CH. 4700- CH. 4875) maintain 2 lanes traffic. Duration 3 months. |
31/10/2020 till 31/1/2021 (8.00am to 6.00pm) |
Laying 1.950m dia. MS Pipe by excavation open trench at road reserve/ road shoulder. | Contractor: Pembinaan Ikhasas-Merak Sdn. Bhd. PIMSB Site Office: 03-91075675 Project Manager : 019-2658430 |