P2A – Aerator: Joint meter reading for raw water flowmeter with LUAS.

P2A – Dewatering Building: Transporting out the sludge by Air Selangor in progress.

P2A – TWPS: Installation of silencer for surge vessel in progress.

P2A – Administration Building: Pre-Inspection for handing over to AiS.





P2A – TWPS: Re-fixing of cooling fan for Hulu Langat pumpset in progress.

P2A – Dewatering Building: Transporting out the sludge by Air Selangor in progress.

P2A – WAMS: Join inspection on tagging to the equipment in Generator Building.

P2A – WAMS: Join inspection on tagging to the equipment in Dewatering Building.





P2A – Administration Building: Rectification of building services in Conference Room in progress.

P2A – Service Trench: Testing of drainage pumps in progress.

P2A – Dewatering Building: Disposal of sludge by Air Selangor in progress..

P2A – Washwater Recovery Plant: Testing of floating arm at Washwater Recovery Plant B.

P2A – Washwater Recovery Plant: Testing of floating arm at Washwater Recovery Plant A.

P2A – Chemical Building: Defect inspection for Stream A in progress.







P2A- Dewatering Building: Modification of access for polymer discharge platform in progress.

P2A- Dewatering Building: Modification of polymer discharge platform in progress.

P2A – Chemical Building: Fixing of portable scale at Fluorite Plant in progress.

P2A – Washwater Recovery Plant: Crane inspection by JKKKP for “Permit Mesin Angkat”.

P2A- Store: Crane inspection by JKKKP for “Permit Mesin Angkat”.

P2A – Generator Building: Audit by Jabatan Audit Negara.

P2A – Treatment Plant Switchhouse: Audit by Jabatan Audit Negara.

P2A – Administration Building: Handing over of RFID scanners to Air Selangor.









P2A – Dewatering Plant: Repairing of conveyor in progress.

P2A – Dewatering Plant: Repairing of Decanter No. 1 & 3 in progress.

P2A – Dewatering Plant: Testing of conveyor system (no load test) in progress.

P2A – Dewatering Plant: Functional test for screw conveyor in progress.

P2A – Dewatering Plant: Testing of overhead crane in progress.

P2A – Generator Building: Maintenance of generator in progress.

P2A – Thickened Residuals Pumping Station: Retesting of thickened pump Stream B in progress.

P2A– Chemical Building: Dry run test for lime recirculation pumps (Stream A) in progress.





















P2A – Clear Water Tank: Installation of chain block for overhead crane in progress.

P2A – Chlorine Stream B: Repairing Chlorinator in progress.

P2A–Thickened Residual Pumping Station: Internal testing at Decanter Feed Pumps Control Panel in progress.

P2A–Thickened Residual Pumping Station: Internal testing for Decanter Feed Pumps in progress.

P2A–Residual Dewatering Plant: Centric water sampling point modification work in progress.

P2A– Residual Dewatering Building: Labeling of equipment in progress.

P2A– Residual Dewatering Building: Recording power consumption in progress.

















No Progress due to MCO

P2A–Aerator A: Continue 600MLD 24-hours pumping of raw water from Pahang for Performance Test.

P2A–Aerator A: Calibration for water monitoring rack at pre-oxidation tank in progress.

P2A–Administration Building: SCADA Performance Test for Stream A in progress.

P2A–Administration Building: Preparation of water samples for testing by independent lab, Permulab Sdn. Bhd for Performance Test.

P2A–Administration Building: Jar test for raw water at Stream A during Performance Test.

P2A–Administration Building: Monitoring of effluent water quality at monitoring rack in progress.

P2A –Clarifier Stream A: Testing of PAC dosing at static mixer during Performance Test.

P2A –Clarifier Stream A: Testing of inlet channel A2 during Performance Test.

P2A –Clarifier Stream A: Testing of polymer dosing at flocculation tank A2 during Performance Test.

P2A –Clarifier Stream A: Testing of clarified water at Clarified Water Channel A2 during Performance Test.



















































P2A–Aerator A: 600MLD 24-hours pumping of raw water from Pahang for internal testing.

P2A–Aerator A: Checking of inlet valve during internal testing in progress.

P2A–Administration Building: Internal functional test for SCADA system Stream A in progress.

P2A–Administration Building: SCADA configuration work for Stream A in progress.

P2A–Administration Building: PH test for raw water Stream A in progress.

P2A–Administration Building: Testing of heat and smoke detector for Fire Alarm System in progress.

P2A –Clarifier Stream A: Internal testing for PAC dosing at static mixer in progress.

P2A –Clarifier Stream A: Internal testing for inlet channel A2 in progress.

P2A –Clarifier Stream A: Internal testing for polymer dosing at flocculation tank A2 in progress.




























































P2A–Aerator B: 300 MLD 24-hours pumping of raw water from Pahang for operation by AiS.

P2A–Laboratory: Testing of Manganese contents by Air Selangor.

P2A–Laboratory: Testing of Iron contents by Air Selangor.

P2A–Administration Building: Operation using SCADA system by Air Selangor.

P2A–Administration Building: SCADA configuration work for Stream A in progress.

P2A–Administration Building: Telephone continuity test in progress.

P2A–Administration Building: Installation of aquarium in progress.