P10 – Pipeline 2500 Ø: Pipe laying works at CH.7808.250 – CH.7800.25 in progress.














P10 – Pipeline 2500 Ø: Pipe laying works at CH.6556.275 – CH.6548.275 in progress.












P10 – Inlet Portal: Mucking out for invert slab at CH.300 – CH.250 in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH.6733.475 – CH.6725.475 in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH.2371.8 – CH.2363.8 in progress.

P10 – Pipeline 2500 Ø: Backfilling work at Jalan Suadamai in progress.

P10 – Inlet Portal: Preparation work to install steel rib at CH.454.40 – CH.452.8 in progress.


















P10 – Inlet Portal: Mucking Out for Invert slab lean con. Ch380-350

P10 – Inlet Portal: Preparation work to lean concrete from CH.380 – CH.370 in progress.











P10 – Outlet Portal: Installation of steel rib no.27 at CH.482 in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH.3414.5 – CH.3406.5 in progress.













P10 – Inlet Portal: Spray final shotcrete at CH.310 onwards in progress.






















P10 – Inlet Portal: Drilling forepoling bar next to steel rib Sec.4 no.9 at CH.501.5 in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH.10318.7 – CH.10313.7 in progress.

P10 – Inlet Portal: Spraying shotcrete heading Sec.4 in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH2842.8 – CH2834.8 in progress.

P10 – Inlet Portal: Installation of steel rib no.10 Sec.4 at CH499 in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH8551.98 – CH8547.98 in progress.



















P10 – Pipeline 2500 Ø: Pipe laying works at CH10516.40 – CH10514.40 in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH10511.8 – CH10505.8 in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH10505.8 – CH10497 in progress.

P10 – Pipeline 2500 Ø: Pipe laying works at CH3505 – CH3497 in progress.










No Progress due to MCO

P10 – Inlet Portal: Manual excavation to install crown steel rib no.13 at CH452 in progress.

P10 – Pipeline 2500 Ø: Pipe laying work at CH10562.4 – CH10554.4 in progress.

P10 – Pipeline 2500 Ø: Driving sheet piles for pipe trench at Grand Saga area in progress.

P10 – Pipeline 2500 Ø: Pipe laying work at CH10546.4 – CH10538.4 in progress.

P10 – Inlet Portal: Installation of steel rib no.18 at CH453.2 in progress.

P10 – Pipeline 2500 Ø: Pipe laying work at CH10530.4 – CH10522.4 in progress.







P10 – Inlet Portal: Spraying seal shotcrete at RHS of tunnel area in progress.

P10 – Pipeline 2500 Ø: Pipe laying work at CH11115.17 – CH11107.17 in progress.

P10 – Pipeline 2500 Ø: Pipe laying work at CH.10765 – CH.10757 in progress.

P10 – Inlet Portal: Hacking work to seal shotcrete at RHS excavate area (CH450) in progress.

P10 – Pipeline 2500 Ø: Pipe laying work at CH10741 – CH10733 in progress.

P10 – Inlet Portal: Grout injection at point 1 (CH448) & point 2 (CH450) in progress.

P10 – Pipeline 2500 Ø: Pipe laying work at CH10725 – CH10717 in progress.