![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.12.25-P10556.png)
P10 – Pipeline 2500 Ø: Pipe laying works at CH.7808.250 – CH.7800.25 in progress.
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.12.25-P10643.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.12.25-P10731.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.12.25-P10817.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.12.25-P10902.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.12.25-P10991.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.12.25-P101075.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.12.25-P10556-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.12.25-P10643-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.12.25-P10731-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.12.25-P10817-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.12.25-P10902-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.12.25-P10991-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.12.25-P101075-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.11.27-P10568.png)
P10 – Pipeline 2500 Ø: Pipe laying works at CH.6556.275 – CH.6548.275 in progress.
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.11.27-P10656.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.11.27-P10743.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.11.27-P10827.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.11.27-P10914.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.11.27-P101001.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.11.27-P10568-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.11.27-P10656-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.11.27-P10743-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.11.27-P10827-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.11.27-P10914-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2021/01/2020.11.27-P101001-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P10564.png)
P10 – Inlet Portal: Mucking out for invert slab at CH.300 – CH.250 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P10650.png)
P10 – Pipeline 2500 Ø: Pipe laying works at CH.6733.475 – CH.6725.475 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P10737.png)
P10 – Pipeline 2500 Ø: Pipe laying works at CH.2371.8 – CH.2363.8 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P10821.png)
P10 – Pipeline 2500 Ø: Backfilling work at Jalan Suadamai in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P10896.png)
P10 – Inlet Portal: Preparation work to install steel rib at CH.454.40 – CH.452.8 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P10996.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P101083.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P101170.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P101253.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P101341.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P101428.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P10564-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P10650-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P10737-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P10821-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P10896-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P10996-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P101083-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P101170-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P101253-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P101341-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/11/2020.10.25-L2P101428-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-4550.png)
P10 – Inlet Portal: Mucking Out for Invert slab lean con. Ch380-350
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-4623.png)
P10 – Inlet Portal: Preparation work to lean concrete from CH.380 – CH.370 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-4716.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-4803.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-4886.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-4971.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-4550-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-4623-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-4716-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-4803-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-4886-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-4971-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-3827.png)
P10 – Outlet Portal: Installation of steel rib no.27 at CH.482 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-3913.png)
P10 – Pipeline 2500 Ø: Pipe laying works at CH.3414.5 – CH.3406.5 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-3994.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-31074.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-31181.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-31266.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-31342.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-3827-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-3913-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-3994-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-31074-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-31181-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-31266-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-31342-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-2563.png)
P10 – Inlet Portal: Spray final shotcrete at CH.310 onwards in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-2641.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-2721.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-2808.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-2880.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-2953.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-21040.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-21127.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-3562.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-3643.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-3726.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-2563-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-2641-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-2721-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-2808-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-2880-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-2953-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-21040-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-21127-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-3562-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-3643-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/P10-3726-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-11.png)
P10 – Inlet Portal: Drilling forepoling bar next to steel rib Sec.4 no.9 at CH.501.5 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1103.png)
P10 – Pipeline 2500 Ø: Pipe laying works at CH.10318.7 – CH.10313.7 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1187.png)
P10 – Inlet Portal: Spraying shotcrete heading Sec.4 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1257.png)
P10 – Pipeline 2500 Ø: Pipe laying works at CH2842.8 – CH2834.8 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1337.png)
P10 – Inlet Portal: Installation of steel rib no.10 Sec.4 at CH499 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1421.png)
P10 – Pipeline 2500 Ø: Pipe laying works at CH8551.98 – CH8547.98 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1503.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1586.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1666.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1750.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1830.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1914.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-11-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1103-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1187-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1257-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1337-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1421-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1503-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1586-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1666-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1750-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1830-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10-1914-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p101.png)
P10 – Pipeline 2500 Ø: Pipe laying works at CH10516.40 – CH10514.40 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/10/p1087.png)
P10 – Pipeline 2500 Ø: Pipe laying works at CH10511.8 – CH10505.8 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10170.png)
P10 – Pipeline 2500 Ø: Pipe laying works at CH10505.8 – CH10497 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10252.png)
P10 – Pipeline 2500 Ø: Pipe laying works at CH3505 – CH3497 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10329.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10413.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10496.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p101-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p1087-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10170-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10252-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10329-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10413-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/10/p10496-150x150.png)
No Progress due to MCO
![](https://langat2.paab.my/wp-content/uploads/2020/05/P101-1.png)
P10 – Inlet Portal: Manual excavation to install crown steel rib no.13 at CH452 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/05/P1098.png)
P10 – Pipeline 2500 Ø: Pipe laying work at CH10562.4 – CH10554.4 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10180.png)
P10 – Pipeline 2500 Ø: Driving sheet piles for pipe trench at Grand Saga area in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10281.png)
P10 – Pipeline 2500 Ø: Pipe laying work at CH10546.4 – CH10538.4 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10362.png)
P10 – Inlet Portal: Installation of steel rib no.18 at CH453.2 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10443.png)
P10 – Pipeline 2500 Ø: Pipe laying work at CH10530.4 – CH10522.4 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/05/P101-1-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/05/P1098-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10180-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10281-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10362-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10443-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/05/P101.png)
P10 – Inlet Portal: Spraying seal shotcrete at RHS of tunnel area in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/05/P1085.png)
P10 – Pipeline 2500 Ø: Pipe laying work at CH11115.17 – CH11107.17 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10169.png)
P10 – Pipeline 2500 Ø: Pipe laying work at CH.10765 – CH.10757 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10250.png)
P10 – Inlet Portal: Hacking work to seal shotcrete at RHS excavate area (CH450) in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10348.png)
P10 – Pipeline 2500 Ø: Pipe laying work at CH10741 – CH10733 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10427.png)
P10 – Inlet Portal: Grout injection at point 1 (CH448) & point 2 (CH450) in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10517.png)
P10 – Pipeline 2500 Ø: Pipe laying work at CH10725 – CH10717 in progress.
![](https://langat2.paab.my/wp-content/uploads/2020/05/P101-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/05/P1085-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10169-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10250-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10348-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10427-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/05/P10517-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/03/P10-12.png)
![](https://langat2.paab.my/wp-content/uploads/2020/03/P10-194.png)
![](https://langat2.paab.my/wp-content/uploads/2020/03/P10-1176.png)
![](https://langat2.paab.my/wp-content/uploads/2020/03/P10-1247.png)
![](https://langat2.paab.my/wp-content/uploads/2020/03/P10-1343.png)
![](https://langat2.paab.my/wp-content/uploads/2020/03/P10-1438.png)
![](https://langat2.paab.my/wp-content/uploads/2020/03/P10-12-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/03/P10-194-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/03/P10-1176-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/03/P10-1247-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/03/P10-1343-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2020/03/P10-1438-150x150.png)