P2B- HSSE: Conducting ESH committee walkabout

P2B- Environmental : The fifth environment audit of year 2020 by 3rd party.































































P2B- HSSE: Weekly safety toolbox meeting before start works.

P2B- QAQC : Cube test at Fortis Star batching plant

P2B- Environment: Cleaning of public access road (entrance to site) in progress.

P2B- TNB: Concreting works for roof slab in progress.

























































P2B- Environmental: Water sampling at discharge point (WQ2).

P2B- QAQC : Cube test for RC slab Block F4 at Fortis Star concrete batching plant.

P2B- Road Works: Laying of ACBC for access road to project site office in progress.

P2B- TNB Substation : Concreting of services trench in progress.

P2B- Block Dewan: Applying anti termite for ground slab in progress.




















































P2B- Safety & Health: Toolbox meeting for all workers before start works

P2B- Environmental: Fogging for dengue prevention.

P2B- Civil Works: Road cutting for laying of sewer line under existing road in progress.

P2B- Civil Works: Brickworks for 600mm block drain in progress.

















































P2B- Block Dewan: Preparation of earth platform for ground slab in progress.

P2B- Block Surau: Casting of ground floor slab in progress.

P2B- Block Surau: Overall view.

P2B- Block F1: Casting of 2nd floor beam & slab in progress.







































P2B- Block Surau: Installation of building services at ground floor.

P2B- Block Surau: Overall view of Block Surau.

P2B- Block F1: Overall view of Block F1.

P2B- Block F2: Applying termite control system for ground slab.

P2B- Block F2: Overall view of Block F2




















P2B- Block F2: Concreting of pile cap in progress.

P2B- Safety: Weekly safety toolbox meeting

P2B- Block F2: Dismantling of pile cap formworks in progress.

P2B- Block F1: Installation of BRC and pipe fitting for ground slab in progress.

P2B- Block F1: Dismantling of formworks for ground floor slab in progress.

P2B- Block F3: Installation of sanitary and rain water down pipes in progress.

P2B- Block F2: Applying termite control system for pile caps in progress.

P2B- Block F1: Concreting of columns at ground floor in progress.









P2B- Project Office: Brick laying in progress.

P2B- Block F1: Installation of formworks for ground beam in progress.

P2B- Block F2: Jack-in piling in progress.

P2B- Block F4: Concreting of pile caps in progress.




No Progress due to MCO

P2B- Piling: Jack-in piling for Block F3 in progress.

P2B- Pile Cap: Excavation for pile cap Block F3 in progress.

P2B- Pile Cap: Cutting pile head for block F4 in progress.

P2B- Preliminaries: Installation of project signboard in progress.

P2B- Testing: Tensile & bending test for reinforcement bar at 3rd party lab.

P2B- Pile cap: Lean concrete for pile cap Block F1 in progress.







P2B- Survey: Survey for as built pile for block F4 in progress.

P2B- Piling: Pre boring for block E1 in progress.

P2B- Test: Pile Dynamic Analysis Test (PDA) for block F4 in progress.

P2B- Test: Pile Integrity Test (PIT) for block F1 in progress.