Open Menu
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Pakej 6 : Paip Air Terawat Utama dari Kolam Air Ampang ke Kolam Air AU3
print
2020
2019
2018
2017
2016
Dec 20
Nov 20
Oct 20
Sep 20
Aug 20
Jul 20
Jun 20
Mar 20
Apr 20
Mar 20
Feb 20
Jan 20
L2P06 – 1no of 2m S/Piece and 1no of 14d Bend laid at CH9613m to CH9617m, Jalan 15/56(Au3)
L2P06 – Excavation Work at CH9275m to CH9285m, Jalan 01/56 (Au3)
L2P06 – Piloting Work in progress at CH9250m, Jalan 10/56(Au3)
L2P06 – Excavation Work in Progress at CH9457m to CH9465m, Jalan 15/56(Au3)
L2P06 – 1no of 7.3m S/piece pipe laid at CH9457m to CH9465m, Jalan 15/56(Au3)
L2P06 – Welding Work in Progress at CH9457m, Jalan15/56(Au3)
L2P06 – Piloting Work in Progress at CH9270m, Jalan 1/56(Au3)
L2P06 – Setting up guard rail for pipe jacking at Jalan 15/56(AU3)
L2P06 – Concrete Thrust Block for 45d Bend at Jalan 10/56(AU3)
L2P06 – Excavation Work at CH9915m to CH9905m, Jalan 15/56(AU3)
L2P06 – 1no of 10m Straight pipe Laid at CH9915m to CH9905m, Jalan 15/56 (AU3)
L2P06 – Excavation Work in Progress at CH9122m to CH9132m, Jln 10/56(AU3)
L2P06 – 1no of 10m Straight Coated Pipe Laid at CH9122m to CH9132m, Jln 10/56(AU3)
L2P06 – Excavation Work at CH9915m to CH9905m, Jalan 15/56(AU3)
P6 – Pipeline: Pipe laying at CH1496 to CH1486 in progress.
P6 – Pipeline: Pipe laying at CH6144 to CH6139 in progress.
P6 – Reinstatement work: Laying of crusher run at CH9030 to CH8960, Jalan AU3/12.
P6 – Reinstatement work: Laying of ACBC and ACWC at CH9030 to CH8960, Jalan AU3/12.
P6 – Pipeline: Pipe laying at CH1476 to CH1469 in progress.
P6-Pipeline: Laying of 30Ëš bend laid at CH6128 to CH6130 in progress.
P6 –Pipeline: Piloting work at Jalan AU3/12 in progress.
P6 – Pipeline: Welding work at CH1476 in progress.
P6 – Pipeworks: laying of 5m short piece pipe at ch1373.3 to ch1378.3 in progress.
P6 – Pipeworks: Pipe cutting for 90˚ bend in progress.
P6 – Pipeworks: Air test for collar joint at thrust block of saddle support.
P6 – Pipeworks: Welding in progress at CH1373.3.
No Progress due to MCO
P6-Pipeline: Laying of 11° horizontal bend to the pipeline between CH7911 and CH7912.
P6-Pipeline: Laying of 1.5m short piece at CH101 in progress.
P6-Pipeline: Casing of RC thrust block for 60° bend in progress.
P6-Pipeline: Trench excavation in progress.
P6-Pipeline: Casing of RC thrust block for 11° horizontal bend in progress.
P6-Pipeline: Casing of RC thrust block for 15° bend at CH150 in progress.
P6-Pipeline: Joint operation with MPAJ to remove the illegal gate to enter IRDK area.
P6-Pipeline: Joint operation with MPAJ to remove the illegal gate to enter IRDK area.
P6 – Technical: Pipe laying at Bukit Belacan in progress.
P6 – Technical: Pipe laying at Good Shepherd in progress.
P6 – Technical: Pipe laying at Liberty area in progress.
P6 – Technical: Pipe laying for overcrossing at Bkt Belacan in progress.
P6 – Technical: pipe laying for overcrossing at Sg Ampang in progress.
P6 – Technical: Pipe jacking at Lorong Kerja Air Lama 2 in progress.
P6 – Technical: Pipe laying at Jln Anggerik in progress.
P6 – Technical: Welding work for overcrossing at Sg Ampang in progress.
P6 – Technical: Pipe laying at Pt23 in progress.
P6 – Technical: Backfilling Work at Lorong Kerja Air Lama in progress.