P11-Pipeline 2400Ø: Wash out tee (F103) was laid at CH7874.725 – CH7872.275.
Sg Bohol, BK6.
Dec 20
Nov 20
Oct 20
Sep 20
Aug 20
Jul 20
Jun 20
May 20
Apr 20
Mar 20
Feb 20
Jan 20

P11-Pipeline 1950Ø: Piloting work for utilities crossing at CH4270.00. Lebuhraya Bukit




















P11-Pipeline 1950Ø: Reinforced concrete jacking pipe 4m (LW151A) no.13 was jacked at CH4303.000 – CH4299.000. Taman Perindustrian Kinrara.






















P11-Pipeline 1950Ø: Short pipe 1.4m (LW222a) was laid at CH481.700 – CH483.025. Kinrara hill.

P11-Pipeline 1950Ø: Concrete thrustblock for vertical bend 60° (F083) at CH2776.540 – CH2779.740. BK5 Rimba.

P11-Pipeline 1950Ø: Short pipe 7m (LW282a) was laid at CH3430.430 – CH3437.355. Persiaran Taman Perindustrian Kinrara.














P11-Pipeline 2500Ø: Reinstatement work for pipe laying work done at CH2560 –
CH2570. Jalan Mawar, Taman perindustrian Bukit Serdang.
CH2570. Jalan Mawar, Taman perindustrian Bukit Serdang.

P11-Pipeline 1950Ø: Concrete work for 3 nos precast chamber at Reserve forest, BK6.



















P11-Pipeline 1950Ø: Vertical bend 13° (F093) was laid at CH2684.050 – CH2686.050.
Rimba, BK5.
Rimba, BK5.

P11-Pipeline 1950Ø: Short pipe 2m (LW402d) was laid at CH2686.050 – CH2688.100.
Rimba, BK5.
Rimba, BK5.















P11-Pipeline 1950Ø: Piling work for wash out chamber at CH440. Kinrara hill, BK6.

P11-Pipeline 2400Ø: Wash out tee (F103) was laid at CH7874.725 – CH7872.275.
Sg Bohol, BK6.






P11-Pipeline 1950Ø: Vertical bend 13° (F093) was laid at CH2684.050 – CH2686.050.
Rimba, BK5.
Rimba, BK5.

P11-Pipeline 1950Ø: Short pipe 2m (LW402d) was laid at CH2686.050 – CH2688.100.
Rimba, BK5.
Rimba, BK5.










P11-Pipeline 1950Ø: Unloading of painted pipes at Reserved Forest, BK5 in progress.

P11-Pipeline 2500Ø: Laying of 45° bend at CH2718-CH2721 (Multiplex, BS10) in progress.

P11-Pipeline 1950Ø: Casting of anchorblock at CH1540 (Reserved Forest, BK5).

P11-Pipeline 1950Ø: Casting of thrustblock for offset w/o tee at CH1929 Reserved forest, BK5.

P11-Pipeline 1950Ø: Concrete surround for pipea at C1720-CH1593 (Reserved Forest, BK5).

P11-Pipeline 2400Ø: Pipe laying on saddle support at CH7905-CH7900 (Duet, BK6).

P11-Pipeline 2400Ø: Pipe laying on saddle support at CH7900-CH7892 (Duet, BK6).

P11-Pipeline 2500Ø: Laying of air valve tee at CH2721-CH2723 (Multiplex, BS10).









P11-Pipeline 1950Ø: Cut and fill earthworks at Reserved Forest, BK5.

P11-Pipeline 1950Ø: Short pipe 2m (LW236b) was laid at CH1665.225 – CH1667.275 Reserved Forest, BK5.

P11-Pipeline 1950Ø: Standard pipe 10m (LW403) was laid at CH1655.300 – CH1665.225

P11-Pipeline 1950Ø: Standard pipe 10m (LW316) was laid at CH1645.375 – CH1655.300 Reserved Forest, BK5.




No Progress due to MCO

P11-Pipeline 2500Ø: Pipe laying at CH2620 – CH2612 (Multiplex, BS10) in progress.

P11-Pipeline 1950Ø: Pipe laying at CH79 – CH89 (Hening, BK5E) in progress.

P11-Pipeline 1800Ø: Rock hacking work at line stopping (Bukit Dengkil) in progress.

P11-Pipeline 2500Ø: Pipe laying at CH2594 – CH2597 (Jln PBS 14/16, Tmn Per Bukit Serdang).

P11-Pipeline 1950Ø: Pipe laying at CH1719 – CH1721 (Reserved Forest, BK5) in progress.

P11-Pipeline 1950Ø: Casting of anchor blocks at reserved forest, BK5 in progress.

P11-Pipeline 1800Ø: Pipe laying at CH5011 – CH5021 (Phase 1, Line Stopping, Bukit Dengkil).

P11-Pipeline 1950Ø: Pipe laying at CH1709 – CH1719 (Reserved Forest, BK5) in progress.









P11-Pipeline 1950Ø: Pipe laying at CH79.400 – CH89.325 (Hening, BK5E) in progress.

P11-Pipeline 1950Ø: Casting of thrustblock for VB 45° at CH118-CH121 (Hening, BK5E).

P11-Pipeline 1950Ø: Pipe laying at CH1827-CH1837 (Hutan Rimba, BK5) in progress.

P11-Pipeline 2500Ø: Pipe laying at CH2675.914 – CH2667.989 (Multiplex, BS10) in progress.

P11-Pipeline 1950Ø: Laying of VB 45° at CH1916-CH1920 (Hutan Rimba, BK5) in progress.

P11-Pipeline 2500Ø: Pipe laying at CH2660-CH2652 (Multiplex, BS10) in progress.

P11-Pipeline 1800Ø: Pipe laying at CH4960-CH4970 (Phase 1 Line stopping, Bukit Dengkil).

P11-Pipeline 1950Ø: Installation of Air valve tee at CH1810-CH1813 (Hutan Rimba, BK5).