P11-Pipeline 2500Ø: Road reinstatement works at CH2193 (Jalan PBS14/7) in progress.
P11-Pipeline 2500Ø: Pipe laying at Jalan PBS14/7 in progress.
P11-Pipeline 2500Ø: Piloting work at alignment Jalan PBS14/16 in progress.
P11–Pipeline 2400Ø: Pipe laying at Jalan BK6E in progress.
P11 – Pipeline 2500Ø: Preparation for hydrotest at CH1925 (Sg. Kuyuh) in progress.
Dec 18
Nov 18
Oct 18
Sep 18
Aug 18
Jul 18
Jun 18
May 18
Apr 18
Mar 18
Feb 18
Jan 18

P11-Pipeline 2400Ø: Pipe laying at CH6728.710 to CH6725.160 (Jalan BK6E) in progress.

P11–Pipeline 2400Ø: Laying of air valve tee at CH4591.097 (Jalan PUJ9) in progress.

P11–Pipeline 2500Ø: Fabrication of bends for Sungai Kuyuh overcrossing (CH1250) in progress.

P11-Pipeline 2400Ø: Laying of 45˚ bend at CH6725 to CH6722 (Jalan BK6E) in progress.

P11-Pipeline 2500Ø: Road reinstatement works at CH2193 (Jalan PBS14/7) in progress.

P11-Pipeline 2400Ø: Laying of 10˚ bend at CH4591 to 4594 (Jalan PUJ9) in progress.

P11-Pipeline 2500Ø: Pipe laying at CH2193 to CH2201 (Jalan PBS14/7) in progress.








P11–Pipeline 2400Ø: Reinstatement work at Jalan BK6F in progress.

P11–Pipeline 2400Ø: Casting of thrust block for 90˚ bend at Jalan PUJ9 in progress.

P11–Pipeline 2400Ø: Backfilling work at Jalan PBS14/7 in progress.

P11-Pipeline 2400Ø: Laying of 90˚ bend at Jalan BK6E in progress.

P11-Pipeline 2500Ø: Pipe laying at Jalan PBS14/7 in progress.

P11-Pipeline 2500Ø: Piloting work at alignment Jalan PBS14/16 in progress.

P11-Pipeline 2400Ø: Reinstatement work for walkway along Jalan BK6F in progress.

P11-Pipeline 2500Ø: Laying of 60˚ bend at Sg Kuyuh overcrossing in progress.









P11-Pipeline 2500Ø: Pipe laying at Jalan PBS14/7 in progress.

P11–Pipeline 2400Ø: Pipe laying at Jalan BK6E in progress.

P11–Pipeline 2400Ø: Reinstatement work at Jalan BK6E in progress.

P11-Pipeline 2400Ø: Joint survey for road settlement monitoring at MEX Highway.

P11-Pipeline 2500Ø: Casting of thrust block for 45° bend at Jalan PBS14/7 in progress.

P11-Pipeline 2400Ø: Piloting work at Jalan BK6E in progress.

P11-Pipeline 2400Ø: Construction of air valve chamber at Jalan BK6F in progress.








P11–Pipeline 1950Ø: Pipes delivery at Jalan PUJ9 in progress.

P11–Pipeline 2500Ø: Construction of receiving pit at Jalan Kasturi in progress.

P11–Pipeline 1950Ø: Casting for base of air valve chamber at Jalan TPK in progress.

P11-Pipeline 2400Ø: Pipe laying at Jalan PUJ9 in progress.

P11-Pipeline 2400Ø: Laying of 45˚ bends at Jalan BK6F in progress.

P11-Pipeline 2400Ø: Driving sheetpiles at Jalan BK6F for slope protection in progress.

P11-Pipeline 2400Ø: installation of fittings for offset a/v tee at Jalan BK6F in progress.

P11-Pipeline 2400Ø: Pipe laying at Jalan BK6F in progress.









P11–Pipeline 2400Ø: Casting of thrust block for bend 45˚ at Jalan BK6f in progress.

P11–Pipeline 1950Ø: Pipes delivery at Jalan BK6 in progress.

P11–Pipeline 2400Ø: Construction of thrust block at MEX Highway in progress.

P11-Pipeline 2400Ø: Pipe laying at Jalan PUJ9 in progress.

P11-Pipeline 2400Ø: Air testing to welding joint at Jalan BK6F in progress.

P11-Pipeline 2400Ø: Fabrication of S-bend at Jalan BK6F in progress.

P11-Pipeline 2400Ø: Backfilling work to pipeline at Jalan BK6F in progress.








P11–Pipeline 2400Ø: Pipe jacking at Jalan BK6F in progress (11/27 nos).

P11–Pipeline 2400Ø: Pipe laying at Jalan BK6F in progress.

P11–Pipeline 2400Ø: Road restatement work at Jalan BK6F in progress.

P11-Pipeline 2400Ø: Pipe laying at Jalan PUJ9 in progress.

P11-Pipeline 2400Ø: Installation of wash out tee at Kasturi/MEX highway in progress.

P11-Pipeline 2400Ø: Pipe laying at Jalan PUJ9/11 in progress.

P11-Pipeline 2500Ø: Pipe laying at Jalan PBS 14/5 in progress.

P11-Pipeline 2500Ø: Preparation for jacking pit at Jalan Kasturi in progress.













P11–Pipeline 2400Ø: Casting of anchor block CH4476.5 at Kasturi-MEX highway in progress.

P11–Pipeline 2400Ø: Pipe laying works at CH6036.6 (Jalan Kinrara 6F) in progress.

P11–Pipeline 2400Ø: Casting of thrust block for HB10° at CH5973 – CH5974 (Jalan Kinrara 6F)

P11–Pipeline 2400Ø:Mackintosh probe test at CH4275 (Tmn Perindustrian Kinrara) in progress.

P11-Pipeline 2400Ø: Pipe laying works at CH4762.4 (Jalan PUJ9/11) in progress.

P11-Pipeline 2400Ø: Delivery of pipes at PUJ9/11 in progress.

P11-Pipeline 2400Ø: Excavation work at Jalan PUJ8 in progress.

P11-Pipeline 2400Ø: Installation of inner collar for jacking pipe across MEX highway in progress.









P11–Pipeline 1950Ø: Fixing of S-bend for overcrossing pipes at Jalan TPK in progress.

P11–Pipeline 1950Ø: Concrete casting of air valve chamber at Jalan BK6 in progress.

P11–Pipeline 2400Ø: Concreting for trust block of 25˚bend at Jalan PUJ 9/11 in progress.

P11–Pipeline 2400Ø: Laying of 30˚bend at Jalan PUJ 9/11 in progress.

P11-Pipeline 2500Ø: Pipe laying at Jalan BS10 in progress.

P11–Pipeline 2400Ø: Welding of inner collar at jacking pipes crossing MEX Highway in progress.







P11–Pipeline 1950Ø: Concreting to Horizontal bend 45˚ at CH3692 (Jalan TPK) in progress.

P11–Pipeline 2400Ø: Excavation for receiving pit at CH6550 (Jalan BK6f) in progress.

P11–Pipeline 2500Ø: Casting of caisson for receiving pit at CH1100 (DBKL/ITIS) in progress.

P11–Pipeline 2400Ø: Pipe laying at CH5306 – CH5310 (Jalan PUJ 9) in progress.

P11–Pipeline 2400Ø: Pipe laying at CH5310-CH5311 (Jalan PUJ 9) in progress.

P11–Pipeline 1950Ø: Pipe laying at CH3607-CH3609 (Jalan TPK) in progress.

P11–Pipeline 2400Ø: Pipe jacking work at CH4506 (MEX Highway) in progress.

P11-Pipeline 1950Ø: Concreting work for washout chamber base at CH1075 in progress.









P11–Pipeline 2500Ø: Construction of caisson for jacking pit at CH1100 (DBKL/ITIS) in progress.

P11 – Pipeline 2400Ø: Piloting works in progress at Jalan Kinrara 6F.

P11 – Pipeline 2400Ø: Casting of anchor block at CH5508 (PUJ 8) in progress.

P11–Pipeline 2500Ø: Construction of pile cap for Sg. Kuyuh river-crossing (CH1314) in progress.

P11 – Pipeline 1950Ø: Pipe laying in progress at CH3625 (Taman Perindustrian Kinrara)

P11 – Pipeline 2500Ø: Material inspection for delivered pipes/fittings at Jalan Kasturi.







P11 – Pipeline 2400Ø: Concstruction of AV Chamber at CH4235 (Jalan Kasturi) in progress.

P11 – Pipeline 2400Ø: Trench excavation at CH5212 (Jalan PUJ 9) in progress.

P11 – Pipeline 2400Ø: Sand filling at CH3500 (Jalan Kasturi) in progress.

P11 – Pipeline 2400Ø: Pipe Delivery at CH5800 (Jalan Kinrara 6F) in progress.

P11 – Pipeline 2400Ø: Pipe laying at CH3485 (Jalan Kasturi) in progress.

P11 – Pipeline 1950Ø: Pipe laying at CH3165 (Taman Perindustrian Kinrara) in progress.

P11 – Pipeline 2500Ø: Casting of concrete caisson at CH1100 (Sg. Kuyuh/DBKL) in progress.

P11 – Pipeline 2400Ø: Pipe laying works at CH3477 (Jalan Kasturi) in progress.









P11 – Pipeline 1950Ø: Pipe Laying Works at CH1136 (Bandar Kinrara 6) in progress.

P11 – Pipeline 2400Ø: Casting of Thrust Block at CH5076 (PUJ 8) in progress.

P11 – Pipeline 2400Ø: Pipe laying works at CH3584 (Jalan Kasturi) in progress.

P11 – Pipeline 2400Ø: Pipe Laying Works at CH5079 (PUJ 9) in progress.

P11 – Pipeline 2500Ø: Preparation for hydrotest at CH1925 (Sg. Kuyuh) in progress.

P11 – Pipeline 2400Ø: Piloting works at CH5300 (PUJ 9) in progress.

P11 – Pipeline 2500Ø: Casting of Counter Weight Block at CH1132 (DBKL/ASTRO) in progress.

P11 – Pipeline 2500Ø: Construction of pipe support for river-crossing at CH1258 (DBKL/ASTRO).