P9 – Phase 1 Reservoir: Rectification works for defect list at roof slab in progress.
P9 – External M&E Works: Testing for compound lighting in progress.
P9 – RC Chamber: Installation of RC slab cover for altitude valve chamber in progress.
P9 – Phase 1 Reservoir: Impounding water into compartment 1 for water tightness test in progress.
P9 – SI Works: Monitoring of underground water level at BH4 in progress.
P9 – Road Works: Compaction test (FDT) for sub-base in progress.
Current
Aug 19
Jul 19
Jun 19
May 19
Apr 19
Mar 19
Feb 19
Jan 19
Completed
![](https://langat2.paab.my/wp-content/uploads/2019/09/P92.jpg)
P9 – Road Works: Surface cleaning prior to laying of wearing course in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/09/P984.png)
P9 – Phase 1 Reservoir: External painting works at compartment 2 in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/09/P9167.png)
P9 – Phase 1 Reservoir: Casting of perimeter apron slab at compartment 2 in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/09/P9256.png)
P9 – Road Works: Laying of wearing course in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/09/P92-150x150.jpg)
![](https://langat2.paab.my/wp-content/uploads/2019/09/P984-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/09/P9167-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/09/P9256-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/08/P92-1.jpg)
P9 – Detention Pond: Desilting of detention pond in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/08/P965.png)
P9 – Phase 1 Reservoir: Rectification works for defect list at roof slab in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/08/P9155.png)
P9 – Phase 1 Reservoir: Painting on external wall in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/08/P9221.png)
P9 – Phase 1 Reservoir: Drainage work at compartment 1 in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/08/P92-1-150x150.jpg)
![](https://langat2.paab.my/wp-content/uploads/2019/08/P965-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/08/P9155-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/08/P9221-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/08/P92.jpg)
P9 – Phase 1 Reservoir: Water level monitoring for water tightness test (compartment 1).
![](https://langat2.paab.my/wp-content/uploads/2019/08/P992.png)
P9 – RC Chamber: Installation of RC Precast cover for Bypass Chamber in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/08/P9179.png)
P9 – M&E Works: Installation of copper tape for lightning protection system in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/08/P9271.png)
P9 – Phase 1 Reservoir: Impounding water into compartment 2 for testing in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/08/P9361.png)
P9 – Valve Installation: Installation of headstock and spindle bar in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/08/P9444.png)
P9 – Site Formation: Turfing works at Phase 2 area in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/08/P92-150x150.jpg)
![](https://langat2.paab.my/wp-content/uploads/2019/08/P992-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/08/P9179-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/08/P9271-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/08/P9361-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/08/P9444-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/06/P92.jpg)
P9 – Site Formation: Turfing works at Phase 2 area in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/06/P967.png)
P9 – Drainage Works: Installation of HDG MS Grating in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/06/P9136.png)
P9 – RC Chamber: Installation of precast RC slab cover in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/06/P9208.png)
P9 – Phase 1 Reservoir: Impounding water into compartment 1 for water tightness test in progress. Water level as on 24/5/2019 is 6750mm.
![](https://langat2.paab.my/wp-content/uploads/2019/06/P9350.png)
P9 – Switch Room: Touch up works for external wall painting in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/06/P9426.png)
P9 – Phase 1 Reservoir: Rectification works to plug the leakage on wall in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/06/P92-150x150.jpg)
![](https://langat2.paab.my/wp-content/uploads/2019/06/P967-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/06/P9136-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/06/P9208-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/06/P9350-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/06/P9426-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/05/P92.jpg)
P9 – Valve Installation: Installation of Altitude Valve in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/05/P972.png)
P9 – Phase 1 Reservoir: Rectification of defect at roof slab in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/05/P9149.png)
P9 – Site Formation: Turfing works at Phase 2 area in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/05/P9216.png)
P9 – Phase 1 Reservoir: Impounding water into compartment 1 for water tightness test in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/05/P9321.png)
P9 – Site Clearing: Dismantlinh of temporary workers’ camp in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/05/P9396.png)
P9 – External M&E Works: Testing for compound lighting in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/05/P9467.png)
P9 – RC Chamber: Installation of RC slab cover for altitude valve chamber in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/05/P92-150x150.jpg)
![](https://langat2.paab.my/wp-content/uploads/2019/05/P972-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/05/P9149-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/05/P9216-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/05/P9321-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/05/P9396-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/05/P9467-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/04/P92-1.jpg)
P9 – Phase 1 Reservoir: Impounding water into compartment 1 for water tightness test in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9102.png)
P9 – Road Works: Laying of crusher run for road-base (Zone A) in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9180.png)
P9 – Valve Installation: Installation of 700mm DN Butterfly Valve in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9262-1.png)
P9 – SI Works: Monitoring of underground water level at BH4 in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9340.png)
P9 – M&E Works: Insulation test for compound lighting cable in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9416.png)
P9 – Site Formation: Close turfing to the slope formation in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9493.png)
P9 – Phase1 Reservoir Rectification works to the leaked structure inside compartment 2 in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/04/P92-1-150x150.jpg)
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9102-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9180-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9262-1-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9340-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9416-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9493-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/04/P92.jpg)
P9 – Anti-climb Fence: Installation of anti-climb panel in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/04/P976.png)
P9 – Pipework: Installation of 900mmØ Butterfly Valve inside inlet chamber in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9169.png)
P9 – Pipework: Installation of 700mmØ Butterfly Valve inside inlet chamber in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9262.png)
P9 – Site Formation: Close turfing to slope formation on top of RE Wall 1 in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9353.png)
P9 – Phase 1 Reservoir: Impounding water into compartment 1 for water tightness test in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9455.png)
P9 – Road Works: Compaction test (FDT) for sub-base in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9524.png)
P9 – Road Works: Laying of crusher run for road base in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9595.png)
P9 –M&E (External works): Cable laying for compound lighting in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/04/P92-150x150.jpg)
![](https://langat2.paab.my/wp-content/uploads/2019/04/P976-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9169-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9262-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9353-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9455-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9524-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/04/P9595-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/02/P92.jpg)
P9 – Drainage Works: Casting of interceptor drain on top of RE Wall 1 in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/02/P988.png)
P9 – Pipe Laying Works: Casting of thrust block for 45˚ 1100Ø bend in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/02/P9172.png)
P9 – Pipe Laying Works: Pipe laying works for 1100mmØ MS pipe in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/02/P9252.png)
P9 – Earthwork & Site Formation: Field Density Test for backfilling works in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/02/P9343.png)
P9 – Phase 1 Reservoir: Checking for any possible cavity below the RC slab prior to rectification works for expansion joint in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/02/P9484.png)
P9 – Pipe Laying Works: Applying bitumen wrapping to 1100mmØ MS pipe in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/02/P9572.png)
P9 – HSSE: Installation of temporary silt fence in progress.
Array
![](https://langat2.paab.my/wp-content/uploads/2019/02/P92-150x150.jpg)
![](https://langat2.paab.my/wp-content/uploads/2019/02/P988-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/02/P9172-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/02/P9252-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/02/P9343-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/02/P9484-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/02/P9572-150x150.png)