P9 – Phase 1 Reservoir: Rectification works for defect list at roof slab in progress.
P9 – External M&E Works: Testing for compound lighting in progress.
P9 – RC Chamber: Installation of RC slab cover for altitude valve chamber in progress.
P9 – Phase 1 Reservoir: Impounding water into compartment 1 for water tightness test in progress.
P9 – SI Works: Monitoring of underground water level at BH4 in progress.
P9 – Road Works: Compaction test (FDT) for sub-base in progress.
Current
Aug 19
Jul 19
Jun 19
May 19
Apr 19
Mar 19
Feb 19
Jan 19
Completed

P9 – Road Works: Surface cleaning prior to laying of wearing course in progress.

P9 – Phase 1 Reservoir: External painting works at compartment 2 in progress.

P9 – Phase 1 Reservoir: Casting of perimeter apron slab at compartment 2 in progress.

P9 – Road Works: Laying of wearing course in progress.





P9 – Detention Pond: Desilting of detention pond in progress.

P9 – Phase 1 Reservoir: Rectification works for defect list at roof slab in progress.

P9 – Phase 1 Reservoir: Painting on external wall in progress.

P9 – Phase 1 Reservoir: Drainage work at compartment 1 in progress.





P9 – Phase 1 Reservoir: Water level monitoring for water tightness test (compartment 1).

P9 – RC Chamber: Installation of RC Precast cover for Bypass Chamber in progress.

P9 – M&E Works: Installation of copper tape for lightning protection system in progress.

P9 – Phase 1 Reservoir: Impounding water into compartment 2 for testing in progress.

P9 – Valve Installation: Installation of headstock and spindle bar in progress.

P9 – Site Formation: Turfing works at Phase 2 area in progress.







P9 – Site Formation: Turfing works at Phase 2 area in progress.

P9 – Drainage Works: Installation of HDG MS Grating in progress.

P9 – RC Chamber: Installation of precast RC slab cover in progress.

P9 – Phase 1 Reservoir: Impounding water into compartment 1 for water tightness test in progress. Water level as on 24/5/2019 is 6750mm.

P9 – Switch Room: Touch up works for external wall painting in progress.

P9 – Phase 1 Reservoir: Rectification works to plug the leakage on wall in progress.







P9 – Valve Installation: Installation of Altitude Valve in progress.

P9 – Phase 1 Reservoir: Rectification of defect at roof slab in progress.

P9 – Site Formation: Turfing works at Phase 2 area in progress.

P9 – Phase 1 Reservoir: Impounding water into compartment 1 for water tightness test in progress.

P9 – Site Clearing: Dismantlinh of temporary workers’ camp in progress.

P9 – External M&E Works: Testing for compound lighting in progress.

P9 – RC Chamber: Installation of RC slab cover for altitude valve chamber in progress.








P9 – Phase 1 Reservoir: Impounding water into compartment 1 for water tightness test in progress.

P9 – Road Works: Laying of crusher run for road-base (Zone A) in progress.

P9 – Valve Installation: Installation of 700mm DN Butterfly Valve in progress.

P9 – SI Works: Monitoring of underground water level at BH4 in progress.

P9 – M&E Works: Insulation test for compound lighting cable in progress.

P9 – Site Formation: Close turfing to the slope formation in progress.

P9 – Phase1 Reservoir Rectification works to the leaked structure inside compartment 2 in progress.








P9 – Anti-climb Fence: Installation of anti-climb panel in progress.

P9 – Pipework: Installation of 900mmØ Butterfly Valve inside inlet chamber in progress.

P9 – Pipework: Installation of 700mmØ Butterfly Valve inside inlet chamber in progress.

P9 – Site Formation: Close turfing to slope formation on top of RE Wall 1 in progress.

P9 – Phase 1 Reservoir: Impounding water into compartment 1 for water tightness test in progress.

P9 – Road Works: Compaction test (FDT) for sub-base in progress.

P9 – Road Works: Laying of crusher run for road base in progress.

P9 –M&E (External works): Cable laying for compound lighting in progress.









P9 – Drainage Works: Casting of interceptor drain on top of RE Wall 1 in progress.

P9 – Pipe Laying Works: Casting of thrust block for 45˚ 1100Ø bend in progress.

P9 – Pipe Laying Works: Pipe laying works for 1100mmØ MS pipe in progress.

P9 – Earthwork & Site Formation: Field Density Test for backfilling works in progress.

P9 – Phase 1 Reservoir: Checking for any possible cavity below the RC slab prior to rectification works for expansion joint in progress.

P9 – Pipe Laying Works: Applying bitumen wrapping to 1100mmØ MS pipe in progress.

P9 – HSSE: Installation of temporary silt fence in progress.