Open Menu
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Pakej 9 : Kolam Air AU3 Berkapasiti 28 Juta Liter 2016
print
2019
2018
2017
2016
Dec 16
Nov 16
Oct 16
Sep 16
Aug 16
P9 – RC Wall: Dismantle Formwork in progress at Zone B3 & A3
P9 – Reservoir Phase 1: Inspection of soft ground by Runhill geotech team.
P9 – Reservoir Phase 1: Fixing rebar for slab zone A4 in progress.
P9 – Reservoir Phase 1: Water stop installation at Zone A6 in progress.
P9 – Reservoir Phase 1: Concreting work at Zone A6 in progress.
P9 – Reservoir Phase 1: Construction of foundation for Reservoir in progress.
P9 – RE Wall 2: Installation of precast panel in progress
P9 – Re Wall 2: Construction of drainage system for R.E wall in progress.
P9 – RE Wall 2: Installation of precast panel in progress.
P9 – RC Wall: Concreting work at Zone B-1 in progress.
P9 – RC Wall: Installation of reinforcement bar at Zone B2 in progress.
P9 – Reservoir Phase 1: Fixing of reinforcement for slab Zone A5 & B5 in progress.
P9 – Reservoir Phase 1: Cube test for 7 days (G20).
P9 – Storage Yard: QAQC inspection for MS Pipes in progress.
P9 – RE Wall 2: Installation of leveling pad in progress.
P9 – RC Wall: Installation of formwork & rebar in progress.
P9 – RC Wal: Temporary hoarding for Telecommunication Tower completed
P9 – RC Wall: Preparation for concrete test cube.
P9 – RE Wall 2: Delivery of pre-cast panel in progress.
P9 – Reservoir (Phase 1) Platform: Excavation for working platform formation in progress.
P9 – Phase 1 platform: Earthwork in progress.
P9 – Overall site: Field density test for filling layer in progress.
P9 – Overall site: Lab test for imported earth (borrow pit) in progress.
P9 – Overall site: Lab test for imported earth (borrow pit) in progress.
P9- Reservoir Platform: Site clearing in progress.
P9- Reservoir Platform: Mobilization of additional machinery for earthwork.
P9- General: Project signboard with all parties contact number completed.
P9- General: Project signboard with all parties contact number completed.
P9- General: Soil investigation work in progress