2020
2019
2018
Dec 20
Nov 20
Oct 20
Sep 20
Aug 20
Jul 20
Jun 20
May 20
Apr 20
Mar 20
Feb 20
Jan 20

P13: Chamber Concreting of 2nd lift Flowmeter Chamber 2 in progress












P13: Earthworks Breaking hard material and slope trimming FGL 99.50m in progress












P13: Earthworks Breaking hard material and slope excavation in progress

P13: Drainage Excavation of Berm Drain Type 2 in progress









P13: Earthworks Hacking hard material and slope excavation in progress

P13: Detention Pond Excavation Detention Pond in progress









P13: Drainage Hacking and excavation Drain Type 2 at FGL 114.50m in progress

P13: Detention Pond Excavation and USM replacement at Detention Pond in progress











P13: Drainage Brickworks to 450mm PC Drain in progress












P13-Pipework: Excavation for Air Valve Chamber and Bypass Chamber in progress.

P13- Reservoir: Concreting for Roof Slab Panel RC3 in progress.

P13- Reservoir: Rebar to Roof Slab Panel RC3 in progress.

P13- Drainage: Concreting of RC Wall for 450mm PC Drain in progress.

P13- Reservoir: Fixing formwork for Roof Slab Panel RB3 in progress.

P13- RE Wall: Backfilling works in progress.







P13- Drainage: Excavation for Berm Drain Type 1 in progress.

P13- Reservoir: Rebar for Roof Slab Panel B2 in progress.

P13- Reservoir: Formwork for 3rd lift of wall Panel A7 in progress.

P13- Reservoir: Concreting of 2nd lift wall Panel B7 in progress.

P13- Drainage: Concreting for PC drain in progress.

P13- RE Wall: Backfilling to RE Wall in progress.






No Progress due to MCO

P13- Reservoir Compartment 2: Concreting of 3rd lift wall (Panel A4) in progress.

P13- Reservoir Compartment 1: Concreting of 1st lift wall for Outlet Chamber in progress.

P13- Drainage: Fixing formwork to 3rd lift wall of Manhole MH05 in progress.

P13- Reservoir Compartment 2: Fixing formwork to 1st lift wall of Panel B7 in progress.

P13- Detention Pond: Excavation to Detention Pond in progress.

P13- Reservoir Compartment 1: Rebar and formwork to Roof Slab Panel RC2 in progress.







P13- Reservoir: Concreting of roof slab Panel RA1 in progress

P13- Reservoir: Concreting of roof slab Panel RC1 in progress.

P13- Drainage: Plastering work to 300mm PC Drain in progress.

P13- Reservoir Compartment 2: Formwork to 1st lift wall Panel C7 in progress.

P13- RE Wall Phase 2: Hacking and excavation to RE Wall platform in progress.












