Open Menu
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Pakej 12 : Kolam Air Sg. Besi Berkapasiti 22 Juta Liter 2017
print
2020
2019
2018
2017
Dec 17
Nov 17
Oct 17
Sep 17
Aug 17
Jul 17
Jun 17
May 17
Apr 17
Mar 17
Feb 17
Jan 17
P12-Earthworks: Bulk excavation at platform area in progress.
P12-Earthworks: Removal of hard material at reservoir platform area in progress.
P12-Reservoir: Concrete blinding at base slab in progress.
P12-Reservoir: Rebar installation at base slab in progress.
P12-Reservoir: Welding works to scour pipe in progress.
P12-Switch Room: Plate bearing test in progress.
P12- Earthworks: Bulk excavation at platform area in progress.
P12- RC Wall: Mackintosh Probe Test in progress.
P12- Earthworks: Removal of existing shotcrete and soil nail in progress.
P12- RC Wall: Casting for wall in progress.
P12- Reservoir: Plate Bearing Test in progress.
P12- Reservoir: Rebar installation works at Inlet Chamber in progress.
P12- Earthworks: Bulk excavation at platform area in progress.
P12- Reservoir: Removing of existing shotcrete in progress.
P12- Soil Investigation: Plate bearing test at reservoir area in progress.
P12- RC Wall: Fixing rebars for base slab in progress.
P12- Reservoir: Construction of temporary workers’ quarters in progress.
P12- Reservoir: Bulk excavation work at Phase 1 platform area in progress.
P12- RC Wall: Excavation works in progress.
P12- General: Site visit during Technical Meeting No.12/2017.
P12- Reservoir: Bulk excavation work at Phase 1 platform area in progress.
P12- Reservoir: Site visit during Technical Meeting No.11/2017
P12- Reservoir: Disposal of debris in progress.
P12- Reservoir: Tool box talk during Q1/2017 Safety Day.
P12- Reservoir: Bulk excavation work at Phase 1 platform area in progress.
P12- General: Site visit during Technical Meeting No.10/2017.
P12- HSSE: Weekly Toolbox Meeting conducted at site on 27/7/2017.
P12-General: Piloting works at Jalan Desa Cheras in progress.
P12-General: Road reinstatement after piloting works at Jalan Desa Cheras.
P12- Reservoir: Bulk excavation work at reservoir Phase 1&2 area in progress.
P12-Reservoir: Site visit conducted during technical meeting no.9 dated 22/6/2017.
P12- Pipeworks: Delivery of MS pipe 1054mmØ at Jalan Desa Cheras in progress.
P12- Reservoir: Site clearing in progress.
P12- Reservoir: Joint survey for earthwork activities in progress.
P12- Pipeworks: QA/QC inspection for delivered pipes at Jalan Desa Cheras in progress.
P12- Reservoir: Excavation for reservoir platform in progress.
P12- General: Construction of bund wall at skid tank area in progress.
P12- Reservoir: Exporting earth from reservoir platform to Lake Sapphire Puchong in progress.
P12-General: Installing silt fence along the hoarding at Jalan Desa Cheras in progress.
P12-Reservoir: Exporting out the extra earth in progress.
P12-General: Maintaining the silt trap at Jalan Desa Cheras in progress.
P12-Reservoir: Bulk excavation to platform level 91m in progress.
P12- General: Construction of Wash Trough in progress.
P12- Access Road: Construction of temporary access road in progress.
P12- Reservoir: Site clearing in progress.
P12-General: Installation of project signboard in progress.
P12- Reservoir: Site clearance in progress.
P12- Reservoir : Site clearance in progress.
P12- Reservoir: Site clearance in progress.
P12 – Pre-Construction Photo
P12 – Pre-Construction Photo
P12 – Pre-Construction Photo
P12 – Pre-Construction Photo