Open Menu
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Pakej 12 : Kolam Air Sg. Besi Berkapasiti 22 Juta Liter 2019
print
2020
2019
2018
2017
Dec 19
Nov 19
Oct 19
Sep 19
Aug 19
Jul 19
Jun 19
May 19
Apr 19
Mar 19
Feb 19
Jan 19
P12 – Reservoir: Concreting works for perimeter drain at Reservoir in progress.
P12 – Turfing Work: Turfing works at surrounding Reservoir Compartment 1 area in progress.
P12 – Reservoir: Rectification works on external wall compartment 2 in progress.
P12 – Fencing: Casting of concrete kerb for anti-climb fence in progress.
P12 – Drainage Works: Clearing debris and mud inside the 600mm PC Block drain in progress.
P12-Drainage: Concreting works for manhole at Jalan Damai Perdana 3/4 in progress.
P12-Reservoir: Excavation works for reservoir perimeter drain in progress.
P12-Reservoir: Concreting works for PC block drain at perimeter compartment 1 in progress.
P12-Reservoir: Water Tightness Test for compartment 2 in progress.
P12-RC Chamber: Preparation for precast cover slab in progress.
P12-Reservoir: Preparation for concrete base (sub-soil drain of compartment 1) in progress.
P11-Pipeline 1950Ø: Installation of counterweight for pipeline at Hening, BK5E in progress.
P12-Reservoir: Installation of Nylex-cordrain at external wall compartment 1 in progress.
P12-Reservoir: Transferring of water from compartment 1 to compartment 2 in progress.
P12-Detention Pond: Concreting works for RC staircase at detention pond in progress.
P12-Earthworks: Slope reinstatement works at Jalan Desa Cheras in progress.
P12-Reservoir: Rectification works at external wall compartment 1 in progress.
P12 – SI Works: Installation of Standpipe Piezometer, SP-1 in progress.
P12-Drainage: Construction of drainage manhole, MH18 in progress.
P12-Detention Pond: Concreting works for outlet wing wall in progress.
P12-Backfilling Works: Slope reinstatement works at downstream CH100 in progress.
P12-Detention Pond: Excavation to base of PC block drain at detention pond in progress.
P12-Detention Pond: Concreting works for base of PC block drain in progress.
P12-Drainage: Casting of cascade drain at slope facing Jalan Desa Cheras in progress.
P12-Fencing Works: Installation of anti-climb fence post at CH547 in progress.
P12-Detention Pond: Excavation works for base of detention pond in progress.
P12-Detention Pond: Construction of Manhole MH22 in progress.
P12-Drainage: Rebar installation for second lift wall MH23 in progress.
P12-Gate & Fencing: Construction ofanti-climb fence kicker at CH247-CH197 in progress.
P12-Electrical Works: Cable laying works to Inlet Flowmeter Chamber in progress.
P12-Reservoir – Installation works for skylight lantern at roof slab in progress.
P12-Switch Room – Painting works for finishing coat at external wall in progress.
P12-Reservoir – Impounding water into compartment 1 for leakage test in progress.
P12-Fencing Works- Installation of anti-climb fencing post at CH390-CH490 in progress.
P12-Drainage- Plastering works for side wall of 300mm PC block drain in progress.
P12-RC Chamber- Concreting works for second lift wall Inlet Chamber no.1 in progress.
P12-Drainage: Construction of Inter-Connection Chamber in progress.
P12-Pipe Works: Laying of 600DN short piece MS pipe in progress.
P12-Drainage: Laying of 300mm PC block drain at CH190 in progress
P12-RC Chamber: Construction of Inlet Chamber no.1 in progress.
P12-Reservoir: Impounding water into compartment 1 for leakage test in progress.
P12-Drainage: Construction of PC block drain at main access road (CH150-CH250) in progress.
P12-Earth Works: Trimming slope at CH100 in progress.
P12-Pipe Works: Laying 800DN MS Inlet Pipe towards Orifice Plate Chamber in progress.
P12-Reservoir: Impounding water into compartment 1 for leakage test in progress. (415mm)