2020
2019
2018
2017
P12-Gate & Fencing: Construction ofanti-climb fence kicker at CH247-CH197 in progress.
Dec 19
Nov 19
Oct 19
Sep 19
Aug 19
Jul 19
Jun 19
May 19
Apr 19
Mar 19
Feb 19
Jan 19







P12 – Reservoir: Concreting works for perimeter drain at Reservoir in progress.

P12 – Turfing Work: Turfing works at surrounding Reservoir Compartment 1 area in progress.

P12 – Reservoir: Rectification works on external wall compartment 2 in progress.

P12 – Fencing: Casting of concrete kerb for anti-climb fence in progress.

P12 – Drainage Works: Clearing debris and mud inside the 600mm PC Block drain in progress.






P12-Drainage: Concreting works for manhole at Jalan Damai Perdana 3/4 in progress.

P12-Reservoir: Excavation works for reservoir perimeter drain in progress.

P12-Reservoir: Concreting works for PC block drain at perimeter compartment 1 in progress.

P12-Reservoir: Water Tightness Test for compartment 2 in progress.





P12-RC Chamber: Preparation for precast cover slab in progress.

P12-Reservoir: Preparation for concrete base (sub-soil drain of compartment 1) in progress.

P11-Pipeline 1950Ø: Installation of counterweight for pipeline at Hening, BK5E in progress.

P12-Reservoir: Installation of Nylex-cordrain at external wall compartment 1 in progress.

P12-Reservoir: Transferring of water from compartment 1 to compartment 2 in progress.






P12-Detention Pond: Concreting works for RC staircase at detention pond in progress.

P12-Earthworks: Slope reinstatement works at Jalan Desa Cheras in progress.

P12-Reservoir: Rectification works at external wall compartment 1 in progress.




P12 – SI Works: Installation of Standpipe Piezometer, SP-1 in progress.

P12-Drainage: Construction of drainage manhole, MH18 in progress.



P12-Detention Pond: Concreting works for outlet wing wall in progress.

P12-Backfilling Works: Slope reinstatement works at downstream CH100 in progress.

P12-Detention Pond: Excavation to base of PC block drain at detention pond in progress.

P12-Detention Pond: Concreting works for base of PC block drain in progress.





P12-Drainage: Casting of cascade drain at slope facing Jalan Desa Cheras in progress.

P12-Fencing Works: Installation of anti-climb fence post at CH547 in progress.

P12-Detention Pond: Excavation works for base of detention pond in progress.

P12-Detention Pond: Construction of Manhole MH22 in progress.





P12-Drainage: Rebar installation for second lift wall MH23 in progress.

P12-Gate & Fencing: Construction ofanti-climb fence kicker at CH247-CH197 in progress.

P12-Electrical Works: Cable laying works to Inlet Flowmeter Chamber in progress.

P12-Reservoir – Installation works for skylight lantern at roof slab in progress.

P12-Switch Room – Painting works for finishing coat at external wall in progress.

P12-Reservoir – Impounding water into compartment 1 for leakage test in progress.







P12-Fencing Works- Installation of anti-climb fencing post at CH390-CH490 in progress.

P12-Drainage- Plastering works for side wall of 300mm PC block drain in progress.

P12-RC Chamber- Concreting works for second lift wall Inlet Chamber no.1 in progress.




P12-Drainage: Construction of Inter-Connection Chamber in progress.

P12-Pipe Works: Laying of 600DN short piece MS pipe in progress.

P12-Drainage: Laying of 300mm PC block drain at CH190 in progress

P12-RC Chamber: Construction of Inlet Chamber no.1 in progress.

P12-Reservoir: Impounding water into compartment 1 for leakage test in progress.






P12-Drainage: Construction of PC block drain at main access road (CH150-CH250) in progress.

P12-Earth Works: Trimming slope at CH100 in progress.

P12-Pipe Works: Laying 800DN MS Inlet Pipe towards Orifice Plate Chamber in progress.

P12-Reservoir: Impounding water into compartment 1 for leakage test in progress. (415mm)



