P12-Drainage: Construction of manhole MH5 in progress.
P12- Reservoir: Rebar installation at base slab panel A6 in progress.
Dec 18
Nov 18
Oct 18
Sep 18
Aug 18
Jul 18
Jun 18
May 18
Apr 18
Mar 18
Feb 18
Jan 18
![](https://langat2.paab.my/wp-content/uploads/2019/01/P121.png)
P12-RC Valve Chamber: Casting of 2nd lift wall for outlet flowmeter chamber no.1 in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/01/P12100.png)
P12-Reservoir: Installation of stainless steel cat ladder inside compartment 1 in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/01/P12199.png)
P12-Reservoir (Water Tightness Test): Impounding water into compartment 1 in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/01/P12291.png)
P12-Drainage: Construction of manhole MH5 in progress.
![](https://langat2.paab.my/wp-content/uploads/2019/01/P121-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/01/P12100-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/01/P12199-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2019/01/P12291-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/12/P122.png)
P12-RC Valve Chamber: Construction of Outlet Chamber no.2 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/12/P1278.png)
P12-Pipe Laying: Laying of 900Ø MS outlet pipe in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/12/P12146.png)
P12-Drainage: Concreting works at 3rd lift wall manhole MH13 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/12/P12226.png)
P12-Drainage: Formworks installation at 1st lift wall manhole MH4 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/12/P122-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/12/P1278-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/12/P12146-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/12/P12226-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/11/P124.png)
P12-Reservoir: Construction of external staircase no.2 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/11/P1276.png)
P12-RC Valve Chamber: Construction of outlet chamber no.1 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/11/P12151.png)
P12-Reservoir: Concreting works for roof slab panel R.A2 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/11/P12225.png)
P12-Drainage: Brick laying works at cascade drain MH14-MH15 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/11/P12303.png)
P12-Pipe Laying Works: Laying of 800DN MS inlet pipe in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/11/P124-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/11/P1276-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/11/P12151-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/11/P12225-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/11/P12303-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/10/P124.png)
P12-Reservoir: Construction of external RC staircase no.1 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/10/P1280.png)
P12-Reservoir: Concreting works at roof slab panel R.B3 in progress
![](https://langat2.paab.my/wp-content/uploads/2018/10/P12157.png)
P12-Valve Chamber: Concreting works at second lift wall of by-pass chamber in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/10/P12249.png)
P12-Reservoir: Formworks installation at 3rd lift wall of panel A4 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/10/P124-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/10/P1280-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/10/P12157-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/10/P12249-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/09/P121.png)
P12-Reservoir: Concreting works for 2nd lift wall panel A5 in progress
![](https://langat2.paab.my/wp-content/uploads/2018/09/P125.jpg)
P12-Drainage: Concreting works for base slab of manhole MH8 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/09/P1277.png)
P12-Drainage: Casting of RC wall for 300mm PC block drain MH8-MH13 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/09/P12157.png)
P12-Reservoir: Rebar installation at roof slab panel C2 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/09/P12315.png)
P12-Reservoir: Dismantling formworks for 2nd lift wall A5 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/09/P121-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/09/P125-150x150.jpg)
![](https://langat2.paab.my/wp-content/uploads/2018/09/P1277-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/09/P12157-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/09/P12315-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/08/P122-1.jpg)
P12- Reservoir: Concreting works for roof slab panel R-C1 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/08/P1276.png)
P12- Reservoir: Formworks installation for 3rd wall panel C5 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/08/P12154.png)
P12- Reservoir: Formworks installation for 1st wall panel A4 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/08/P12233.png)
P12- Drainage: Concreting works for 1st lift wall MH 1 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/08/P122-1-150x150.jpg)
![](https://langat2.paab.my/wp-content/uploads/2018/08/P1276-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/08/P12154-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/08/P12233-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/08/P122.jpg)
P12- Reservoir: Concreting works for roof slab panel R.A1 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/08/P1275.png)
P12- Reservoir: Concreting works for 2nd lift wall panel C6 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/08/P12152.png)
P12- Reservoir: Concreting works for 1st lift wall panel A5 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/08/P12229.png)
P12- Reservoir: Rebar and formworks installation for roof slab panel R.B1 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/08/P122-150x150.jpg)
![](https://langat2.paab.my/wp-content/uploads/2018/08/P1275-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/08/P12152-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/08/P12229-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/06/P122.jpg)
P12- Reservoir: Concreting works for first lift wall panel C6 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/06/P1279.png)
P12- Switch Room: Plastering works in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/06/P12132.png)
P12- Reservoir: Fixing rebars at first lift wall panel A7 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/06/P12207.png)
P12- Reservoir: Concreting works for first lift wall panel C7 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/06/P122-150x150.jpg)
![](https://langat2.paab.my/wp-content/uploads/2018/06/P1279-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/06/P12132-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/06/P12207-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/05/P12-April-20182.jpg)
P12- Reservoir: Concreting works for 3rd lift wall panel A1 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/05/P12-April-201877.png)
P12- Switch Room: Concreting works for roof beam and slab in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/05/P12-April-2018152.png)
P12- Reservoir: Rebar installation at base slab panel A6 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/05/P12-April-2018226.png)
P12- Reservoir: Concreting works for base slab panel B7 in progress
![](https://langat2.paab.my/wp-content/uploads/2018/05/P12-April-20182-150x150.jpg)
![](https://langat2.paab.my/wp-content/uploads/2018/05/P12-April-201877-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/05/P12-April-2018152-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/05/P12-April-2018226-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/05/P12-March-20182.jpg)
P12- Reservoir: Concreting works for base slab panel C7 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/05/P12-March-201872.png)
P12- Reservoir: Concreting works for 1st lift wall panel B1 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/05/P12-March-2018149.png)
P12- RC Wall: Casting of 3rd lift wall Panel 2,3,4 & 5 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/05/P12-March-2018222.png)
P12- Switch Room: Concreting works for ground beam and base slab in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/05/P12-March-20182-150x150.jpg)
![](https://langat2.paab.my/wp-content/uploads/2018/05/P12-March-201872-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/05/P12-March-2018149-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/05/P12-March-2018222-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/03/P122.jpg)
P12 – Reservoir: Fixing rebars and formwork for base slab panel B2 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/03/P1284.png)
P12 – Reservoir: Fixing rebars and formwork for base slab panel C2 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/03/P12167.png)
P12 – Reservoir: Fixing rebars first lift wall panel A4 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/03/P12241.png)
P12 – Reservoir: Casting of second lift wall panel 2 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/03/P122-150x150.jpg)
![](https://langat2.paab.my/wp-content/uploads/2018/03/P1284-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/03/P12167-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/03/P12241-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/02/P122.jpg)
P12 – Reservoir: Fixing rebars for base slab panel A2 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/02/P1271.png)
P12 – Reservoir: Concrete surround to spare outlet pipe in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/02/P12145.png)
P12 – Switch Room: Construction of cable trench in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/02/P12210.png)
P12 – Reservoir: Casting of base slab panel A1 in progress.
![](https://langat2.paab.my/wp-content/uploads/2018/02/P122-150x150.jpg)
![](https://langat2.paab.my/wp-content/uploads/2018/02/P1271-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/02/P12145-150x150.png)
![](https://langat2.paab.my/wp-content/uploads/2018/02/P12210-150x150.png)