Open Menu
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Home
Project Info
Project Background
Project Objective
Project Location Plan
Project Layout Plan
Water Treatment Process
Construction Packages
Construction Method
Open Trench Pipe Laying
Trenchless Pipe Laying
Langat 2 Project Team
Frequent Asked Questions
Work Progress
Water Treatment Plant Works
Pakej 1B
Pakej 2A
Pakej 2B
Pakej 15
Northern Corridor Treated Water Bulk Transfer Works
Pakej 6
Pakej 7
Pakej 9
Western Corridor Treated Water Bulk Transfer Works
Pakej 4
Pakej 5
Pakej 10
Pakej 11
Pakej 12
Pakej 13
Pakej 14
Announcement
Traffic Announcements
News
Events
Public Awareness
Corporate Info
About Us
Contact Us
PAAB
Pakej 4 : Kolam Air Imbangan Bukit Enggang Berkapasiti 210 Juta Liter 2017
print
2019
2018
2017
2016
Dec 17
Nov 17
Oct 17
Sep 17
Aug 17
Jul 17
Jun 17
May 17
Apr 17
Mar 17
Feb 17
Jan 17
P4 – Reservoir : Casting of Roof Slab B15 in progress.
P4 – Reservoir : Casting of Wall I6 2nd lift in progress.
P4 – Reservoir : Casting of 1st lift columns in progress.
P4 – Inlet Overflow Structure : Casting of base slab in progress.
P4 – Inlet Overflow Structure : Casting of wall in progress.
.
P4 – Pipeline : Pipe laying on saddle supports in progress.
P4 – Drainage : Laying of PC block drains in progress.
P4 – Drainage : Construction of berm drain in progress.
P4 – Turfing: Turfing work in progress at Main Access Road area.
P4 – Material Delivery: Valves delivered at site and covered with canvas.
P4 – Reservoir : Casting of Roof Slab F7 in progress
P4 – Reservoir : Casting of Columns at Panel B14 in progress
P4 – Reservoir : Casting of Base Slab H6 in progress
P4 – Reservoir : Excavation and laying of subsoil drain in progress.
P4 – TNB Sub Station : Fixing of formworks for roof slab in progress
P4 – Guard House : Fixing of rebars for Base Slab in progress.
P4 – Switch House : Trench excavation in progress
P4 – Main Access Road : Earth filling in progress from CH250 to CH200.
P4 – Overflow Inlet Structure: Fixing of rebars for Base Slab in progress
P4 – Pipeline : Inlet pipes laying (Phase 1 & 2) crossing EKVE Highway in progress.
P4 – Pipeline Concrete surround for inlet pipelines for EKVE crossing in progress.
P4 – Reservoir : Casting of Baffle Wall F7 & F8 2nd lift in progress
P4 – Reservoir : Casting of Base Slab G7 in progress
P4 – Reservoir : Casting of Roof Slab A9 in progress
P4 – Reservoir : Casting of Inlet Valve Chamber L1 in progress
P4 – Main Access Road: Filling works (LHS) from CH250 – CH350 in progress.
P4 – Main Detention Pond: Casting of Wingwall Structure in progress.
P4 – Pipeline : Laying of horizontal bends 1900mmØ inlet pipes in progress.
P4 – Drainage: Construction of PC Block Drain in progress
P4 – Reservoir : Casting of Base Slab A15 in progress.
P4 – Reservoir : Casting of Wall F8 3rd lift in progress.
P4 – Reservoir : Casting of columns 2nd lift in progress.
P4 – TNB Substation : Incidental excavation for foundation in progress.
P4 – Main Access Road : Filling works in progress.
P4 – Pipe Overcrossing : Installation of Arch Beam for Pipe Bridge in progress.
P4 – Sg. Perimbun Pipe Overcrossing : Casting of Saddle Support in progress
P4 – Pipeline : Laying of pipes 2500mm diameter in progress from CH149.
P4 – Drainage : Construction of Berm Drain in progress at Main Access Road (RHS).
P4 – Drainage : Construction of U Drain 3600mm x 1800mm in progress.
P4 – Reservoir : Concreting for base slab C3 in progress.
P4 – Reservoir : Concreting for roof slab D4 & D5 in progress.
P4 – Reservoir : Concreting for 2nd lift wall I8 in progress.
P4 – Reservoir : Concreting for 3rd lift wall E4 in progress.
P4 – Reservoir : Concreting for column in progress.
P4 – Reservoir : Construction of outlet sump in progress.
P4 – Pipeline : Installation of 1900mmØ tee plain & flange ended pipe in progress.
P4 – Main Access Road : Embankment fill at CH380 in progress.
P4 – Main Flood Detention : Construction of roadside drain at CH20 in progress.
P4 – Sg Perimbun Pipe Overcrossing: Fixing rebar & formwork for saddle support in progress.
P4 – Reservoir : Concreting for 1st lift wall panel F4 in progress.
P4 – Reservoir : Concreting for 2nd lift baffle wall panel B3 in progress.
P4 – Reservoir : Concreting for 3rd lift baffle wall panel B7 in progress.
P4 – Reservoir : Concreting for roof slab C1 in progress.
P4 – Reservoir : Concreting for columns in progress.
P4 – Reservoir : Concreting for base slab of inlet valve chamber in progress.
P4 – Reservoir : Concreting for RC Chamber wall in progress.
P4 – Main Access Road : Construction of berm drain at CH300 in progress.
P4 – Sg Perimbun Pipe Overcrossing: Concreting for pier head in progress.
P4 – Pipeline: Excavation at EKVE platform in progress.
P4 – Reservoir : Concreting for 2nd lift baffle wall panel C8 in progress.
P4 – Reservoir : Concreting for base slab I15 in progress.
P4 – Reservoir : Concreting for columns in progress.
P4 – Reservoir : Fixing formwork for roof slab in progress.
P4 – Pipeline: Casting of thrust block for inlet pipe at CH725 in progress.
P4 – Pipeline: Laying of 3300mmØ RCP pipes in progress.
P4 – Pipeline: Laying of 1900mmØ inlet pipe at CH860 in progress.
P4 – Main Access Road : Embankment fill at CH420 in progress.
P4 – Main Access Road : Close turfing at slope CH420 in progress.
P4 – Sg Perimbun Pipe Overcrossing: Concreting for RC piers in progress.
P4 – Reservoir : Concreting for base slab panel F6 in progress.
P4 – Reservoir : Concreting for 2nd lift wall panel D1 in progress.
P4 – Reservoir : Concreting for 3rd lift baffle wall panel C2 in progress.
P4 – Reservoir : Concreting for 1st lift baffle walls panel B4 & B5 in progress.
P4 – Reservoir : Concreting for columns in progress.
P4 – Reservoir : Mass concrete to 2mØ spare outlet pipe in progress.
P4 – Reservoir : Concreting for staircase No.2 in progress.
P4 – Reservoir : Rock breaking at CH220 for outlet chamber in progress.
P4 – Pipeline: Casting of anchor block for 2.0mØ and 2.5mØ outlet pipes at CH146 in progress.
P4 – Pipeline: Laying of 2500mm Ø outlet pipe in progress.
P4 – Main Access Road: Embankment filling at CH460 in progress.
P4 – Flood Detention Pond A : Construction of U drain in progress.
P4 – Flood Detention Pond B : Installation of U drain in progress.
P4 – Sg Perimbun Pipe Overcrossing: Construction of pile cap in progress.
P4 – Reservoir Platform Phase 1: Concreting for 1st lift wall in progress.
P4 – Reservoir Platform Phase 1: Concreting for base slab in progress.
P4 – Reservoir Platform Phase 1: Rock excavation for outlet pipe trench in progress.
P4 – Reservoir Platform Phase 2: Construction of berm drain in progress.
P4 – Pipeline: Casting of reinforced anchor block for inlet pipes at CH464 in progress.
P4 – Pipeline: Laying of 2500mm diameter outlet pipe at CH58 in progress.
P4 – Pipeline: Laying of 2000mm diameter outlet pipe at CH35 in progress.
P4 – Main Access Road: Embankment fill at CH380 in progress.
P4 – Flood Detention Pond B: Concreting for base slab of outlet structure in progress.
P4 – Sg Perimbun Pipe Overcrossing: Lean concrete for pile cap in progress.
P4 – Reservoir Platform Phase 1: Concreting for base slab Panel A2 in progress.
P4 – Reservoir Platform Phase 1: Concreting base slab for Panel B8 in progress.
P4 – Reservoir Platform Phase 1: Lean concrete for base slab Panel F1 in progress.
P4 – Reservoir Platform Phase 1: Incidental excavation for reservoir base slab in progress.
P4 – Reservoir Platform Phase 1: Rock excavations at outlet chamber in progress.
P4 – Pipeline: Laying of twin pipe 1900mm dia inlet pipe in progress.
P4 – Pipeline: Air test inspection in progress.
P4 – Main Access Road: Construction of berm drain at CH 400 (RHS) in progress.
P4 – Flood Detention Pond A: Fixing formwork for outlet wing wall slab in progress.
P4 – Flood Detention Pond A: Construction of roadside block drain in progress.
P4 – Sg Perimbun Pipe Overcrossing: PDA test for 500mm dia. spun pile in progress.
P4 – Flood Detention Pond A: Casting for inlet RC Sump in progress.
P4 – Reservoir Platform Phase 1: Rock excavation at CH320 in progress.
P4 – Reservoir Platform Phase 1: Lean concrete for reservoir base slab gridline 2-3/V-X in progress.
P4 – Reservoir Platform Phase 1: Fixing rebars for base slab gridline1-4/X-Z in progress.
P4 – Reservoir Platform Phase 1: Rock drilling prior to blasting work at CH 370 for 1900mm inlet pipe trench in progress.
P4 – Main Flood Detention Pond: Removing USM at CH680 in progress.
P4 – Main Flood Detention Pond: Cut to formation of slope at CH35 in progress.
P4 – Main Flood Detention Pond: Concreting wall for cascading drain join to inlet sump in
progress
P4 –Flood Detention Pond A: Construction of base slab of inlet structure in progress.
P4 –Flood Detention Pond A: Construction of block drain at CH 150 in progress.
P4 – Main Access Road: Filling embankment at CH290 – CH370 RHS in progress.
P4 – Sg Perimbun Overcrossing: Driving spun piles 250Ø for Cap 15 to Pile Cap 26 in progress.
P4 – Casting Yard: Casting 300mm PC block drain in progress.
P4 – Reservoir Platform Phase 1: Rock excavation at CH230 in progress.
P4 – Reservoir Phase 1: Lean concrete for subsoil drain at gridline 1a-1/Y-Z1 in progress.
P4 – Main Flood Detention Pond: Laying of 300mm PC block drain at CH350 in progress.
P4 –Flood Detention Pond A: Laying of crusher run on slope in progress.
P4 –Flood Detention Pond B: Construction of inlet structure no 1 in progress.
P4 –Flood Detention Pond B: Construction of 300mm PC block drain at CH160 in progress.
P4 – Main Access Road: Construction of berm drain at CH220 RHS in progress.
P4 – Main Access Road: Construction of cascade spillway at CH440 RHS in progress.
P4 – Sg Perimbun Pipe Bridge: Mackintosh probe test for pile cap at CH280 in progress.
P4 – Sg Perimbun Pipe Bridge: Preparation for load test for pun piles in progress.
P4 – Casting Yard: Casting of 300mm PC block drain in progress.
P4 – U-Drain 1800mm x 900mm: Construction of U-Drain at CH25 in progress.