P4 – Reservoir : Concreting for base slab of inlet valve chamber in progress.
P4 – Pipeline: Excavation at EKVE platform in progress.
P4 – Reservoir : Concreting for columns in progress.
P4 – Flood Detention Pond A : Construction of U drain in progress.
P4 – Reservoir Phase 1: Lean concrete for subsoil drain at gridline 1a-1/Y-Z1 in progress.
Dec 17
Nov 17
Oct 17
Sep 17
Aug 17
Jul 17
Jun 17
May 17
Apr 17
Mar 17
Feb 17
Jan 17

P4 – Reservoir : Casting of Roof Slab B15 in progress.

P4 – Reservoir : Casting of Wall I6 2nd lift in progress.

P4 – Reservoir : Casting of 1st lift columns in progress.

P4 – Inlet Overflow Structure : Casting of base slab in progress.

P4 – Inlet Overflow Structure : Casting of wall in progress.
.
.

P4 – Pipeline : Pipe laying on saddle supports in progress.

P4 – Drainage : Laying of PC block drains in progress.

P4 – Drainage : Construction of berm drain in progress.

P4 – Turfing: Turfing work in progress at Main Access Road area.

P4 – Material Delivery: Valves delivered at site and covered with canvas.











P4 – Reservoir : Casting of Roof Slab F7 in progress

P4 – Reservoir : Casting of Columns at Panel B14 in progress

P4 – Reservoir : Casting of Base Slab H6 in progress

P4 – Reservoir : Excavation and laying of subsoil drain in progress.

P4 – TNB Sub Station : Fixing of formworks for roof slab in progress

P4 – Guard House : Fixing of rebars for Base Slab in progress.

P4 – Switch House : Trench excavation in progress

P4 – Main Access Road : Earth filling in progress from CH250 to CH200.

P4 – Overflow Inlet Structure: Fixing of rebars for Base Slab in progress

P4 – Pipeline : Inlet pipes laying (Phase 1 & 2) crossing EKVE Highway in progress.

P4 – Pipeline Concrete surround for inlet pipelines for EKVE crossing in progress.












P4 – Reservoir : Casting of Baffle Wall F7 & F8 2nd lift in progress

P4 – Reservoir : Casting of Base Slab G7 in progress

P4 – Reservoir : Casting of Roof Slab A9 in progress

P4 – Reservoir : Casting of Inlet Valve Chamber L1 in progress

P4 – Main Access Road: Filling works (LHS) from CH250 – CH350 in progress.

P4 – Main Detention Pond: Casting of Wingwall Structure in progress.

P4 – Pipeline : Laying of horizontal bends 1900mmØ inlet pipes in progress.

P4 – Drainage: Construction of PC Block Drain in progress









P4 – Reservoir : Casting of Base Slab A15 in progress.

P4 – Reservoir : Casting of Wall F8 3rd lift in progress.

P4 – Reservoir : Casting of columns 2nd lift in progress.

P4 – TNB Substation : Incidental excavation for foundation in progress.

P4 – Main Access Road : Filling works in progress.

P4 – Pipe Overcrossing : Installation of Arch Beam for Pipe Bridge in progress.

P4 – Sg. Perimbun Pipe Overcrossing : Casting of Saddle Support in progress

P4 – Pipeline : Laying of pipes 2500mm diameter in progress from CH149.

P4 – Drainage : Construction of Berm Drain in progress at Main Access Road (RHS).

P4 – Drainage : Construction of U Drain 3600mm x 1800mm in progress.











P4 – Reservoir : Concreting for base slab C3 in progress.

P4 – Reservoir : Concreting for roof slab D4 & D5 in progress.

P4 – Reservoir : Concreting for 2nd lift wall I8 in progress.

P4 – Reservoir : Concreting for 3rd lift wall E4 in progress.

P4 – Reservoir : Concreting for column in progress.

P4 – Reservoir : Construction of outlet sump in progress.

P4 – Pipeline : Installation of 1900mmØ tee plain & flange ended pipe in progress.

P4 – Main Access Road : Embankment fill at CH380 in progress.

P4 – Main Flood Detention : Construction of roadside drain at CH20 in progress.

P4 – Sg Perimbun Pipe Overcrossing: Fixing rebar & formwork for saddle support in progress.











P4 – Reservoir : Concreting for 1st lift wall panel F4 in progress.

P4 – Reservoir : Concreting for 2nd lift baffle wall panel B3 in progress.

P4 – Reservoir : Concreting for 3rd lift baffle wall panel B7 in progress.

P4 – Reservoir : Concreting for roof slab C1 in progress.

P4 – Reservoir : Concreting for columns in progress.

P4 – Reservoir : Concreting for base slab of inlet valve chamber in progress.

P4 – Reservoir : Concreting for RC Chamber wall in progress.

P4 – Main Access Road : Construction of berm drain at CH300 in progress.

P4 – Sg Perimbun Pipe Overcrossing: Concreting for pier head in progress.

P4 – Pipeline: Excavation at EKVE platform in progress.











P4 – Reservoir : Concreting for 2nd lift baffle wall panel C8 in progress.

P4 – Reservoir : Concreting for base slab I15 in progress.

P4 – Reservoir : Concreting for columns in progress.

P4 – Reservoir : Fixing formwork for roof slab in progress.

P4 – Pipeline: Casting of thrust block for inlet pipe at CH725 in progress.

P4 – Pipeline: Laying of 3300mmØ RCP pipes in progress.

P4 – Pipeline: Laying of 1900mmØ inlet pipe at CH860 in progress.

P4 – Main Access Road : Embankment fill at CH420 in progress.

P4 – Main Access Road : Close turfing at slope CH420 in progress.

P4 – Sg Perimbun Pipe Overcrossing: Concreting for RC piers in progress.











P4 – Reservoir : Concreting for base slab panel F6 in progress.

P4 – Reservoir : Concreting for 2nd lift wall panel D1 in progress.

P4 – Reservoir : Concreting for 3rd lift baffle wall panel C2 in progress.

P4 – Reservoir : Concreting for 1st lift baffle walls panel B4 & B5 in progress.

P4 – Reservoir : Concreting for columns in progress.

P4 – Reservoir : Mass concrete to 2mØ spare outlet pipe in progress.

P4 – Reservoir : Concreting for staircase No.2 in progress.

P4 – Reservoir : Rock breaking at CH220 for outlet chamber in progress.

P4 – Pipeline: Casting of anchor block for 2.0mØ and 2.5mØ outlet pipes at CH146 in progress.

P4 – Pipeline: Laying of 2500mm Ø outlet pipe in progress.

P4 – Main Access Road: Embankment filling at CH460 in progress.

P4 – Flood Detention Pond A : Construction of U drain in progress.

P4 – Flood Detention Pond B : Installation of U drain in progress.

P4 – Sg Perimbun Pipe Overcrossing: Construction of pile cap in progress.















P4 – Reservoir Platform Phase 1: Concreting for 1st lift wall in progress.

P4 – Reservoir Platform Phase 1: Concreting for base slab in progress.

P4 – Reservoir Platform Phase 1: Rock excavation for outlet pipe trench in progress.

P4 – Reservoir Platform Phase 2: Construction of berm drain in progress.

P4 – Pipeline: Casting of reinforced anchor block for inlet pipes at CH464 in progress.

P4 – Pipeline: Laying of 2500mm diameter outlet pipe at CH58 in progress.

P4 – Pipeline: Laying of 2000mm diameter outlet pipe at CH35 in progress.

P4 – Main Access Road: Embankment fill at CH380 in progress.

P4 – Flood Detention Pond B: Concreting for base slab of outlet structure in progress.

P4 – Sg Perimbun Pipe Overcrossing: Lean concrete for pile cap in progress.











P4 – Reservoir Platform Phase 1: Concreting for base slab Panel A2 in progress.

P4 – Reservoir Platform Phase 1: Concreting base slab for Panel B8 in progress.

P4 – Reservoir Platform Phase 1: Lean concrete for base slab Panel F1 in progress.

P4 – Reservoir Platform Phase 1: Incidental excavation for reservoir base slab in progress.

P4 – Reservoir Platform Phase 1: Rock excavations at outlet chamber in progress.

P4 – Pipeline: Laying of twin pipe 1900mm dia inlet pipe in progress.

P4 – Pipeline: Air test inspection in progress.

P4 – Main Access Road: Construction of berm drain at CH 400 (RHS) in progress.

P4 – Flood Detention Pond A: Fixing formwork for outlet wing wall slab in progress.

P4 – Flood Detention Pond A: Construction of roadside block drain in progress.

P4 – Sg Perimbun Pipe Overcrossing: PDA test for 500mm dia. spun pile in progress.

P4 – Flood Detention Pond A: Casting for inlet RC Sump in progress.













P4 – Reservoir Platform Phase 1: Rock excavation at CH320 in progress.

P4 – Reservoir Platform Phase 1: Lean concrete for reservoir base slab gridline 2-3/V-X in progress.

P4 – Reservoir Platform Phase 1: Fixing rebars for base slab gridline1-4/X-Z in progress.

P4 – Reservoir Platform Phase 1: Rock drilling prior to blasting work at CH 370 for 1900mm inlet pipe trench in progress.

P4 – Main Flood Detention Pond: Removing USM at CH680 in progress.

P4 – Main Flood Detention Pond: Cut to formation of slope at CH35 in progress.

P4 – Main Flood Detention Pond: Concreting wall for cascading drain join to inlet sump in
progress
progress

P4 –Flood Detention Pond A: Construction of base slab of inlet structure in progress.

P4 –Flood Detention Pond A: Construction of block drain at CH 150 in progress.

P4 – Main Access Road: Filling embankment at CH290 – CH370 RHS in progress.

P4 – Sg Perimbun Overcrossing: Driving spun piles 250Ø for Cap 15 to Pile Cap 26 in progress.

P4 – Casting Yard: Casting 300mm PC block drain in progress.













P4 – Reservoir Platform Phase 1: Rock excavation at CH230 in progress.

P4 – Reservoir Phase 1: Lean concrete for subsoil drain at gridline 1a-1/Y-Z1 in progress.

P4 – Main Flood Detention Pond: Laying of 300mm PC block drain at CH350 in progress.

P4 –Flood Detention Pond A: Laying of crusher run on slope in progress.

P4 –Flood Detention Pond B: Construction of inlet structure no 1 in progress.

P4 –Flood Detention Pond B: Construction of 300mm PC block drain at CH160 in progress.

P4 – Main Access Road: Construction of berm drain at CH220 RHS in progress.

P4 – Main Access Road: Construction of cascade spillway at CH440 RHS in progress.

P4 – Sg Perimbun Pipe Bridge: Mackintosh probe test for pile cap at CH280 in progress.

P4 – Sg Perimbun Pipe Bridge: Preparation for load test for pun piles in progress.

P4 – Casting Yard: Casting of 300mm PC block drain in progress.

P4 – U-Drain 1800mm x 900mm: Construction of U-Drain at CH25 in progress.